Crews v. McLING
Crews v. McLING
Dissenting Opinion
1071691 — REVERSED AND REMANDED.
COBB, C.J., and LYONS, WOODALL, SMITH, BOLIN, PARKER, MURDOCK, and SHAW, JJ., concur.
Opinion of the Court
Otto M. McLing and his wife Sandy M. McLing sued Gerald W. Crews, the president of Crews Homes, Inc. ("CHI"), in the Elmore Circuit Court, alleging, among other things, that Crews had negligently delivered and installed on the McLings' property in Wetumpka a mobile home purchased from CHI in May 2005. Approximately 16 months after filing the action against Crews, and while the case against Crews was pending, the McLings commenced a separate action, also in the Elmore Circuit Court, against CHI, alleging that neither CHI nor the CHI employees who delivered and installed the mobile home were properly certified by the Alabama Manufactured Housing Commission ("AMHC"). The McLings argued that their contract with CHI was therefore void and that they were entitled to a refund of the $79,863.75 they had paid for the mobile home. The trial court entered a summary judgment in favor of the McLings in their action against CHI and awarded them the entire $79,863.75 they sought, plus interest and costs. The separate case against Crews proceeded to trial, at the end of which the jury returned a verdict in favor of the McLings for $67,235. Both Crews and CHI appeal the judgments entered against them. In appeal no. 1071479, we affirm the judgment entered against Crews, and, in appeal no. 1071691, we reverse the judgment entered against CHI.
Mosely, Gordon, and other CHI personnel worked on installing the mobile home on Thursday, May 26, and Friday, May 27; however, at the end of the day on May 27, only one-half of the mobile home was "set" and the other half was still approximately two to three feet away from the half that was "set." To protect the mobile home from the elements, the workers placed a tarp across the top of the mobile home before leaving for the weekend. Because it was Memorial Day weekend, they did not return to the McLings' property until Tuesday, May 31, at which time it was discovered that the tarp had failed to protect the interior of the mobile home from the thunderstorms that occurred over the weekend and that the walls, floors, and ceiling of the mobile home were wet. Mold and mildew grew inside the mobile home as a result.
CHI subsequently worked to repair the damage to the mobile home and to complete the installation; however, it did not finish working on the mobile home until late August. The McLings did not move into the mobile home at that time, however, because they still were not satisfied with its condition. The McLings had also made complaints to the manufacturer, and, in January 2006, representatives from Champion worked on the mobile home to repair certain manufacturer's defects. The McLings allege that Champion inflicted additional damage upon the mobile home during that repair process. After Champion and CHI finished working on the mobile home, the McLings still were not satisfied with its condition, and they accordingly continued to make repairs and upgrades, using their own money and efforts. The McLings finally moved into the mobile home in December 2006.
On January 17, 2006, the McLings sued Champion and Crews in the Elmore Circuit Court, alleging, fraud, breach of warranty, negligence, and wantonness. On July 31, 2006, the McLings settled their claims against Champion for $62,500, and Champion was dismissed from the case. Crews thereafter amended his answer to claim a setoff based on the pro tanto settlement entered into to by Champion and the McLings. The McLings responded by moving the trial court to enter a partial summary judgment holding that Crews was not entitled to such a setoff and asking the trial court to bar Crews from even referencing at trial the McLings' settlement with Champion. On April 9, 2008, the trial court granted the McLings' motion and entered the following order:
*Page 691"This case came before the court for a pretrial conference and a motion hearing. Pending before the court was the [McLings'] motion for partial summary judgment or, in the alternative, [the McLings'] first motion in limine. The issue presented to the court is whether the [McLings'] settlement with Champion Home Builders is available to [Crews] as a setoff against any recovery the [McLings] make from [Crews]. Upon consideration of the documents filed and the arguments of counsel, the [McLings'] motion be and hereby is granted. The court finds that there was no `single, indivisible injury' caused by [Crews] and Champion. Based on the testimony of [Crews's] own expert, Michael Bazzell, the damages caused by setup and delivery of the home can readily be separated from the damages caused by the manufacturer of the home. [Crews is] prohibited from making any reference to the [McLings'] settlement with Champion in the presence of the jury or the jury venire."
On the same date the trial court entered the above order, it also entered a summary judgment in favor of the McLings in the separate case they had filed against CHI on May 23, 2007.1 In that case, the McLings alleged that CHI had misrepresented that both it and its employee Mosely, who drove the truck that delivered the mobile home to their property, held the certifications required by the AMHC to deliver and install mobile homes. The McLings argued that their contract with CHI was void because, they said, neither was certified, and they further argued that they were entitled to a refund of their purchase price as a result. CHI maintained that both it and Mosely held the proper AMHC certifications and submitted documentary evidence of the certificates they held as well as two affidavits from Jim Sloan, administrator of the AMHC and the author of its regulations, in which he swore that both CHI and Mosely held the necessary certifications to deliver and install mobile homes. Both the McLings and CHI thereafter moved for a summary judgment, and, on April 9, 2008, the trial court entered a summary judgment in favor of the McLings by way of the following order:"1. The affidavits of Jim Sloan be and hereby are stricken on the grounds that Mr. Sloan may not provide oral testimony to interpret unambiguous regulations. See State v. Jackson Securities Inv. Co.,
243 Ala. 83 ,8 So.2d 573 (1942). In view of the court's ruling on this motion to strike, the court finds it unnecessary to address the other grounds alleged by the [McLings] in support of their motions to strike Mr. Sloan's testimony."2. The court finds that Crews Homes, Inc., contracted to deliver and install the [McLings'] mobile home, and that it was not licensed to do so as required by §
24-5-32 , Ala. Code 1975, and the regulations of the Alabama Manufactured Housing Commission."3. The court further finds that Terry Mosely, who transported the home, was not a certified installer and was not under written contract with a licensed manufacturer or a licensed retailer as required by the regulations of the Alabama Manufactured Housing Commission.
"4. Based on the foregoing the court finds that the [McLings'] contract with Crews Homes, Inc., is null and void, and that the [McLings] are entitled to a refund of their purchase price, together with interest at the rate of 6%.
"5. The [McLings'] motion for summary judgment filed on or about July 17, 2007, be and hereby is granted. [CHI's] motion for summary judgment filed March 11, 2008, be and hereby is denied."
After the summary judgment was entered in favor of the McLings in their case against CHI, the McLings moved the trial court to prohibit Crews from referring to that judgment or the ordered refund during the upcoming trial on their claims against him. On April 21, 2008, the trial court granted that motion by docket entry, noting that Crews was "[n]ot to discuss prior judgment and refund." The McLings' case against Crews was also called for trial on that date. During the course of the trial, the McLings agreed to dismiss all the claims they had asserted against Crews except the negligence claim, and, on April 24, 2008, the jury returned a verdict in favor of the McLings and against Crews for $67,235. Crews moved *Page 692 for a new trial pursuant to Rule 59, Ala. R. Civ. P.; however, that motion was denied, and the appeal Crews subsequently filed with this Court was docketed as appeal no. 1071479.
On May 6, 2008, CHI also moved the trial court, pursuant to Rule 59, Ala. R. Civ. P., to alter, amend, or vacate the summary judgment entered against it. On May 23, 2008, after that motion was filed, but before a hearing was held on it, this Court released its opinion in Fausnight v. Perkins,
"On the same bases as articulated in the above-referenced annotation from American Law Reports,[2] we conclude that the fact that the home builder in this case was not licensed, standing alone, is not a sufficient basis on which to require [the builder] to return the funds he has received from the [homebuyers]. We note as to the first four reasons stated in that annotation that Alabama's statute contains no provision expressly requiring an unlicensed home builder to refund moneys paid to it. To read the statute as containing such a provision would be to read into the statute a private cause of action for homeowners that easily could have been, but was not, expressed by the legislature in the statute. The statute expressly deprives the unlicensed home builder of the right to use Alabama courts to collect unpaid moneys otherwise owed it; it does not purport to provide homeowners with a cause of action to obtain refunds of amounts paid to unlicensed home builders."
994 So.2d at 921. On June 11, 2008, CHI filed a "supplement" to its previous Rule 59 motion calling the trial court's attention to Fausnight and arguing for the first time that the McLings had no legal basis upon which to claim a refund of their purchase price. The McLings filed an objection, arguing that CHI had failed to raise this argument previously and that, because the argument had not been made before the summary judgment was entered, it could not be raised in the Rule 59 motion. They also argued that CHI's "supplement" was untimely because all posttrial motions filed pursuant to Rule 59 are to be filed within 30 days of judgment. The trial court denied CHI's Rule 59 motion, and CHI then filed this appeal, docketed as appeal no. 1071691.
In support of his argument that he was entitled to a setoff, Crews cites Ex parte Goldsen,
"`It is a universal rule that a plaintiff, although entitled to full compensation for an injury, is entitled to only one recovery for a single injury caused by two or more tortfeasors.' Shepherd v. Maritime Overseas Corp.,
614 So.2d 1048 ,1051 (Ala. 1993); see also Ex parte Rudolph,515 So.2d 704 (Ala. 1987). In those cases where one tortfeasor settles, we have allowed the nonsettling tortfeasor to have the jury award reduced by the amount of any pro tanto settlement. Campbell v. Williams,638 So.2d 804 (Ala. 1994)."
The McLings, however, argue that the rule cited in Ex parteGoldsen is inapplicable because, they argue, Crews and Champion were not joint tortfeasors. The McLings argue that each damaged the mobile home at different times and it is possible to identify and separate the specific damage caused by each of them. In support of this argument, the McLings rely onEx parte Martin,
"We hold that, as a matter of law, non-joint tort-feasor defendants whose acts do not combine to cause one single injury cannot claim a set-off as a matter of law of any amount received by the plaintiff in settlement with other non-joint tort-feasor defendants based on distinct acts of those defendants.
"The second issue raised by the petitioners is whether they are entitled to a satisfaction of the judgment on the theory that to require them to pay the full $300,000 would result in a double recovery for [the plaintiff] for a single injury. However, we do not believe that [the plaintiff] has alleged a `single' injury. She claimed to have suffered the humiliation, mental anguish, and embarrassment as a result of the settling defendants' conduct in April 1986, and she claimed to have suffered the same type of injury as a result of the petitioners' conduct in February 1985. Because the actions of the defendants did not combine to cause a single injury, we cannot say that [the plaintiff] has received double compensation.
"While, in cases such as this, evidence of the existence of similar claims against multiple defendants who acted separately in time and manner may be probative on the issue of the amount of damage attributable to each defendant, the question whether testimony concerning the actual settlement will be allowed is, by necessity, within the trial court's discretion and, therefore, would not be reviewable by a writ of mandamus when the right to appeal exists.
"We have considered this petition because the trial court had denied a set-off where the petitioners claimed the law required it. We now hold that the law did not require a set-off. Because codefendants *Page 694 who are not joint tort-feasors are not entitled to a set-off of the settlement amount, the petitioners have failed to show that they have a `clear legal right' to have their judgment reduced by the amount of the settlement; therefore, we deny the petition for the writ of mandamus."
We must determine, therefore, whether Champion and Crews were in fact joint tortfeasors so that Crews would be entitled to a setoff based on the settlement entered into by the McLings and Champion. The answer to that question in turn hinges on whether their actions combined to cause a single injury. The trial court held that there was no "single, indivisible injury" and cited the deposition testimony of Crews's own expert, Michael Bazzell, in support of that holding. Bazzell testified as follows in that deposition:
"Q: And what you have put down here on your report on plaintiff's exhibit # 702 are things that in your judgment were related to setup of the [mobile] home?
"A: Yes.
"Q: And not related to the manufacture of the home?
"A: Correct.
"Q: In other words, this is not a situation where it's just totally impossible to go in there and sort out or separate the manufacturing problems from the setup items? It's not impossible to do that, is it?
"A: No.
"Q: Have you had cases where you felt that was in fact the case, you just couldn't sort them out, or can you always sort them out?
"A: You pretty much can always."
The McLings' expert, Randall Chesser, also testified that the estimated cost to repair only the problems specifically attributable to installation and setup was $14,200, further indicating that it was possible to separate the damage done by Crews from the manufacturer's defects and damage done by Champion in repairing those defects. In light of this evidence, the trial court's holding that Crews was not entitled to a setoff because there was no single indivisible injury is due to be affirmed.3
Crews next argues that he was wrongfully prohibited from cross-examining the McLings about actions of Champion that may have contributed to the McLings' mental anguish. In support of this argument, he cites multiple cases standing for the proposition that a defendant is entitled to question a plaintiff seeking damages for personal injuries, including mental-anguish damages, about other conditions or injuries that the plaintiff has suffered that might, in fact, have been the actual source of the injury in question. See, e.g., Lassie v. ProgressiveIns. Co.,
The McLings do not dispute the correctness of the legal principle that forms the basis for Crews's argument; however, they contend that his argument is nevertheless without merit because, they say, the trial court never prevented Crews from asking the McLings whether Champion's actions contributed to their mental anguish. They note that Crews has not cited any specific ruling in which the trial court limited Crews's cross-examination of the McLings in this regard, and they further note that the trial court's April 9, 2008, order stated only that "[t]he defendants are prohibited from making any reference to the plaintiffs' settlement with Champion. . . ." (Emphasis added.) Thus, the McLings argue, although the trial court prevented Crews from referencing their settlement with Champion, it did not prohibit Crews from asking the McLings about damage to their home caused by Champion and any mental anguish they may have suffered as a result of that damage.
Furthermore, the McLings argue, Crews in fact asked Otto McLing about other possible sources of his mental anguish during the trial, as evidenced by the following transcript of his cross-examination:
"Q: One more thing, Mr. McLing. I think you testified earlier that you suffered a great deal of annoyance and disappointment and inconvenience resulting from this lawsuit; is that right?
"A: Yes, sir.
"Q: Was there anything else going on in your life that could have also caused inconvenience, disappointment, or annoyance?
"A: Not at that time I don't believe.
"Q: Not at this time?
"A: No, sir.
"Q: Not at any time when you filed this lawsuit?
"A: No, sir."
An off-the-record discussion was held immediately following this testimony; however, the testimony quoted above was not stricken, and there is no indication that the trial court prevented Crews from continuing to pursue that line of questioning. Because it is not clear that the trial court prohibited Crews from asking the McLings whether a portion of the mental anguish they claimed to have suffered was attributable to Champion, much less that the trial court exceeded its discretion by doing so, see Kingsley v.Sachitano,
Crews's final argument in appeal no. 1071479 is that the trial court wrongfully precluded him from presenting evidence showing that CHI, in the separate action the McLings had filed against it, had been ordered to refund the McLings the $79,863.75 that they paid for their mobile home, plus interest and costs. Crews argues that the judgment entered against CHI fully compensated the McLings for any injuries they suffered and that the subsequent judgment entered against him in this case should have been barred by the doctrine of res judicata. The only cases cited by Crews in support of this argument are Hughes v.Allenstein,
The McLings argue that Crews waived this argument because he never raised it in the trial court. See, e.g., ImperialCrown Marketing Corp. v. Wright,
We first consider the evidence indicating whether CHI was properly licensed to install the McLings' mobile home. Section
CHI, however, argues that it is a certified installer even though the installation certificate it claims to operate under was issued in Crews's name. In support of this argument, CHI submitted to the trial court the official "application for installer certification" form that it filed with the AMHC. The first item of information requested on that application is the "name of applicant (person or company)." The application form submitted to the trial court by CHI lists the applicant in this case as "Crews Homes, Inc./Gerald W. Crews." The next line states "if this is a firm or corp. list name of officer to becertified" and specifically requests that the person listed be the "same as [the] principal on bond."5 (Emphasis added.) The official AMHC application form therefore indicates, CHI argues, that if a corporation applies for certification, that certification will be issued in the name of the officer listed as the principal on the corporation's bond.6 In light of this evidence, we agree with CHI that there is, at least, a genuine issue of material fact as to whether it was properly certified by the AMHC as a mobile-home installer. The trial court accordingly erred by holding, as a matter of law, that it was not.
We next consider the evidence indicating whether Mosely was properly certified to transport the McLings' mobile home. Rule
1071479 — AFFIRMED.
COBB, C.J., and LYONS, WOODALL, SMITH, BOLIN, PARKER, and SHAW, JJ., concur.
Reference
- Full Case Name
- Gerald W. Crews v. Otto M. McLing and Sandy M. McLing. Crews Homes, Inc. v. Otto M. McLing and Sandy M. McLing.
- Cited By
- 3 cases
- Status
- Published