Gnekow v. Confer
Gnekow v. Confer
Opinion of the Court
This action is brought to foreclose a mechanic’s lien taken by plaintiff upon a building of the defendant the Masonic Building Association, to secure a balance of $756 due on account of material furnished and labor performed upon a building described as the “New Masonic Building,” situate in Redding, county of Shasta, state of California. The other defendants, viz., Confer and Hanks, who were the original contractors for the construction of the building, made default. The defendant the Masonic Building Association had judgment, upon the ground that the lien of plaintiff was not filed within the time prescribed by the statute, viz., within thirty days after the completion of the building. Plaintiff appeals from the judgment and the cause is presented on the judgment-roll.
Appellant acquiesces in the judgment refusing to enforce his lien, but insists that upon the findings he was entitled to a personal judgment against the corporation defendant for $756, the amount of his claim. The findings show in substance as follows: (1) In the month of July,. 1891, the corporation defendant entered into a contract with Saul Confer and W. E. Hanks, by which the latter agreed for $25,000 to construct the new Masonic building or temple in the city of Redding, and work was commenced before the contract was recorded in the office of the county recorder, and is therefore void as against plaintiff. (2) About September 15, 1891, plaintiff entered into an agreement with Confer & Hanks to furnish tin for the roof of said building, gas and water pipes, waiter-closets, sinks, soil-pipes, etc., and to perform the labor of placing all of the material in place for $1,956. Plaintiff completed his contract, and was paid $1,200 on account thereof by the owner of the building, the corporation defendant. The residue of the findings relate to matters going to the validity of plaintiff’s lien, but in no wise affecting the personal liability of the corporation defendant to plaintiff.
We think appellant’s claim that he is entitled to a personal judgment against the corporation defendant cannot be upheld. Plaintiff was a subcontractor, who furnished material
We concur: Belcher, C.; Haynes, C.
For the reasons given in the foregoing opinion the judgment is affirmed.
Reference
- Full Case Name
- GNEKOW v. CONFER
- Status
- Published
- Syllabus
- Mechanics’ Liens—Personal Liability of Owner.—Code of Civil Procedure, section 1183', providing that a building contract shall be void if not filed with plans and specifications, and that in such case the labor done and materials furnished by all persons except the contractor shall be deemed to have been done and furnished “at the personal instance of the owner,” and that the persons furnishing them shall have a lien for their value, does not create a contractual relation between the owner and subcontractor, whereby the owner can be held personally liable for such work and materials, but merely affords an opportunity for a lien by complying with the statute.