Clark Const. Co. v. STATE OF ALA. HWY. DEPT.
Clark Const. Co. v. STATE OF ALA. HWY. DEPT.
Opinion
Clark Construction Company, Inc., a pre-qualified contractor with the Alabama Highway Department (appellee), submitted its bid on a bridge construction project in Mobile County upon notice from the department. Clark's bid, at submission, indicated a total amount of $1,119,609. Under one particular item of its bid, Item No. 10 (508B-00), Steel Bridge Superstructure, Clark listed in figures under "Amount Bid" the sum of $368,000. However, for the same item under "Item With Unit Price Written In Words," Clark inserted the words "Three Hundred Sixty Eight" ($368.00) immediately before "Dollars," mistakenly deleting the word "Thousand."
Clark's bid was announced at the total of $1,119,609. The Alabama Highway Department, however, computed Clark's bid by referring to the written words "Three Hundred Sixty Eight" ($368.00) for Item No. 10, rather than the figure $368,000, on the basis of section
The Alabama Highway Department issued its low bid sheet dated December 17, 1982, showing Clark to be low bidder at $816,977.60, some $273,405 below the next lowest bid. On December 18, 1982 Clark was informed that it had been listed as low bidder. Clark, knowing the bid of "New Mc" had preliminarily been announced as lowest, realized there was an error in its bid. The following Monday Clark called the department, inquired as to the error, and was informed of the discrepancy in Item No. 10.
Clark asked permission to withdraw its bid on the basis of the mistake but the department refused to permit the bid to be withdrawn; whereupon, Clark refused to accept the job, and the department declared Clark's $10,000 bid bond to be forfeited.
On the basis of its mistake, i.e. discrepancy between the words and figures in Item No. 10 of its bid, and the above-stated events, Clark filed suit to have its bid rescinded and its bid bond returned. On the basis of section
It is Clark's contention that its appeal does not involve the interpretation or construction of section
In support of its argument, Clark relies mainly on the Alabama cases of Ex parte Perusini Construction Co.,
In the recent case of Montgomery Bridge Engineering, Inc.v. State Highway Department,
We found the legislative intent that section
The facts of Montgomery Bridge can be distinguished from the facts of the present case. In Montgomery Bridge the contractor did not attempt to rescind its contract because of the mistake made in the bid. Instead, it accepted the award of the contract based on its bid, which contained a mistake causing the contract price to be considerably less than intended, while at the same time seeking relief from the mistake by trying to force the state highway department to allow it to correct its mistake (i.e. revise the bid upward) in spite of the provisions of section
The difference in the present case is that low bidder Clark is not attempting to correct its bid. Instead, it seeks to merely have the courts excuse its mistake so that it will not be penalized by the forfeiture of its $10,000 bid bond, as is required under section
After having considered the facts of the instant case, the case authority cited by counsel, and the statutory scheme applicable to bids on public works contracts, we are of the opinion that the equitable doctrine relied upon in Perusini is not here applicable. Several factors lead us to this result. First of all, the statutory scheme dealing with public works contracts which was enacted after Perusini is comprehensive.See sections
In light of the above reasoning, we find that the trial court did not err in denying rescission and upholding forfeiture of Clark's bond. The cause is due to be affirmed.
AFFIRMED.
All the Judges concur.
Case-law data current through December 31, 2025. Source: CourtListener bulk data.