Justice v. ARAB LUMBER AND SUPPLY, INC.
Justice v. ARAB LUMBER AND SUPPLY, INC.
Opinion
This appeal arises from a suit by a materialman to enforce a lien against the *Page 540 "unpaid balance" due the original contractor by a homeowner.1 Following nonjury proceedings, the trial court awarded judgment for the materialman. We affirm.
To finance a portion of the construction price, the Justices on October 1, 1985, obtained a construction loan from United Tennessee Savings and Loan Association. The loan was secured by a mortgage on their land and the house that was to be constructed thereon. The proceeds of this loan were to be placed in a bank account ("construction account") and then disbursed to Albright by United Tennessee Savings and Loan and the Justices according to the disbursement schedule.
Construction commenced on or around October 1, 1985. Subsequent thereto, Albright received three disbursements as provided for under the terms of the contract: $11,000 on December 17, 1985; $15,000 on January 13, 1986; and $16,000 on February 10, 1986.2 As of February 10, 1986, Albright had thus received a total of $42,000 of the total contract price of $67,000. The disbursements were made after the lender's representative and Jimmy Justice had inspected the premises and found Albright's work to be satisfactory.
As of March 20, 1987, the house had not been completed. Counsel for the Justices sent a letter to Albright pointing out that the house had not been completed according to the specifications of the contract and demanding adequate assurance that the house would be completed within 15 days. The letter was accompanied by a "punchlist" of work that remained unfinished. Albright failed to respond to the letter.3
Acting upon advice of counsel, the Justices notified United Tennessee Savings and Loan that Albright was in default and they subsequently made arrangements with other workmen to complete the house. As of February 10, 1986, the date of the last disbursement to Albright, there remained in the construction account $23,000. Between March 8, 1986, and March 11, 1986, the Justices moved into the partially completed house.
In early April 1986, Jack Hamilton, general manager of Arab Lumber and Supply, Inc. ("Arab Lumber"), contacted Kathryn Justice. He informed her that Arab Lumber had not been paid for materials that had been purchased on credit by Albright to construct the house and requested that *Page 541 no further payments be made to Albright by the Justices. Arab Lumber had given no advance notice to the Justices that it was furnishing construction materials to Albright to be used in construction of the home.4 The total price for assorted materials furnished to Albright on credit by Arab Lumber was $21,790.59. Kathryn Justice indicated that no further checks would be presented to Albright until suppliers and materialmen had been paid.
Jimmy Justice, in a conversation with Jack Hamilton in March or April 1986, stated that it was his intention to finish construction of the house but that upon completion Arab Lumber would be entitled to any funds remaining in the construction account.5 Arab Lumber maintains that it continued to furnish on credit materials for use in the construction of the Justices' house.
As indicated, the Justices retained other workmen to complete the house after Albright stopped working on the project. The Justices made payments from the construction account to various individuals and companies and also reimbursed themselves in the amount of $1,686.10 for materials and labor that they personally had furnished.6 All of the work on the house was performed, according to the Justices, in accordance with the original contract specifications. They nonetheless maintained that at the time the funds in the construction account were nearly exhausted, the house was not completely finished according to specifications. The Justices then offered $2,000 remaining in the account to Arab Lumber in satisfaction of its claim for materials and supplies. The offer was refused.
On June 27, 1986, Arab Lumber sent notice to the Justices of its intention to file a lien for materials and supplies against their house for the unpaid account totaling $25,002.80.7 On July 16, 1986, a verified statement of lien was filed by Arab Lumber against the Justices' property and against any unpaid balance due the contractor (Albright).
On August 14, 1986, Arab Lumber filed the instant suit against the Justices, Bobby Albright, and the lender, United Tennessee Savings and Loan, for the unpaid balance of the account. The complaint alleged separate counts, seeking recovery under the following theories: a materialman's lien against the Justices' real estate; breach of an expressed or implied contract between Arab Lumber and the Justices for payment for the materials supplied in the construction of their house; fraud and/or deceit by the Justices in representing to Arab Lumber that it would be paid for all or for a substantial portion of the materials furnished; and a quantum meruit claim for goods furnished by Arab Lumber to the Justices or for their benefit.
Prior to trial, Bobby Albright received a discharge in bankruptcy of the debt owed to Arab Lumber. On September 11, 1986, United Tennessee Savings and Loan filed an answer maintaining that its mortgage was a first and paramount lien against the property that was the subject of the pending action and was therefore superior to any right, title, and interest claimed by Arab Lumber.
The Justices filed an answer to the complaint, denying any and all liability. United Tennessee Savings and Loan (presently known as United Federal Savings Bank) filed a motion for summary judgment, *Page 542 alleging that its mortgage lien upon the real estate was superior and prior in all respects to any mechanic's lien found to exist in favor of Arab Lumber. The motion was granted, and judgment was entered in favor of United Federal Savings Bank on June 9, 1987.
The case was tried to the court, without a jury, on June 9 and 10, 1987. On July 2, 1987, the trial court entered judgment for Arab Lumber and made the following written findings:
"The court finds from the evidence that the contract price for the construction of the house was $67,000.00; that the contractor had been paid $42,000.00 at the time he left the job; that the contract was ninety percent (90%) complete at that time; and that the contractor was due to be paid an additional $18,300.00 ($67,000 x 90% — $42,000.00).
"The court finds further that at the time the contractor quit the job, he owed for labor and material the sum of $33,921.57, of which $21,790.59 was owed to plaintiff and the balance owed to various other suppliers. The plaintiff's amount of $21,790.79 was 64% of the total amount owed to suppliers by the contractor at the time he quit the job. The court finds therefore that the plaintiff was due to be paid from the amount owing the contractor the sum of $11,712.00, being 64% of $18,300.00.
"Judgment is hereby entered for the plaintiff and against the defendant Jimmy R. Justice and Kathryn H. Justice in the amount of $11,712.00 plus interest at the legal rate from April 5, 198[6].
"It is further ordered that the plaintiff have a lien for the amount of $11,712.00 on the real estate of the defendants Justice as described in the complaint, subject to the first mortgage on the property; the lien is hereby ordered affixed.
"It is further ordered that the plaintiff have and recover from the defendant Bobby Albright the sum of $21,890.57 (which amount includes the amount of the judgment against the defendants Justice).
"Costs of this proceeding are taxed to the defendants Justice, for which execution may issue.
"ORDERED and DONE on this the 2nd day of July, 1987."
"/S/ RUDOLPH W. SLATE "CIRCUIT JUDGE"
The Justices appealed.
It is well settled that where a trial court bases its judgment upon findings of fact in a nonjury case in which the evidence is presented ore tenus, that judgment is reviewed on appeal with a presumption of correctness. Gray v. Reynolds,
At trial, Jimmy Justice testified that the house was 70-80% complete when the third construction loan disbursement was made to Albright on February 10, 1986. (R. 16). In additional testimony, he maintained that the house was still only 70-80% complete a month later when the Justices moved into the house between March 8 and March 11, 1986. (R. 141). As Jimmy Justice further testified, however, Albright continued to work on the house and grounds from February 10, 1986, to March 11, 1986. (R. 17).8 This testimony gives rise to an inconsistency: Jimmy Justice acknowledges that Albright continued to work on the house from February 10, 1986, to March 11, 1986, a period of 30 days; but at the same time he maintains that the house on March 11, after a period of 30 more days of work, was no closer to being finished than it was on February 10.
The trial court thus may have reasonably concluded that Albright performed more work toward completion of the house than Jimmy Justice indicated in his testimony. Where testimony is taken in proceedings conducted ore tenus, the weight and credibility accorded that testimony is to be determined by the trial court. Meyer v. Meyer,
Id.,"The ore tenus rule is grounded upon the principle that when the trial court hears oral testimony it has an opportunity to evaluate the demeanor and credibility of witnesses. In this case, the trial court observed one witness testify concerning this issue and made a determination of credibility. The fact that this determination was negative does not entitle us to ignore it. The fact remains that the trial court, having heard the testimony of one witness, is in a better position to resolve conflicting evidence than are we who must rely solely on written documents. Therefore, we accord the trial court's finding a presumption of accuracy, and we examine the record only to determine if that finding was clearly erroneous."
Viewing the trial court's finding with a presumption of correctness, we have carefully examined the record and find that the judgment as to this issue is supported by the evidence and is not plainly erroneous, palpably incorrect, or manifestly unjust.
The undisputed evidence at trial showed that the Justices paid Albright $42,000 under a construction contract that specified a $67,000 price. Finding that he had completed 90% of his contractual undertaking, the trial court concluded that Albright had earned the additional amount of $18,300 (or 90% of $67,000, less the $42,000 already paid). The court then calculated that Albright owed the total sum of $33,921.57 for labor and materials furnished by his subcontractors both before and after his contract terminated. Albright owed Arab Lumber $21,790.59, or 64% of this total. The trial court accordingly entered judgment in favor of Arab Lumber for $11,712.00, that amount being 64% of the balance unpaid to Albright by the Justices. The Justices also argue that the trial court failed to subordinate Arab Lumber's lien to their right to complete their construction contract by use of the balance unpaid to the contractor, Albright. Again, this contention is unsupported by the record.
Based on its finding that Albright completed only 90% of the construction contract, the trial court immediately deducted $6,700 from the $25,000 unpaid balance due to Albright. The court then deducted another $6,588, representing a 36% pro rata reduction for claims (other than the one asserted by Arab Lumber) that had been left unpaid by Albright. The trial court then decreased the unpaid balance by 53%, or the sum of $13,288, leaving the remainder of the unpaid balance available to the Justices. Instead of awarding Arab Lumber the full amount of its claim, the trial court thus subordinated Arab Lumber's claim to the Justices' right to use the $13,288 to complete construction and to pay the materialmen who had been engaged by Albright.
In support of their contention that the trial court failed to subordinate Arab Lumber's lien to their right to complete the construction contract by use of the unpaid balance, the Justices assert that a homeowner may use any amount unpaid to the original contractor to furnish labor and materials to complete the job in the event the contractor fails to do so. As a general proposition, the decisions of this Court are in accord with that view:
Standard Sanitary Mfg. Co. v. Aird,"It is settled that the owner can use any amount unpaid by him to his original contractor in furnishing labor and material to complete the job in event such original contractor shall fail to do so. In such event the lien of other laborers and materialmen who had furnished their labor and supplies to the contractor are subordinated to this right of the owner to complete the job by the use of such balance."
The expenditures by the Justices from the unpaid balance subsequent to Albright's default included the following: $6,000 for the purchase and installation of special rock for the exterior walls; $760 for the purchase of garage door openers; $454 for additional insulation; $425 for miscellaneous work; $1,516.90 for plumbing and electrical work; and a $1,686.10 payment to themselves for out-of-pocket expenses. From April 5, 1986, to May 8, 1986, a total of $22,997.98 was disbursed by the Justices from the unpaid balance of the construction account. Although it did not explicitly so indicate, the trial court apparently concluded that the payments itemized above, totaling $10,842.00, were not payments for work left uncompleted by Albright. These expenditures were not directly connected with the contract and were not required to indemnify the owner for the contractor's deviation from their agreement. Where a trial court does not make specific findings of fact, the reviewing appellate court will assume that the trial court made those findings that are necessary to support its judgment, unless those findings are clearly erroneous or against the great weight of the evidence. Davis v. Weatherington,
Such a conclusion is supported by the record in this case. We have reviewed the contract specifications and description of materials and find that neither the special exterior rock nor the garage door openers are included in the contract. Although the "punchlist" sent to Albright on March 20, 1986, by counsel for the Justices makes reference to "rock laid around foundation — front and sides," there is no indication that the rock is contemplated by the description of materials in the contract. As to the remaining payments, including the disbursement to themselves, the Justices apparently proffered no evidence to show that the labor or materials were required under the contract with Albright. In a suit by a materialman to establish a statutory materialman's lien, it is incumbent upon the homeowner who seeks to establish that expenditures of the "unpaid balance" have been used to complete construction, to show the connection of those expenditures with the particular job. Huffman-East Devel. Corp., supra.
The argument advanced by the Justices is that although $25,000 remained unpaid to the original contractor (Albright), none of it was due to him because the Justices had expended $25,451.88 to complete the home. Thus, they say, nothing remained in the construction account with which to pay Arab Lumber, and, because no unpaid balance was due to Albright, no lien could attach.
Such a contention presupposes, however, that the Justices were entitled to spend $25,451.88 to complete the house. As indicated in our treatment of the second issue presented in this appeal, supra, we will assume that the trial court found that the Justices impermissibly deducted from the unpaid balance payments that were not required in order to complete the contract or to correct deviations from it.
We would also observe that in Alabama an action for the enforcement of a statutory materialman's lien is in the nature of an equitable remedy. Hancock v. Taylor,
Based on the foregoing, the judgment of the trial court as to all of the issues herein addressed is due to be, and it hereby is, affirmed.
AFFIRMED.
TORBERT, C.J., and JONES, SHORES and ADAMS, JJ., concur.
"The Justices moved into their new home on or about March 9, 1986. Mr. Justice testified in deposition that the home was ninety (90%) percent complete, although much of the work and materials had not been paid for." The deposition here referred to was not, however, available at trial for use as evidence or for impeachment. Such testimony is obviously inconsistent with the assertions made by Jimmy Justice at trial that the house was 70 to 80 percent complete. Arab Lumber maintains that the alleged statement in the deposition became evidence in the trial and that it should therefore be considered as the direct testimony of Jimmy Justice. The Justices, on the other hand, assert that the alleged statement was not in evidence and thus could not be properly considered by the trial court. "With respect to the admissibility against a party of a pleading drawn and signed only by his counsel, and not shown to have been sworn to, signed by, drawn under or recognized by him in some other way as a correct statement, [Alabama] decisions are [apparently] in conflict." C. Gamble, McElroy's Alabama Evidence § 181.01(2) (3d ed. 1977). We pretermit any consideration of this issue, however, on the basis that there was sufficient evidence, irrespective of this alleged statement, to support the finding of the trial court. Any consideration thereof by the trial court was therefore immaterial.
Reference
- Full Case Name
- Jimmy R. Justice and Kathryn H. Justice v. Arab Lumber and Supply, Inc.
- Cited By
- 41 cases
- Status
- Published