Opinion of the Court
*1008Real party in interest Laurel Way Joint Venture (LWJV) appeals from the trial court's order setting aside a planned development permit (PDP) issued by the City of Redwood City (City). LWJV represents 14 sets of owners of 18 undeveloped lots in the City who seek to build up to 16 homes on a street known as Laurel Way. Following the preparation of an environmental impact report (EIR), the City issued the PDP for a planned upgrade to Laurel Way, covering the first phase of a development project referred to as the Laurel Way Development Project (Project). The PDP includes such elements as a cul-de-sac for a fire truck turnaround, a fire hydrant, new streetlights, pedestrian pathways, an open space land dedication, and other civic improvements. It does not include any development on the individual lots. The court set aside the PDP, concluding the City had abused its discretion by failing to evaluate the legal status of the 18 lots under the Subdivision Map Act ( Gov. Code, § 66410 et seq. )
*556Because issues regarding the legal status of the individual lots under the SMA are not ripe for judicial review, we now reverse.
FACTUAL BACKGROUND AND PROCEDURAL HISTORY
The Project site along Laurel Way consists of approximately 4.75 acres. The site is contained in a hillside canyon and is steeply sloped. Laurel Way is currently a private, dead end street that is only partially paved. The Project includes undeveloped properties located along the unpaved end of the street.
The City has divided the Project into two phases. The first phase involves improvements to the Project area, including paving the roadway, installing utilities and sewer connections as well as retaining walls, landscaping, drainage infrastructure, and planting replacement trees. The second phase involves the construction of individual residences on the lots. The second phase is not to commence until the first phase has been completed and approved by the City's community development director. The PDP at issue in this case pertains to the first phase of the Project.
*1009On May 1, 2006, LWJV filed its first application with the City for a PDP. Seven months later, the City commenced review for an EIR.
In February 2010, the City circulated a draft EIR for public review, detailing the Project's potential environmental impacts and proposed mitigation measures.
On August 24, 2010, the City's planning commission certified a final EIR, adopting findings for mitigation measures, including a mitigation monitoring program. The EIR concluded that the Project as then proposed would have no significant environmental impact after mitigation.
On September 9, 2011, LWJV withdrew its original PDP application and submitted a new application, reducing by two the proposed number of residences.
In March 2013, a revised final EIR was prepared. The EIR was approved by the City's planning commission.
On April 1, 2013, the City's planning commission adopted a resolution approving the PDP. The resolution includes 63 conditions of approval.
On January 13, 2014, the City Council passed a resolution (Resolution) upholding the City planning commission's decision to certify the EIR and modifying the commission's approval of the PDP. The Project as approved contemplates that up to 16 new houses will be built, subject to additional permits, as well as to extensive additional conditions, and requirements.
On February 13, 2014, respondent Save Laurel Way (SLW) filed a petition for writ *557of mandate and a complaint for injunctive relief asserting four causes of action for (1) violation of the City's municipal code and zoning ordinance, *1010(2) violation of the state Planning and Zoning Law (§ 65300 et seq.), (3) violation of the SMA, and (4) violation of CEQA ( Pub. Resources Code, § 21000 et seq. ).
On August 8, 2014, the City filed its answer to the petition and complaint.
On October 24, 2014, a court trial was held, consisting of oral argument based on the administrative record and trial briefs filed by the parties.
On January 23, 2015, the trial court issued a proposed statement of decision.
On February 8 and 9, 2015, petitioners and real parties filed objections to the proposed statement of decision.
On November 20, 2015, the trial court issued the final statement of decision setting aside the PDP and vacating the City's certification of the EIR. Invoking the SMA and recent cases addressing older subdivision maps, the court concluded the City had abused its discretion in approving the Project because "[t]he facts and law do not support a finding that there are 16 legal lots upon which 16 homes can be built, and do not support a finding that the property owners have a vested right to develop each of the 16 alleged lots." LWJV has appealed.
DISCUSSION
Among the arguments advanced on appeal, LWJV contends that the SMA does not require a city to evaluate lot legality before granting development permits or preparing an EIR under CEQA. The contention is persuasive. Because the SMA's provisions were not invoked by the City's action in approving the PDP and the EIR, we conclude the subdivision map issues addressed by the trial court are not ripe for judicial review.
I. Standard of Review
" Code of Civil Procedure section 1094.5, the state's administrative mandamus provision ... structures the procedure for judicial review of adjudicatory *1011decisions rendered by administrative agencies. ... Subdivision (b) of section 1094.5 prescribes that when petitioned for a writ of mandamus, a court's inquiry should extend, among other issues, to whether 'there was any prejudicial abuse of discretion.' " ( Topanga Assn. for a Scenic Community v. County of Los Angeles (1974)
Our role on appeal is identical to that of the trial court. Thus, we are not bound by the trial court's determinations. ( Lucas Valley Homeowners Assn. v. County of Marin (1991)
*1012II. The SMA
1. General Principles
The SMA is " 'the primary regulatory control' " which governs the subdivision of real property. ( Gardner v. County of Sonoma (2003)
Under the current version of the SMA, subdivisions ordinarily " 'may be lawfully accomplished only by obtaining local approval and recordation of a tentative and final map pursuant to section 66426, when five or more parcels are involved, or a parcel map pursuant to section 66428 when four or fewer parcels are involved. [Citation.] A local agency will approve a tentative and final map or a parcel map only after extensive review of the proposed subdivision and consideration of such matters as the property's suitability for development, the adequacy of roads, sewer, drainage, and other services, the preservation of agricultural lands and sensitive natural resources, and dedication issues. [Citations.]' [Citation.] The [SMA] prohibits the sale, lease, financing or improvement of any parcel or parcels of real property for which a final map or parcel map is required under the Act unless a final map or parcel map has been recorded." ( Abernathy Valley, Inc. v. County of Solano (2009)
The subject lots at issue in the present case were created as part of a residential *559subdivision when the Project area was under the unincorporated San Mateo County jurisdiction. The applicable 1926 subdivision map (1926 Map) reflected a survey, platting into lots, and creation of hundreds of numbered parcels, for purposes of division of land for sale. The City annexed the property along the end of Laurel Way, including the lots that are the *1013subject of the PDP, in 1969. The Project area is currently designated Low Density Residential under the General Plan, and Residential-Hillside under the Zoning Ordinance.
2. Historical Overview of the SMA
As noted above, the lots within the Project site were subdivided in 1926. To understand the basis of the trial court's ruling it is necessary to review the history of the SMA.
"The Subdivision Map Act has regulated the division of land in California since the nineteenth century. 'The first Subdivision Map Act was enacted in 1893. Subsequent versions of the Act were enacted in 1907, 1929, 1937 and 1943. The modern latest version of the Act was enacted as part of the Government Code in 1974.' [Citation.] 'All versions of the Act enacted subsequent to the first Act in 1893 contained grandfather clauses exempting from the current Act those subdivisions established in compliance with laws in effect when recorded.' [Citation.]
"In the earliest twentieth-century version of the Act, 'development was left almost entirely to the discretion of the developer. The act provided for no governmental regulation, and required submission of a subdivision map to local officials only to allow them to check its accuracy in order to assure good title to the resulting parcels.' [Citation.] 'With the advent of zoning in the 1920s, subdivision mapping began to assume some importance as a land use control.' [Citation.] The 1929 version of the Act first authorized local subdivision regulations. [Citation.] The 1937 enactment first prohibited sellers from conveying subdivided lots without prior local approval. [Citation.] 'The 1937 enactment was the basis for the 1943 codification which, together with many amendments thereto, remained in effect until the 1974 recodification. [Citation.]' [Citation.] But by the late 1960's, 'many uncoordinated amendments' had rendered the Act 'so complex and disorganized that the need for recodification was apparent. Following attempts in 1971, 1972 and 1973, the Subdivision Map Act, which had been codified in the Business and Professions Code ( [§] 11500 et seq. ), was recodified in [ Government Code section] 66410 et seq. ' " ( V an't Rood v. County of Santa Clara (2003)
3. The SMA's Grandfather Provision
The trial court focused on whether the 1926 Map is covered by the SMA's current grandfather provision, which provides that the prohibitions on selling, leasing, financing, or improving parcels on maps that do not comply with the SMA do not apply to "any parcel or parcels of a subdivision offered *1014for sale or lease, contracted for sale or lease, or sold or leased in compliance with or exempt from any law (including a local ordinance), regulating the design and improvement of subdivisions in effect at the time the subdivision was established ." (§ 66499.30, subd. (d), italics added; see Gardner, supra, 29 Cal.4th at p. 998,
Subsequently, in Witt , the Court of Appeal ruled that maps filed in compliance with subdivision map laws in effect in 1915 are not covered by section 66499.30, subdivision (d). ( Witt, supra, 165 Cal.App.4th at p. 548,
*1015In Abernathy , a property owner sought a writ of mandate to compel the county to issue a "certificate of compliance"
In Hays v. Vanek (1989)
4. The Trial Court's Ruling
The trial court reasoned that "the issue is not whether the 1926 subdivision map here complied with the law as of 1926, but whether it complies with the law now or otherwise fits squarely within the grandfather clause under the present language." Relying on Abernathy and Hays, the court concluded there was no showing in the record that any applicable "design and improvement" laws existed when the 1926 Map was filed. Thus, it did not appear that the parcels in the Project would fall within the SMA's grandfather provision. However, the trial court did not make an ultimate finding as to whether the lots are illegal. Rather, it found that the city abused its discretion because it expressly found all 16 Project lots were legally created without having considered their status under the SMA. While the court's reasoning is not inconsistent with the pertinent authorities, its ultimate conclusion is flawed.
*1016III. Issues Under the SMA Are Not Ripe for Review
The City concluded the subject lots are presumptively entitled to legal status based on section 33.2 of the RZO. That section provides, in part: "A nonconforming lot or parcel may be used for development subject to compliance with all other provisions of this article and other applicable codes. ..." It is true the City did not also separately evaluate the status of the lots under the SMA.
*562Unlike the present case, in the principal cases cited to by the trial court and relied on by the respondents here, the issues concerned landowners seeking status or relief under the current version of the SMA for properties subdivided under older maps. In Abernathy , a landowner had appealed after a county denied his request to record a certificate of compliance with the SMA for a lot that had been subdivided under a map recorded under the 1907 SMA. ( Abernathy , supra , 173 Cal.App.4th at p. 45,
It is undisputed that the PDP grants authorization to proceed only with infrastructure improvements to the Project area.
"The ripeness requirement, a branch of the doctrine of justiciability, prevents courts from issuing purely advisory opinions. [Citation.] It is rooted in the fundamental concept that the proper role of the judiciary does not extend to the resolution of abstract differences of legal opinion. It is in part designed to regulate the workload of courts by preventing judicial consideration of lawsuits that seek only to obtain general guidance, rather than to resolve specific legal disputes. However, the ripeness doctrine is primarily bottomed on the recognition that judicial decision making is best conducted in the context of an actual set of facts so that the issues will be framed with sufficient definiteness to enable the court to make a decree finally disposing of the controversy." ( Pacific Legal Foundation v. California Coastal Com . (1982)
There are no issues ripe for adjudication under the SMA in the present case because that legislation is not squarely implicated by the City's actions in approving *563the PDP and certifying the EIR.
Our holding in this appeal is a limited one. We conclude the approval of the PDP in Phase 1 of the Project involves only the development of an infrastructure for the land involved. The SMA is not implicated in Phase 1. The validity of conveyance by implication in Phase 1 is not before us. Adjudication of any issue under the SMA is not ripe. In light of our conclusion, we need not address the parties' remaining arguments.
DISPOSITION
The judgment is reversed.
We concur:
Humes, P. J.
Margulies, J.
All further statutory references are to the Government Code except as otherwise indicated.
Two lots within the Project area on Laurel Way already contain houses.
The trial court concluded state law does not require preparation of an EIR under the circumstances presented here. However, in 1988 the City adopted a policy requiring an EIR prior to any new development on the subject portion of Laurel Way. This EIR was intended to analyze the full build-out of the street, with a goal of establishing guidelines for any future development. LWJV was formed in response to the policy requiring an area-wide EIR.
The Resolution affirmed and adopted the planning commission's resolution approving the project, which found that the Project as approved would not be detrimental or injurious "because the project has been found to be consistent with the community goals established in the City's General Plan and Zoning Ordinance." The Resolution also approved the planning commission's approval of the EIR. That approval includes a finding that the Project "provides a high quality, single-family residential in-fill housing project" that supports the City's goal of meeting its regional housing need under the housing element of its general plan.
The City is not a party to this appeal.
Section 66424 defines a subdivision, in part, as follows: " 'Subdivision' means the division, by any subdivider, of any unit or units of improved or unimproved land, or any portion thereof, shown on the latest equalized county assessment roll as a unit or as contiguous units, for the purpose of sale, lease, or financing, whether immediate or future. Property shall be considered as contiguous units, even if it is separated by roads, streets, utility easement, or railroad rights-of-way." (See Witt Home Ranch, Inc. v. County of Sonoma (2008)
The trial court noted, however, that it appeared the 1926 Map was in compliance with state laws that were in effect at the time.
A developer may request a determination from the appropriate local agency as to whether the property at issue complies with the SMA and applicable local ordinances. (§ 66499.35, subd. (a); Gardner, supra, 29 Cal.4th at p. 998,
Prior to the issuance of this opinion, and in its petition for rehearing, SLW argued that it should be allowed to file a supplemental brief on the issue of ripeness, citing to Government Code section 68081, which provides that "before . . . a court of appeal . . . renders a decision . . . based upon an issue which was not proposed or briefed by any party to the proceeding, the court shall afford the parties an opportunity to present their views on the matter through supplemental briefing. . . ." We denied the request. Under this statute, "[t]he parties need only have been given the opportunity to brief the issue decided by the court, and the fact that a party does not address an issue, mode of analysis or authority that is raised or fairly included within the issues raised does not implicate the protections of section 68081." (People v. Alice (2007)
The city council found that each of the lots in the Project area are nonconforming lots that do not comply with the current minimum lot size requirements set forth in the RZO for such steeply sloped lots. The City noted that had LWJV proposed a new subdivision map for the area, the RZO would not have allowed the creation of more than four or five lots. The City observed that the lots had already been created by the 1926 Map and concluded "[n]o credible evidence has been presented to demonstrate that these lots are unlawful." Specifically, the City found that the owners were conditionally entitled to develop the lots under RZO section 33.2, including obtaining a planned development permit for lots having a slope greater than 30 percent.
Our decision in Save Mount Diablo v. Contra Costa County (2015)
As stated in the Resolution, Phase I of the Project includes the new paved private roadway, pedestrian paths, utilities, sewer connections, retaining walls, landscaping, drainage infrastructure, and the planting of replacement trees. Phase II of the Project is the construction of the individual residences, which cannot commence until Phase I has been satisfactorily completed.
In Pacific Legal, the Supreme Court adopted a two-pronged ripeness analysis used by the United States Supreme Court, requiring an evaluation of (i) "the fitness of the issues for judicial decision" and (ii) "the hardship to the parties of withholding court consideration." (Pacific Legal, supra, 33 Cal.3d at p. 171, italics omitted; see Abbott Laboratories v. Gardner (1967)
The EIR was based on the assumption that 18 new homes would be constructed. It was also based on the assumption that the owners had a right to reasonably develop each property, noting that "[o]ver time, each lot could be developed on an individual basis under current City regulations." (Italics added.) This was seen as potentially detrimental, as piecemeal development would not result in a comprehensive plan for infrastructure improvements. Under the circumstances, the phased development strategy undertaken by the City does not suggest an abuse of discretion.
SLW also argues that the trial court held the City failed to make a required finding that the Project will provide " 'an environment of physical and functional desirability, in harmony with the character of the surrounding neighborhood' " and that LWJV waived this point by not addressing it in the opening brief. SLW also argues that the trial court held the City failed to make a required finding that the project will provide " 'an environment of physical and functional desirability, in harmony with the character of the surrounding neighborhood' " and that LWJV waived this point by not addressing it in the opening brief. As the trial court's statement of decision is somewhat confusing on this point, we decline to treat the issue as waived because LWJV adequately addresses this finding in its reply brief. We agree with LWJV that other findings in the Resolution and the April 2013 planning commission's resolution explain how the Project will achieve the goal of harmony with neighborhood character.
Case-law data current through December 31, 2025. Source: CourtListener bulk data.