Orlandi v. Gray
Orlandi v. Gray
Opinion of the Court
This appeal arises upon the foreclosure of two mechanics’ liens. At the trial the actions were consolidated and a single judgment rendered in favor of plaintiffs. An appeal is taken from that judgment, and also from an order denying the motion for a new trial. Only two questions of any importance are involved.
One of these plaintiffs was to furnish materials and do the staff work upon the building at an agreed price of nine hundred and twenty dollars. The other plaintiff was engaged to do certain sculpture work upon the front of the building at a wage of three dollars per day. The trial court found as a fact that the building was completed upon January 4, 1897, and this finding is now -attacked as without support in the evidence. The building is a large building, and the owner, by herself and tenants, moved into it during the first half of October, 1896. It is now claimed by this appellant that the completion of the building dates from that time by reason of her occupation. This contention is based upon the following provisions of section 1187 of the Code of Civil Procedure: “And in cases of contracts the occupation or use of a building, improvement, or structure by the owner or his representative, or the acceptance by such owner or his agent of said building, improvement or structure, shall be deemed conclusive evidence of completion.”
It is now insisted that the rule of law quoted from the foregoing opinion is obiter. We will not pause to settle that contention. It is immaterial at the present time, for we deem the law there laid down eminently sound. Tested by the principle there declared, the facts of this ease entirely fail to show -an occupation or use by the owner which would start the statute in motion as to the time when liens should be filed; at least, a finding of fact made by the trial court to that effect will not
For the foregoing reasons the judgment and order are affirmed.
Harrison, J., and Van Dyke, J., concurred.
Reference
- Full Case Name
- C. ORLANDI v. MRS. C. M. GRAY, and Others, Defendants LAMBERT J. HAYNE v. MRS. C. M. GRAY, and Others
- Cited By
- 6 cases
- Status
- Published
- Syllabus
- Mechanics’ Liens—Subcontract of Architect—Record—Presumption.—A subcontract in favor of the architect with the contractor,, which was attached to the original contract for the erection of a building, and recorded with it, must be presumed to have been made with the knowledge of the owner of the building; and, in the absence of fraud or deception, the mere dual position occupied by the architect does not ipso facto render either of the contracts void, or preclude the enforcement of liens in favor of persons performing labor and furnishing materials for the subcontractor. Id.—Completion of Building—Occupation by Owner—Subsequent Work—Construction of Code.—The occupation of the building by the owner is conclusive evidence of its completion, within the meaning of section 1187 of the Civil Code, only when it is open, entire and exclusive, and inconsistent with a continuance by the contractor in the completion of his contract, and such as to give notice that the building is accepted in satisfaction of the contract. If the contractor continues the work of construction, or labor is done and materials are furnished, pursuant to the contract, after the occupation by the owner, such occupation is not conclusive evidence of completion, and does not start the statute in motion as to the time when liens should be filed.