Zeigler v. Blount Bros. Const. Co.
Zeigler v. Blount Bros. Const. Co.
Opinion
This is an appeal from the grant of motions to dismiss filed by the defendants. We affirm.
The plaintiffs brought this action seeking to represent a class of persons who purchase electric power from Alabama Power Company (APCO). The action is grounded upon the failure in 1975 of the Walter Bouldin Dam which is located on the Coosa River in Elmore County, and which is part of the hydroelectric generating system of APCO. In their complaint the plaintiffs alleged that during 1963 or 1964 the defendant *Page 1165 Blount Brothers Construction Company (Blount) as general contractor agreed with APCO to construct Walter Bouldin Dam. The defendant, Southern Services, Inc., allegedly prepared the plans and specifications for the dam. Harbert Construction Company (Harbert), another defendant, was a sub-contractor for the powerhouse excavation and embankments, and Harry Hendon Associates (Hendon), another co-defendant, contracted with APCO to furnish inspections and to advise of possible construction defects. The complaint alleged that Southern Services improperly designed and prepared the plans and specifications, and that Blount and Harbert breached their contracts by failing to construct the dam in accord with the plans and specifications, causing it to collapse. Hendon's inspections, it further alleged, did not detect the deficiencies which resulted in the collapse. These failures, the plaintiffs continued, resulted in APCO, under Alabama law, Public Service Commission's regulations, and the "fuel adjustment clause," increasing the price it charged its customers proportionately by the price it was required to pay for electricity it otherwise would have generated using Walter Bouldin Dam.
The complaint as amended asserted three separate theories on which relief was based: (1) equitable subrogation; (2) third-party beneficiary principles; and (3) negligence. We shall treat these seriatim.
1. Equitable subrogation.
When the plaintiffs were required to pay the increased electricity rates passed on to them under the "fuel adjustment clause," which is a part of the general rate schedule for APCO, this, they contend, enabled them to be subrogated to the rights of Alabama Power Company to claim those increases in rates allowed by the Public Service Commission. In short, by paying the increased rate, it is alleged, the plaintiffs paid for APCO's injury and stand in APCO's shoes. APCO cannot make any claim, it is stated, because APCO has passed these "damages" on to the ultimate consumer.
While we agree with the plaintiffs' general statement that Alabama recognizes the doctrine of equitable subrogation, we must also note that its application is dependent upon the facts of the particular case and is not a matter of strict right.Jefferson Standard Life Ins. Co. v. Brunson,
We have been cited to nothing which convinces us of the soundness of either of these two propositions. We cannot determine from either the record or the briefs that the rate increase in question equated the damages recoverable in APCO's separate action. Nor is there any basis indicated for concluding that APCO cannot recover those compensatory damages in that action. See Prestwood v. Carlton,
2. The third-party beneficiary issue.
It is well-established in this jurisdiction that one who seeks recovery in contract as a third-party beneficiary must establish that the contract was intended for his direct, as opposed to incidental, benefit. Anderson v. Howard Hall Co.,
3. Negligence.
The gist of plaintiffs' negligence action is that these defendants owed a duty of care to the plaintiffs because the defendants could have anticipated that the collapse of the Bouldin Dam would cause subscribers to pay increased utility bills. They cite, inter alia, the case of Havard v. Palmer Baker Engineers, Inc.,
Havard dealt with a contract between an engineering firm and the City of Mobile. Under that contract the firm was to make annual inspections and recommendations pertaining to the safe operation of a vehicular tunnel operated by the city. This Court held that a duty to the plaintiff was alleged in a complaint which charged that the defendant knew that petroleum fires were to be reasonably anticipated and that the purpose of fire equipment located in the tunnel was to provide emergency protection to the traveling public:[w]ould an ordinary man in defendant's position, knowing what they knew or should have known, anticipate that injury of the nature of that suffered was likely to result. . . .
It could be foreseen or anticipated by Palmer Baker that a fire could break out in the Tunnel and when it did break out, good and workable fire-fighting equipment would be needed to fight the fire. Otherwise, if a fire could not be foreseen or anticipated, why have any such equipment at all in the Tunnell. . . . Havard at 307, 302 So.2d at 232.
By analogy the plaintiffs conclude that the defendants, being construction and engineering firms, could have foreseen that the collapse of Bouldin Dam would have a "tremendous effect on the generating capacity of the Company system" and "would ultimately mean higher costs to power company customers." Such an analogy, of course, assumes a foreseeable relationship between the construction of the dam and higher costs to consumers because of the imposition of the "fuel adjustment clause."
We disagree with that analogy. The foreseeability aspect ofHavard was premised upon the relationship between the ultimate risk of harm and the professional knowledge of the engineer defendants. The availability of emergency firefighting equipment was viewed as a subject within the scope of their expertise, and it was foreseeable that the particular harm suffered would necessitate the use of such equipment. But the situation here is materially different. The defendants here are construction and engineering firms. They might, indeed, be held to have foreseen the loss of generating capacity due to a collapse of the dam. They are not, however, utility rate makers nor do the facts otherwise suggest that they have any knowledge with respect to that technical subject. For aught that appears the "fuel adjustment clause" is a rate-fixing device authorized by the Public Service Commission. That body, as we have shown, possesses the authority to fix rates, and their power includes the power to allow the imposition of the "fuel adjustment clause." If APCO has been allowed by the Public Service Commission to adjust its rates upward on account of the failure of Bouldin Dam, it is conceivable that APCO will be required by that Commission to adjust them downward should it recover damages in its lawsuit against some of these defendants. Such an issue is for *Page 1168
the Commission to decide, not the courts. Alabama PublicService Commission v. Southern Bell Telephone Telegraph Co.,
Let the judgment granting the defendants' motions to dismiss be affirmed.
AFFIRMED.
TORBERT, C.J., and MADDOX, JONES and SHORES, JJ., concur.
Reference
- Full Case Name
- Jim Zeigler v. Blount Brothers Construction Co.
- Cited By
- 25 cases
- Status
- Published