Zedot Constr. v. Red Sullivan's Air Serv.
Cases that cite this one
7 later published cases cite this decision.
- O'Neal v. Bama Exterminating Co. (Ala. 2013)
- SouthTrust Bank v. Bowen (Ala. 2006)
- Norvell v. Parkhurst (Ala. 2017)
- Norvell v. Parkhurst (Ala. 2017)
- African Methodist Episcopal Church, Inc. v. Smith (Ala. 2016)
- Todd v. Discover Bank (Ala. Civ. App. 2012)
- Paragon Ltd., Inc. v. Boles (Ala. 2007)
This list shows which later cases cite this one. It does not say how they treated it, and no review of that has been done. Not a substitute for Shepard’s or KeyCite — verify before relying.
Opinion
Zedot Construction, Inc., appeals from the Jefferson Circuit Court's denial of Zedot's motion to compel arbitration.
Because, according to Zedot, CAS's work on the project was deficient, Zedot terminated CAS and hired a new subcontractor. On January 20, 2005, CAS sued Zedot in the Jefferson Circuit Court, alleging breach of contract, open account, unjust enrichment, and a violation of the Alabama Prompt Pay Act.
On February 24, 2005, Zedot filed a motion to dismiss, which made no mention of the arbitration clause. Rather, Zedot's motion argued that CAS's claim was barred by the two-year statute of limitations set out in §
On March 4, CAS filed its opposition to Zedot's motion for a summary judgment. On April 18, without a hearing, the trial court denied Zedot's motion and ordered Zedot to answer CAS's complaint within 30 days. On May 18, Zedot filed an answer to CAS's complaint and a counterclaim alleging breach of contract. In its answer, Zedot pleaded arbitration as an affirmative defense and stated that it asserted its counterclaim only to preserve that claim. On June 16, CAS filed its answer to Zedot's counterclaim. On July 20, Zedot filed a motion to compel arbitration. CAS opposed Zedot's motion to compel arbitration by arguing that Zedot had waived its right to arbitrate by participating in the litigation process. The trial court agreed and denied Zedot's motion. Zedot appealed.
Ocwen Loan Servicing, LLC v. Washington,"`The [Federal] Arbitration Act establishes that, as a matter of federal law, any doubts concerning the scope of arbitrable issues should be resolved in favor of arbitration, whether the problem at hand is the construction of the contract language itself or an allegation of waiver, delay, or a like defense to arbitrability.'
"460 U.S. at 24-25 (emphasis added; footnote omitted). In order to establish waiver, the party opposing arbitration bears a heavy burden, and waiver is not lightly to be inferred. Thompson v. Skipper Real Estate Co.,
729 So.2d 287 ,292 (Ala. 1999), and cases cited therein."
Zedot argues that the trial court erred in denying its motion to compel arbitration because, it says, Zedot had not substantially invoked the litigation process and because CAS will not be substantially prejudiced if it is required to arbitrate its claims against Zedot. Zedot points out that it pleaded arbitration as an affirmative defense in its answer to CAS's complaint. Zedot contends that its filing of a motion to dismiss asserting the defense of the statute of limitations, which was treated as a motion for a summary judgment and which was the only pleading Zedot filed before it asserted the affirmative defense of arbitration in its answer, does not constitute a substantial invocation of the litigation process. We agree.
"[T]he mere filing of a pleading does not constitute a waiver of the right to compel arbitration." Salter,
Further, CAS did not meet its burden of showing that it would be substantially *Page 400 prejudiced if it is forced to arbitrate its claims. Approximately four months passed between the filing of CAS's complaint and the filing of Zedot's answer, which raised arbitration as an affirmative defense, and approximately six months passed between the filing of CAS's complaint and the filing of Zedot's motion to compel arbitration. During that time, no hearings were held and no discovery took place, other than CAS's service of interrogatories on Zedot, which CAS did only after it was put on notice, by Zedot's answer, of Zedot's intent to seek arbitration. No trial date has been set.
Morrison Restaurants, Inc. v. Homestead Village ofFairhope, Ltd.,
"Homestead failed to seek mediation or arbitration either in its answer or in its response to Morrison's motion for summary judgment. In fact, eight months passed from the filing of the complaint before Homestead first asserted its right, in a motion filed on March 24, 1997. Further, and perhaps more important, when Homestead did assert its right to mediation or arbitration under the contract, it was not until after it had suffered an adverse ruling, in the form of the summary judgment as to liability. In light of these facts, we conclude that Homestead's actions indicate it intended to avail itself of the litigation process in lieu of the mediation/arbitration provisions in the contract. In addition, to refer the case to mediation or arbitration at such a late date would prejudice Morrison."
In the instant case, Zedot pleaded the affirmative defense of arbitration in its answer to CAS's complaint. And Zedot's motion to dismiss, converted to a motion for a summary judgment, was substantially different than the summary-judgment motion the trial court considered in Morrison. Zedot's motion was based only on the statute of limitations and was accompanied by an affidavit intended only to verify that a prerequisite to the application of the statute of limitations was satisfied. In contrast, the motion for a summary judgment inMorrison, which was considered by the trial court after Homestead failed to assert arbitration in its answer and in its response to that motion, required the court to construe the contract and determine whether the evidence presented a question as to the breach of that contract. Finally, the statement inMorrison that "perhaps more important, when Homestead did assert its right to mediation or arbitration under the contract, it was not until after it had suffered an adverse ruling, in the form of the summary judgment as to liability,"
REVERSED AND REMANDED.
NABERS, C.J., and SEE, HARWOOD, STUART, SMITH, BOLIN, and PARKER, JJ., concur.