1 2 3 4 5 UNITED STATES DISTRICT COURT 6 EASTERN DISTRICT OF CALIFORNIA 7 8 KENAI MID-CONTINTENT, INC., Case No. 1:24-cv-00434-KES-CDB
9 Plaintiff and ORDER DENYING STIPULATED REQUEST Counter-Defendant, TO CONTINUE CASE MANAGEMENT 10 DATES v. 11 (Doc. 16) GREAT BASIN OPERATING, LLC, 12 Defendant and 13 Counter-Claimant.
14 15 Relevant Background 16 The operative scheduling order governing the litigation of this case was entered on July 17 10, 2024. (Doc. 11). As set forth therein, nonexpert discovery closes on April 30, 2025; expert 18 discovery closed on July 25, 2025. The undersigned admonished that the case management dates 19 “are considered to be firm and will not be modified absent a showing of good cause even if the 20 request to modify is made by stipulation.” (Id. at 7) (emphasis in original). 21 In advance of the mid-discovery status conference, on February 13, 2025, the parties filed 22 a joint-mid-discovery status report in which they represented on January 31, 2025, 23 Defendant/Counter-Claimant Great Basin Operating, LLC (“Defendant”) served interrogatories, 24 document requests, and requests for admission on Plaintiff/Counter-Defendant Kenai Mid- 25 Continent, Inc. (“Plaintiff”) with a response due on March 3, 2025. (Doc. 14). The parties 26 represented that on February 13, 2025, Plaintiff likewise served interrogatories, document 27 requests, and requests for admission on Defendant with a response due on March 17, 2025. (Id. at 2). The parties represented that “[r]egarding impediments to completing discovery within the 1 deadlines, [Defendant’s] lead counsel switched firms in August 2024, which resulted in some 2 delay in prosecuting all of his cases, including this one.” (Id.). The parties represented they both 3 “plan to work with diligence to complete discovery within the current deadlines, but they would 4 like to reserve the right to request the Court for a modest extension of discovery if necessary” 5 and that “they will know by March 17, 2025[,] whether they believe they will need an extension 6 and any motion for [such] will be filed by that date.” (Id.). 7 The Court vacated the mid-discovery status conference and admonished the parties of 8 “their obligation to diligently pursue and timely complete discovery within the scheduled case 9 management dates.” (Doc. 15). 10 Stipulated Request to Continue Case Management Dates 11 Pending before the Court is the parties’ joint, stipulated request to extend unexpired case 12 management dates and deadlines by 60 days, filed on March 17, 2025. (Doc. 16). The parties 13 proffer that good cause exists for the extension in part because Defendant’s lead counsel switched 14 firm in August 2024, which resulted in delay in prosecuting this case, and while the parties “have 15 worked diligently to complete discovery within the allotted timeframe, this matter is document 16 intensive and factually complex.” (Id. at 3). The parties represent that based on Plaintiff’s March 17 11, 2025, responses to Defendant’s January 31, 2025, discovery requests, Defendant “will need to 18 procure far more expansive third-party discovery than initially anticipated as [Plaintiff] proffers 19 that it does not have control, possession or custody of many of the requested records.” (Id.). 20 Defendant proffers that “the documents and information sought … will apparently have to be 21 obtained via third parties[.]” (Id.). The parties represent that “[r]esponses are forthcoming” to 22 Plaintiff’s discovery requests served on February 13 and 27, 2025. (Id.). The parties represent 23 that Defendant “requires time to identify and locate … witnesses [identified in Plaintiff’s March 24 11, 2025, production of records] … some of which are likely to live out of state, and depose them, 25 before the close of discovery.” (Id. at 4). The parties represent the requested extension will not 26 impede on the trial date. (Id.). 27 Standard of Law 1 amend the pleadings, complete discovery, and file motions.” Fed. R. Civ. P. 16(b)(3). Once 2 entered, a scheduling order “controls the course of the action unless the court modifies it.” Fed. R 3 Civ. P. 16(d). Scheduling orders are intended to alleviate case management problems. Johnson 4 v. Mammoth Recreations, Inc.,
975 F.2d 604, 610(9th Cir. 1992). 5 “A scheduling order is not a frivolous piece of paper, idly entered, which can be cavalierly 6 disregarded by counsel without peril.” (Id.) (quotation and citation omitted). Under Federal Rule 7 of Civil Procedure 16(b), a scheduling order “may be modified only for good cause and with the 8 judge’s consent.” Fed. R. Civ. P. 16(b)(4). As the Court of Appeals has observed:
9 In these days of heavy caseloads, trial courts in both the federal and state systems routinely set schedules and establish deadlines to foster efficient treatment and 10 resolution of cases. Those efforts will be successful only if the deadlines are taken seriously by the parties, and the best way to encourage that is to enforce the deadlines. 11 Parties must understand that they will pay a price for failure to comply strictly with scheduling and other orders... 12 13 Wong v. Regents of Univ. of Cal.,
410 F.3d 1052, 1060(9th Cir. 2005). “Rule 16(b)’s ‘good 14 cause’ standard primarily considers the diligence of the party seeking the amendment.” Johnson, 15
975 F.2d at 609. If the moving party is unable to reasonably meet a deadline despite acting 16 diligently, the scheduling order may be modified. (Id.). If, however, the moving party “‘was not 17 diligent, the inquiry should end’ and the motion to modify should not be granted.” Zivkovic v. So. 18 Cal. Edison Co.,
302 F.3d 1080, 1087(9th Cir. 2002) (quoting Johnson,
975 F.2d at 609). 19 Discussion 20 Here, although the parties represent they have “worked diligently to complete discovery 21 within the allotted timeframe” given that lead counsel for Defendant “switched firms in August 22 2024[,]” (Doc. 16 at 3), Defendant did not serve initial discovery requests until January 31, 23 2025—more than six months after the case was scheduled and at least five months after counsel’s 24 reported relocation to a different firm. Further, Plaintiff did not serve its initial discovery requests 25 until February 13, 2025—seven months after the case was scheduled. The parties have not 26 provided the Court with any details concerning what discovery was completed before 27 Defendant’s counsel switched firms in August 2024 or otherwise explained the significant delay 1 Because the parties have failed to establish they acted diligently to meet discovery 2 | deadlines as set forth in the scheduling order, the parties’ request to extend case management 3 || dates will be denied. See Zivkovic,
302 F.3d at 1087; (Doc. 11 at 7). 4 Conclusion and Order 5 Accordingly, IT IS HEREBY ORDERED, the parties’ stipulated request to extend 6 | discovery and all other case management dates (Doc. 16) is DENIED. 7 | ITIS ORDERED. | Dated: _Mareh 18, 2025 | hr Rr 9 UNITED STATES MAGISTRATE JUDGE 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28