United States v. Honeywell International, Inc.
United States v. Honeywell International, Inc.
Opinion of the Court
Before the Court are Defendants’ Motion for Summary Judgment at Docket 220 and Relators’ Motion for Partial Summary Judgment at Docket 225. The motions have been fully briefed;
This is the third time the Court has addressed dispositive motions in this case. The Ninth Circuit has twice, sent this case back to the district court following orders granting motions to dismiss based solely on the allegations pled by Relators.
BACKGROUND
In the late 1990s the Army sought to privatize the utilities at U.S. Army installations.
As part of the privatization initiative, beginning in 1999 the Fort Richardson Army base in Anchorage, Alaska (“FRA”) contemplated shutting down its central heating and power plant (“CHPP”) and instead buying its electricity from a commercial provider.
As the proposals were developed, there were extensive discussions between Honeywell’s engineers and the engineers at Huntsville about the basis, and reasonableness of certain calculations. Over time, these issues were resolved in multilateral meetings and exchanges. Honeywell submitted several revised drafts containing certain amended calculations during the course of these discussions.
Over the next few years, questions arose as to whether FRA could pay the contract amounts because its actual savings were less than projected.
DISCUSSION
I. Jurisdiction
The Court has jurisdiction pursuant to 28 U.S.C. § 1331 because Plaintiffs’ claims arise under the False Claims Act, 31 U.S.C. § 3729 et seq.
II. Standard for Summary Judgment
Federal Rule of Civil Procedure 56(a) directs a court to “grant summary judgment if the movant shows that there is no genuine dispute as to any material fact and the movant is entitled to judgment as a matter of law.” The burden of showing the absence of a genuine dispute of material fact initially lies with the moving party.
When considering a motion for summary judgment, a court views the facts in the light most favorable to the non-moving party and draws “all justifiable inferences” in the non-moving party’s favor.
To prevail on summary judgment, Relators must show that there is no genuine dispute of material fact as to each element of their claim and that they are entitled to judgment as a matter of law based on those undisputed facts.
III. Summary of Claims
This case arises in the context of a complex statutory, regulatory, and contractual framework. For clarity, the Court will summarize Relators’ theories before addressing the pending motions.
Relators seek to impose FCA liability based on a fraud-in-the-inducement theory.
As Relators themselves explain, the “savings guarantee” is derived from an equation.
Second, Relators now claim in their summary judgment briefing (although so far as the Court can discern, this allegation does not appear in their Second Amended Complaint (“SAC”)), that the “cost of energy savings guarantee [in the task orders] is demonstrably false as it excludes, for the post-project heat costs, the post-project/post-contract condition heat load costs for process loads and domestic hot water.”
Third, Relators contend that Honeywell’s “proposal documents knowingly and fraudulently and falsely represented that normal Department of Energy infiltration factors had been used,” but Honeywell had instead used an infiltration value that was “only two thirds of the ‘tight’ construction value.” Relators maintain that the use of the wrong infiltration value resulted in “a significant understatement of defendants’ post-project infiltration heat load requirement and grossly inflated energy savings.”
Fourth, Relators claim that Honeywell “failed to allow for adjustment of the baseline for buildings that were to be demolished” and that this resulted in an improper allocation of savings between Phase 1 and Phase 2 of the project.
Defendants argue that Relators have not and cannot produce any evidence that Honeywell “knowingly” made any false statements to the government, and that therefore Honeywell is entitled to summary judgment.
IV. The Government Knowledge “Defense”
Honeywell contends that one reason Re-
The Court rejects the premise underlying Relators’ first ai-gument as unsupported by the record. There is no evidence in the record to support Relators’ assertion that Honeywell knew there would be no savings from its proposed ECSMs. That assertion rests on the deposition testimony of Suzanne Wunsch, a Honeywell employee involved in the contract negotiations with the government in 2000,
Plaintiffs correctly observe that the Ninth Circuit has held that the fact that the “relevant government officials know of [a statement’s] falsity is not in itself a defense.”
First, government knowledge may be used to rebut the necessary scienter: If the contractor “so completely cooperated and shared all information” with the government, then the contractor “did not ‘knowingly submit false claims.”
Similarly, in Hooper v. Lockheed Martin Corp., the relator alleged that the contractor had used “defective testing' procedures.”
Second, government knowledge may “show that the contract has been modified or that its intent has been clarified, and therefore that the claim submitted by the contractor was not ‘false.’ ”
Several district courts have taken the same view, recognizing that the context of a statement can negate its apparent falsity. Thus, the district court in Butler found that the relator “did not provide legally sufficient evidence that, given the nature of the relationship between [the contractor] and the Army, any statements or claims made by [the contractor] were ‘false or fraudulent.’ ”
In affirming the district court’s directed verdict in Butler, the Ninth Circuit applied this same logic. In that case, the contractor had submitted a report that concluded that the helicopter radios “have been successfully demonstrated and are ready for production.” But in fact the radios had failed to meet certain contractual specifications. The Ninth Circuit held that because “the failure to meet specifications was detailed elsewhere in the report,” the “generalized statement with added details was not the type of [false] representation required by the statute.”
V. Specific Claims
A. Baseline Inclusion of Future Norp-Actual Costs of Electricity
Both the parties principally focus on Relators’ first claim: that Honeywell misrepresented projected savings by assessing the baseline as though FRA were already purchasing electricity on the commercial market.
But Relators have not presented any evidence that Honeywell possessed such knowledge at the time of the initial contracting in 2000. As discussed above, Ms. Wunsch’s statement that “everyone knew” that shutting down the CHPP would increase electricity costs does not establish that Honeywell knew its baseline was improper.
First, Honeywell assessed FRA’s energy usage based on fiscal years 1998 and 1999.
Honeywell’s proposals for Task Orders 8 and 9 each contained two proposed Energy Cost Savings Measures (ECSMs). First, Honeywell would install high-efficiency natural gas furnaces in each building and eliminate reliance on the CHPP for heating.
Of course, there was an additional consequence to shutting down the CHPP. Once the CHPP was shut down, FRA would need to purchase electricity from another source. Relators’ claim is that Honeywell’s projected savings number was “false” because Honeywell “improperly us[ed] the future commercial cost of purchasing electricity as the pre-contract/pre-project cost of electricity energy baseline.”
As Honeywell disclosed during a presentation with Army staff in February 2000 (several months before the task orders were issued), purchasing electricity commercially would cost more money than producing it at the CHPP. In that presentation, Honeywell indicated that the then-current costs associated with generating electricity at the CHPP were $3,652,591 per year, and that the cost to buy the same amount of electricity commercially would
When Honeywell submitted its formal proposals in July 2000 (Proposal # 3) and November 2000 (Proposal #4), it again indicated that the electricity baseline would be “adjusted” to account for the increased costs of purchasing electricity. Honeywell first calculated, “per the monthly plant operating reports,” the CHPP’s electrical production in megawatt-hours per year. It then added the electricity that FRA was currently purchasing to estimate CHPP’s total electricity requirement. Then, under the bolded subtitle “Electrical Baseline Adjustment,” Honeywell calculated how much it would cost to purchase the same amount of electricity commercially.
The record also demonstrates that Honeywell knew that the government also knew about the electrical baseline adjustment. As part of the ESPC process, Honeywell submitted its calculations to the Army Corps of Engineers for review and approval. Tim Brown, one of the Army engineers reviewing the proposal documents, specifically commented to Honeywell with regard to the Electrical Baseline Adjustment that “[t]he analysis should include supportive information to demonstrate the actual electrical charges after the CH & PP is shut down.”
Relators argue that other parts of Honeywell’s savings calculations show that it was misleading the government with regard to how it calculated the electricity costs. They note that one component of the savings guarantee for Task Order 9 was the “electrical savings” from shutting down the CHPP: The CHPP itself required electricity to power lights and various mechanical components in the CHPP build
The Court agrees with Honeywell that, as a matter of law, its extensive disclosures to the government prior to the task orders’ finalization preclude Relators’ FCA claim.
Moreover, Honeywell’s repeated disclosures to the government about the “Electrical Baseline Adjustment” preclude a finding that any statement in that regard was known to be false by Honeywell when made.
In light of the lack of evidence that Honeywell had any knowledge that the baseline was improper, and in light of the overwhelming evidence that Honeywell fully disclosed the baseline adjustment and the fact that its energy savings calculations did not account for the increased costs of electricity, the Court finds that there is no genuine dispute as to any material fact with regard to either the “falsity” of Honeywell’s savings estimates or Honeywell’s knowledge of any alleged falsity. Accordingly, Honeywell is entitled to judgment as a matter of law on this claim. FCA liability cannot be premised on Honeywell’s electrical baseline adjustment.
B. Heat Costs
Relators assert that Honeywell “improperly omitted the process loads and domestic hot water loads from the post-project heat costs.”
Relators suggest that Honeywell can be charged with “knowingly” submitting false claims because it failed to use due diligence to verify its submissions. But this argument fails for two reasons. First, Relators have not proffered any evidence that Honeywell did not use due diligence; they do not discuss at all what processes Honeywell used (or did not use) to verify the submissions. They only repeatedly state what they view as mistakes in Honeywell’s calculations. But if the fact of a mistake was sufficient to charge a sophisticated contractor with knowledge of that mistake, then the “knowingly” element of the False Claims Act would be vitiated entirely: every mistake that a contractor made in submitting claims would be transformed into a lie. This is plainly not the law, as “the common failings of engineers and other scientists are not culpable under the Act.”
In reversing a district court’s grant of the health insurers’ motion to dismiss, the Ninth Circuit concluded that the alleged “one-sided retrospective review” was not a good faith attempt to verify the accuracy of the diagnosis codes, and thus, if the allegations were true, the insurers had falsely certified to the government that its submissions were “accurate, complete and truthful” based on, the “best knowledge, information, and belief’ of the insurers.
Here, Relators have not produced any evidence from which a jury could reasonably infer that.Honeywell had implemented a one-sided review that was designed to correct only certain errors. Even assuming that the omission of the process and hot-water loads was an error, the fact that an error occurred, standing alone, does not establish that Honeywell “knowingly” committed the error, even under a “reckless disregard” standard. Honeywell has met its burden of “showing ... that there is an absence of evidence to support [Relators’] case,” and it is accordingly entitled to judgment as a matter of law on this claim.
• C. Infiltration Rates
Relators alleged in their SAC that Honeywell “deliberately overwrote” software distributed by the Department of Energy (“DOE”) for calculating a structure’s passive heating loss.
As part of its contract proposals, Honeywell estimated the infiltration rates that would exist during the period of contract performance. These infiltration rates were used to project the costs of providing gas heat to each building.
Relators also alleged in their SAC that Honeywell had misrepresented an infiltration rate of 0.15 as a “normal” rate.
Relators instead now argue that Honeywell knew that the 0.15 ACH infiltration rates were impossible to achieve. They base this claim on comments that Steve Craig, a Honeywell executive, made during a July 25, 2006 conference call, six years after the task orders were issued. According to Relator Berg’s recollection in 2010, during that 2006 conference call Mr. Craig “told everyone present that Honeywell knew the project would never save energy and was not viable from the very beginning.”
Relators also cite to Mr. Smith’s declaration to support this claim.
Although the Court views the evidence in the light most favorable to Rela-tors and draws all reasonable inferences in their favor, those “inferences are limited to those upon which a reasonable jury might return a verdict.”
Mr. Berg’s 2010 declaration is at odds with the extensive contemporaneous documentary evidence and is unsupported by any other evidence. It omits the essential
Honeywell also argues that it is entitled to summary judgment on this claim because it disclosed the infiltration rates it projected to the government.
D. Adjustment for Destruction of Buildings
Relators assert that “Honeywell failed to allow for adjustment of the baseline for buildings that were to be demolished.”
VI. Relators’ Opposition
Although Relators do not press the theory in their own motion for summary judgment, in their opposition to Honeywell’s motion they revive their claim that Honeywell misrepresented the contracts as “legal” under the relevant ESPC statutes and regulations.
CONCLUSION
Upon review of the extensive exhibits and portions thereof cited by the parties, and drawing all reasonable inferences in Relators’ favor, the Court concludes that Defendants have met their burden to show that there is no genuine dispute as to any material fact and that Defendants are entitled to judgment as a matter of law. As detailed above, Relators have not presented sufficient evidence from which a reasonable jury could return a verdict in their favor. Defendants have demonstrated that Relators cannot show that a triable issue exists as to whether Honeywell made a false statement in 2000 which it knew to be false at that time. For this reason, Honeywell is entitled to summary judgment on Relators’ fraud-in-the-inducement claim. Because the Court grants summary judgment to Defendants, it will deny Relators’ motion for partial summary judgment.
Therefore, IT IS ORDERED that Defendants’ Motion for Summary Judgment at Docket 220 is GRANTED. Relators’ Motion for Partial Summary Judgment at Docket 225 is DENIED.
All other pending motions are DENIED as moot. The final pretrial conference scheduled for January 9, 2017 and the trial scheduled to commence January 23, 2017 are VACATED. The Clerk of Court is directed to enter a judgment accordingly.
. See Docket 222 (Defs.' Mem.); Docket 303-1 (Relators’ Unredacted Opp.); Docket 258 (Defs.’ Reply); Docket 302-1 (Relators’ Corrected Mem.); Docket 238 (Defs.’ Opp.); Docket 276 (Relators’ Corrected Reply). Rela-tors also filed a Notice of Supplemental Authority at Docket 292.
. See Docket 287 (Hr’g Mins.); Docket 296 (Hr’gTr.).
. See 580 Fed.Appx. 559 (9th Cir. 2014); 502 Fed.Appx. 674 (9th Cir. 2012).
. Docket 319-1 at 4.
. Docket 223-18 at 2.
. Docket 223-18 at 2; 42 U.S.C. § 8287 et seq.
. See Docket 223-18 at 2.
. 42 U.S.C. § 8287(a)(2)(B).
. Id.
. Docket 319-1 at 4 (Paul Knauff Aug. 21, 2002 Information Paper).
. Docket 223-18 at 6 (Col. Mark C. Nelson Mem.).
. See Docket 225-1 (IDIQ) at 1-3.
. Docket 225-1 at 3, 103-04 (ordering clause).
. See Docket 225-5 (Proposal # 3); Docket 265-5 (Proposal # 4). The two proposals were similar in their recommended improvements, but each concerned a distinct group of buildings on FRA.
. See Docket 223-18 at 56 (Nov. 29, 1999 email from Suzanne Wunsch) (inquiring whether FRA intended to close CHPP); Docket 265-10 (Jan. 6, 2000 1ST Presentation) at 13 (stating Honeywell’s assumption that FRA would “convert from central to distributed heating); Docket 265-12 (Feb. 29, 2000 1ST Presentation) at 12 (identifying increased electrical costs from shutting CHPP); Docket 265-12 at 14 (identifying ancillary savings from shutting down CHPP).
. See, e.g., Docket 241-30 at 32-36; Docket 223-22 at 4-10; Docket 223-23 at 10-34.
. See, e.g., Docket 241-26 at 9-34; Docket 223-2 at 32-35.
. Docket 225-2 at 1-3; Docket 225-3 at 1-3.
. See Docket 319-3 at 2.
. See, e.g., Docket 223-38 at 45 (Simmons Mem.). See 31 U.S.C. § 1341.
. Docket 223-42 at 2-20; see also Docket 265-21 (Bridgeman Dep.) at 3. This renegotiated contract is referred to as “Mod II." It combined the two task orders into a single contract. Honeywell and the government had previously modified Task Order 8 to adjust the buildings within its scope. See Docket 223-41 at 14 (documenting “modification 01”).
. See Docket 223-45 at 2.
. See, e.g., Docket 223-45 at 4-5.
. See Docket 1. The operative complaint for purposes of these motions is the Second Amended Complaint (SAC) at Docket 101, filed Aug. 13, 2014.
. Celotex Corp. v. Catrett, 477 U.S. 317, 325, 106 S.Ct. 2548, 91 L.Ed.2d 265 (1986).
. Anderson v. Liberty Lobby, Inc., 477 U.S. 242, 248-49, 106 S.Ct. 2505, 91 L.Ed.2d 202 (1986).
. Id. (citing First National Bank of Arizona v. Cities Service Co., 391 U.S. 253, 88 S.Ct. 1575, 20 L.Ed.2d 569 (1968)).
. Id. at 255, 106 S.Ct. 2505 (citing Adickes v. S.H. Kress & Co., 398 U.S. 144, 158-59, 90 S.Ct. 1598, 26 L.Ed.2d 142 (1970)).
. Flores v. City of San Gabriel, 824 F.3d 890, 897 (9th Cir. 2016) (citing Ctr. for Bio-Ethical Reform, Inc. v. LA. Cnty. Sheriff Dep't, 533 F.3d 780, 786 (9th Cir. 2008)).
. Anderson, 477 U.S. at 248, 106 S.Ct. 2505.
. Id. at 249, 106 S.Ct. 2505.
. Plaintiffs do not seek summary judgment on damages, but damages are not an element of an FCA claim. See United States ex rel. Hagood v. Sonoma Cnty. Water Agency, 929 F.2d 1416, 1421 (9th Cir. 1991) (citing Rex Trailer Co. v. United States, 350 U.S. 148, 152-53 & n.5, 76 S.Ct. 219, 100 L.Ed. 149 (1956)).
. In re Oracle Corp. Sec. Litig., 627 F.3d 376, 387 (9th Cir. 2010).
. Id.
. See Docket 101 (SAC) at ¶¶ 1-3; Docket 225 at 37 ("Relators’ claims are grounded on a fraud in the inducement theory of liability”).
. See United States ex rel. Hendow v Univ. of Phoenix, 461 F.3d 1166, 1174 (9th Cir. 2006).
. See Docket 101 (Second Amended Complaint ("SAC”)) at ¶1¶ 43, 74; Docket 302-1 (Relators' Mot.) at 2 (“Honeywell obtained [the contracts] ... through a materially false guarantee of cost-of-energy savings.... ”).
. See Docket 303-1 (Relators’ Unredacted Opp.) at 45.
. See Docket 303-1 at 27-28.
. Docket 225-2 at 9 (Task Order 8); Docket 225-3 at 9 (Task Order 9). Honeywell’s 30(b)(6) witness testified that the “back-up data” referred to the proposals. See Docket 265-19 (Rogan Dep.) at 3.
. Relators’ SAC contains additional allegations of improper baseline and costs calculations, see, e.g., Docket 101 at ¶ 25 (allegations of false weather data), but they have not advanced those allegations at this stage in the proceedings. In their opposition to Honey
. Docket 101 at ¶ 33.
. Docket 302-1 at 3.
. Docket 225 at 4.
. Docket 101 at ¶ 24; Docket 302-1 at 4; see also Docket 101 at ¶ 79(A).
. Docket 302-1 at 4; see also Docket 101 at ¶ 79(D). The project was divided into two phases. See Docket 223-22 at 6. "Phase 1” was "Proposal # 3" and became Task Order 8. "Phase 2” was "Proposal # 4" and became Task Order 9.
. See Docket 222 at 33-34.
. The Ninth Circuit rejected Honeywell’s efforts to assert a government knowledge defense at the motion to dismiss stage, noting that “[t]he possibility that Honeywell may prevail at a later stage of this litigation under the so-called government knowledge defense to FCA liability does not support the conclusion that the Relators' complaint cannot be saved by an amendment.,.. [That ‘defense’] is therefore appropriate ‘at the summary judgment stage or after trial.' ” Berg v. Honey
. See Docket 222 at 36-37.
. Docket 258 at 10.
. Docket 303-1 at 33.
. Docket 303-1 at 37.
. See Docket 302-1 (Relators’ Mot,) at 18, Ms. Wunsch now goes by Ms. Johnson, but consistent with the documents in evidence and the parties’ briefing, the Court will refer to her as Ms. Wunsch.
. See Docket 265-18 (Wunsch Dep.) at 5.
. Docket 265-18 at 4.
. Docket 265-18 at 4. There is a dispute as to whether the Army actually directed Honeywell to make such an assumption, but as explained below, that dispute is immaterial. See infra note 96
. See infra note 99 and sources cited therein.
. See United States ex rel. Hagood v. Sonoma Cnty. Water Agency (Hagood I), 929 F.2d 1416, 1421 (9th Cir. 1991) (citing United States v. Ehrlich, 643 F.2d 634, 638-39 (9th Cir. 1981)).
. Id. at 1421.
. United States ex rel. Butler v. Hughes Helicopters, Inc., 71 F.3d 321, 327 (9th Cir. 1995); see also Hooper v. Lockheed Martin Corp., 688 F.3d 1037, 1051 (9th Cir. 2012); Wang v. FMC Corp., 975 F.2d 1412, 1421 (9th Cir. 1992), abrogated on other grounds, United States ex rel. Hartpence v. Kinetic Concepts, Inc., 792 F.3d 1121 (9th Cir. 2015).
. Butler, 71 F.3d at 324.
. Id.
. Id.
. Id. at 327.
. Id. at 328.
. 688 F.3d 1037, 1050 (9th Cir. 2012).
. Id. at 1050-51.
. Id. at 1051.
. United States ex rel. Kreindler& Kreindler v. United Techs. Corp., 985 F.2d 1148, 1157 (2d Cir. 1993).
. United States ex rel. Durcholz v. FKW Inc., 189 F.3d 542, 545 (7th Cir. 1999); see also United States ex rel. Burlbaw v. Orenduff, 548 F.3d 931, 952 n.19 (10th Cir. 2008).
. 1993 WL 841192 at *14 (C.D. Cal. Aug. 25, 1993) (granting directed verdict for defendant), aff’d 71 F.3d 321 (9th Cir. 1995).
. 706 F.Supp. 795, 809-10 (D. Utah 1988). Boisjoly arose in the context of a motion to dismiss. While the Ninth Circuit has rejected attempts to employ government knowledge at that stage, it has characterized Boisjoly as “defensible on its facts.” Hagood I, 929 F.2d at 1421.
.Butler, 71 F.3d at 328.
. See Docket 258 at 10.
. See, e.g., Docket 222 (Honeywell’s Mem.) at 13-18; Docket 302-1 (Relators’ Mem.) at 9-14.
. United States ex rel. Hendow v. Univ. of Phoenix, 461 F.3d 1166, 1174 (9th Cir. 2006) (quoting United States ex rel. Hopper v. Anton, 91 F.3d 1261, 1267 (9th Cir. 1996)).
. Some evidence suggests that there actually were substantial energy savings as a result of the ESPCs. See, e.g., Docket 223-50 at 21-23 (Simmons June 27, 2008 Mem.). But whether savings were in fact realized from the project does not impact whether there was fraud in the inducement, and the Court need not decide the issue.
. See supra section IV.
. See Docket 53-1 (Berg Decl.) at 22, ¶ 44,
. See Docket 259-1 at 94 (Berg Dep.) (“As far as I know, as far as I can recollect, the telephone conference centered on heating and not on electrical.”).
. See infra section V.C.
. See, e.g., Docket 302-1 at 15-16, 21-22.
. Cf. Hopper, 91 F.3d at 1268 ("Hopper argues that past regulatory noncompliance creates an inference that the School District lied when certifying future compliance. This is not sufficient evidence to establish knowing fraud under the [False Claims] Act.”).
. See, e.g., Docket 265-5 at 39.
. See Docket 265-5 at 150 (Proposal # 4).
. This percentage varied throughout the various proposals, apparently based on input from FRA employees. See Docket 265-5 at 147 (“Plant Steam to Heating was recalculated using the formula provided by DPW”),
. In Proposal # 4, Honeywell estimated this cost at $2,300,582 per year for electricity and at $2,214,681 for heat. Docket 265-5 at ISO-51. In Proposal # 3, Honeywell had estimated $2,329,158 for electricity and $2,288,850 for heat. Docket 223-22 at 6.
. Docket 265-2 at 23 (Proposal # 3).
. See Docket 265-2 at 27. The project was divided into two phases, with one-half of the heat costs assigned to each phase. See Docket 223-22 at 6.
. See Docket 223-20 at 161.
. Docket 223-20 at 163.
.See Docket 225-2 (Task Order 8) at 9; Docket 225-3 (Task Order 9) at 9. Task Order 8’s savings are the sum of the savings from each proposed ECSM, $235,709 for the first, Docket 223-20 at 28, and $228,530 for the second, Docket 223-20 at 164. Task Order 9's savings are the sum of the savings from each ECSM, $522,941 for the first, Docket 265-5 at 54, and $57,748 for the second, Docket 223-26 at 46. Task Order 9 included additional “electric savings” of $245,681. Honeywell disclosed these savings separately, and reported that “These savings are a result of a phone conversation with Mr. Paul Knauff [an FRA employee] on November 8, 2000.” Docket 265-5 at 54; see also Docket 265-5 at 153 (explaining the calculations for these savings). This item of the savings calculation is not directly at issue in this case, though it is discussed in more detail below. The total savings projected for Task Order 9 was the sum of these three numbers, $826,370. There is a $2,000 discrepancy in the projected savings in the issued task order, see Docket 225-3 at 9 (estimating $828,370), but that discrepancy
. Docket 302-1 at 3.
. Compare Docket 265-1 (Fuel Sensitivity Analysis) at 1, with Docket 225-2 (Task Order 8) at 9.'
. Docket 302-1 at 35.
. Relators identify a genuine dispute of fact as to whether Paul Knauff, an FRA employee, instructed Honeywell to account for the increased costs of electricity in this matter. See Docket 241 (Relators' Opp.) at 18-19; Docket 241-5 (Knauff Dep.) at 3, Paul Knauff's own deposition testimony directly contradicts Honeywell’s 30(b)(6) witness, Richard Rogan. See Docket 241-1 (Rogan Dep.) at 2-3. Separate evidence might also support Honeywell’s version of events if this case went to trial: an Army Audit Agency interview from 2003 indicates that Paul Knauff recalled that “electricity was never included in the project” and that "Honeywell briefed that information upfront when the project first started.” Docket 319-2 at 5. But this statement is ambiguous as to what it meant that "electricity was never included,” and the Court assumes, as it must for purposes of this motion, that Mr. Knauff was not referring to the baseline. While such an instruction, would have bolstered Honeywell's reliance on the government knowledge to defeat Relators’ claims, it is not necessary to it. The Court assumes for puiposes of this motion that Mr. Knauff did not so instruct Honeywell, but the fact turns out to be immaterial: As the discussion in this section shows, Honeywell’s repeated disclosures informed the government exactly how Honeywell was calculating the baseline and the savings, and so its reason for doing so in the first instance does not affect whether its baseline was “false” or whether any falsity was known to Honeywell at the time.
. Docket 265-12 at 12 (Feb. 29, 2000 1ST Meeting Powerpoint).
. Docket 265-12 at 13.
. As a consequence of this adjustment, the baseline was calculated as if FRA had stopped using the CHPP to produce electricity, but was still using it to produce heat. Thus, the ESPCs could account for the ancillary savings from shutting down the CHPP, such as avoided labor and maintenance costs, even though it did not account for the increased cost of electricity. Honeywell may have concluded that FRA was planning exactly this, since the privatization efforts were distinct from the ESPC. See Docket 225-8 (AAA Lessons Learned) at 13 (noting that FRA personnel "were under the impression the Army was getting out of the utility business, no matter what the cost, whether by privatizing or by the use of [ESPCs]”); Docket 223-41 at 7 (Charles Baus March 29, 2000 email) (discussing electrical privatization); Docket 223-38 at 44 (Simmons April 10, 2003 Mem.) ("USARAK [U.S. Army, Alaska] was proceeding with the understanding that the electrical system was going to be privatized.”); Docket 319-2 at 2 ("At the time the project started, it was understood that electricity was to be purchased.”); Docket 319-2 at 6 ("The intent of the ESPC was not to replace the power plant, but to replace the steam distribution system.”).
. Docket 265-5 at 42; see also 225-5 at 5.
. Docket 223-2 at 33-34.
. See supra note 92. This component is not directly at issue, and is distinct from the electrical baseline adjustment.
. See Docket 302-1 at 13.
. See Docket 265-5 at 54; see abo Docket 265-5 at 153 (explaining the calculations for these savings). Cf. supra note 96 (detailing a dispute regarding a different instruction Honeywell contends Paul ¡Knauff gave).
. Relators have focused substantial briefing on whether the baseline was permissible or proper under the applicable statutes and regulations. But FCA liability does not attach to mere regulatory violations. See United States ex rel. Hendow v. Univ. of Phoenix, 461 F.3d 1166, 1171 (9th Cir. 2006). Thus, the Court need not decide whether or not the applicable regulations allowed an ESPC to account for the electricity costs in the manner these ones did. See abo infra Part IV.
. Relators also argue that these numbers were inaccurate for other distinct reasons. The Court addresses these allegations in the pages below.
. Cf. United States ex rel. Butler v. Hughes Helicopters, Inc., 71 F.3d 321, 328 (9th Cir. 1995) (holding that "a generalized statement with added details was not the type of representation required by the statute”).
. Contemporaneous emails between Honeywell employees also rebut any suggestion that Honeywell "knew” the baseline to be "false.” In March 2000, Honeywell’s Charles Baus emailed other Honeywell employees working on the FRA project, and stated that "we will be using the MLP Rate # 760 to determine the baseline electric rate. Again, the philosophy being that the electric system 'privatization' is proceeding without us and this is what they will be paying." Docket 223-41 at 7.
. Butler, 71 F.3d at 327-28.
. Docket 302-1 at 23.
. Docket 238 at 29.
. See, e.g., Docket 302-1 at 38. The extent to which such an omission was wrongful is disputed. Compare Docket 238 (Honeywell Opp.) at 29 ("Relators' own expert agrees ... that ESPC baseline calculations should never include process loads.”), with Docket 302-1 at 36 (arguing that "Honeywell dropped the post-retrofit domestic hot water and process loads” in an attempt "to yield the false energy savings guarantee”).
. See Docket 302-1 at 39 ("Honeywell’s various and creative methods in cherry-picking values and strategically inserting or deleting them from baseline calculations was conscious and deliberate.”).
. United States ex rel. Anderson v. N. Telecom, Inc., 52 F.3d 810, 815 (9th Cir. 1995) (quoting Wang v. FMC Corp., 975 F.2d 1412, 1421 (9th Cir. 1992)).
. See Docket 302-1 at 39 (citing United States v. United Health Insurance Co., 848 F.3d 1161, 1166-67, 2016 WL 7378731 at *2 (9th Cir. Aug. 10, 2016), as amended on denial of r’hrg en banc).
. See 848 F.3d at 1161-67, 2016 WL 7378731 at *2.
. United Healthcare, 848 F.3d at 1174-75, 2016 WL 7378731 at *9.
. See United Healthcare, 848 F.3d at 1168—69, 2016 WL 7378731 at *4.
. Celotex Corp. v. Catrett, 477 U.S. 317, 325, 106 S.Ct. 2548, 91 L.Ed.2d 265 (1986).
. Infiltration rates refer to the “flow rate of outside air into a building” and are a measurement of heating efficiency. See Docket 222 (Honeywell’s Mem.) at 39.
. Docket 101 at ¶ 79(A).
. See Docket 84.
. See Berg v. Honeywell Intern., Inc., 580 Fed.Appx. 559, 559-60 (9th Cir. 2014).
. See, e.g., Docket 101-2 (EMP2 Audit) at 44.
. Docket 302-1 at 31.
. See Docket 223-61 (Berg Dep.) at 27-29.
. E.g., Docket 223-23 at 11. "ACH” refers to "air changes per hour,” reflecting the insulation effectiveness of a building.
. Docket 265-16 (Honeywell Executive Briefing Powerpoint) at 4.
. See Docket 223-54 (DOE Manual) at 25 (recommending rates of 0.3 ACH for “tightly constructed buildings”).
. Docket 101 at ¶ 24 ("The proposal documents knowingly and fraudulently and falsely represented that normal Department of Energy infiltration factors had been used.”)
. See Docket 223-61 (Berg Dep.) at 28-29.
. See, e.g., Docket 223-27 at 7.
. Docket 223-61 at 28.
. Docket 53-1 (Berg Decl.) at 22, ¶ 44.
. Docket 53-21 (Tyler Aug 7, 2006 Mem.) at 2-3.
. Docket 53-21 at 3 (emphasis added).
. See Docket 302-1 at 31-32.
. Docket 52 (Smith Decl.) at 13, ¶ 30.
. United States ex rel. Anderson v. N. Telecom, Inc., 52 F.3d 810, 815 (9th Cir. 1995) (citing T.W. Elec. Servs. Inc. v. Pac. Elec. Contractors Ass'n, 809 F.2d 626, 630-31 (9th Cir. 1987)).
. See, e.g., N. Telecom, 52 F.3d at 815 (“[P]roof of mistakes ‘is not evidence that one is a cheat,’ and 'the common failings of engineers and other scientists are not culpable under the Act.’ ”) (quoting Wang v. FMC Corp., 975 F.2d 1412, 1420-21 (9th Cir. 1992)).
. Anderson v. Liberty Lobby, Inc., 477 U.S. 242, 252, 106 S.Ct. 2505, 91 L.Ed.2d 202 (1986).
. See Docket 222 at 39-40; Docket 223-28 at 7 (Proposal # 4); Docket 265-20 (Dalsfoist Dep.) at 7 ("The infiltration rates were provided to us.”).
. Docket 302-1 at 4.
. Relators' briefing does not meaningfully address this issue, referencing the omission only in a few parentheticals. See Docket 302-1 at 32, 34. Relators do not raise the issue again in their reply or their opposition to Honeywell's summary judgment motion.
. United States ex rel. Hendow v. Univ. of Phoenix, 461 F.3d 1166, 1174 (9th Cir. 2006) (quoting United States ex rel. Hopper v. Anton, 91 F.3d 1261, 1267 (9th Cir. 1996)); see also N. Telecom, 52 F.3d at 815.
. See Docket 303-1 at 13.
. E.g., United States ex rel. Hendow v. Univ. of Phoenix, 461 F.3d 1166, 1174-75 (9th Cir. 2006) (finding a plausible FCA claim premised on knowingly false assurances that the contractor would follow the law).
. Hagood II v. Sonoma County Water Agency, 81 F.3d 1465, 1477 (9th Cir. 1996) (emphasis in original).
. See United States ex rel. Becker v. Westinghouse Savannah River Co., 305 F.3d 284, 288 (4th Cir. 2002) (noting that the government “had at least as much knowledge” as the contractor-defendant "regarding Congressional authority for the [challenged conduct]”).
. United States ex rel. Hixson v. Health Mgmt. Sys., Inc., 613 F.3d 1186, 1190 (8th Cir. 2010).
Reference
- Full Case Name
- UNITED STATES of America, EX REL., Thomas A. BERG, Timothy A. Berg, Ryne J. Linehan, Nayer M. Mahmoud, and Stanley E. Smith v. HONEYWELL INTERNATIONAL, INC., and Honeywell, Inc.
- Status
- Published