Schallert-Ganahl Lumber Co. v. Sheldon
Schallert-Ganahl Lumber Co. v. Sheldon
Opinion of the Court
Action to foreclose a materialman’s lien. Appellant is a corporation engaged in the lumber business. Sheldon & Son are copartners, and contracted in writing with the defendant Annie C. Severance to furnish the material and erect upon her separate property a dwelling-house. Appellant furnished lumber to Sheldon & Son for the building, and a notice of lien therefor was filed. Both parties to this appeal concede that the contract was void. Sheldon & Son abandoned the work early in January, 1889, before completion, and Mrs. Severance employed mechanics, and proceeded with the work. In May, 1889, she, with husband and servants, moved into and occupied the rear
The court found that the building was not completed at the time the notice of lien was filed; and, if that finding is justified by the evidence, it will not be necessary to consider any other specification of error. The occupancy of the rear portion of the house was known to appellant on June 25th, but appellant makes no point upon such occupancy. The complaint alleges completion “on or about August 22d,” and whether the building was then completed was a question of fact to be determined by the court: Willamette Steam Mills Lumbering etc. Co. v. Los Angeles College Co., 94 Cal. 237, 238, 29 Pac. 629. The only witness who testified upon the subject of the completion of the building was Mr. Driscoll, the secretary of the plaintiff corporation. He testified in substance that he visited the building on August 21st; that workmen were there on that day, doing some little things; that there might be one or two men there for several months doing little things, waiting the arrival of material from the east; that Mr. Cranton was working in the house; that Cranton said there were twenty-four doors to hang, ventilators to make, water-closet traps, bathroom not completed, wardrobe not completed, a painter working on the house; that the doors were made, and only had to be hung; that the oxidized hardware, door knobs and locks were not on; that it was stated the locks cost $35 each—a couple of thousand dollars on the whole house, he heard; that he did not know whether the tiling was in the bathroom, nor whether the picture moldings were up in the second story, nor whether the front chamber was completed, nor whether the closets were finished, or the plumbing finished, but thought the house was substantially completed; and, further, that the oxidized hardware and the tiling he thought were not in the contract. Such was the condition of the building on August 21st, the day before the lien was filed,
We concur: Temple, C.; Belcher, C.
For the reasons given in the foregoing opinion the judgment and order are affirmed.
Case-law data current through December 31, 2025. Source: CourtListener bulk data.