Union Oil Co. of California v. Pac. Sur. Co.
Union Oil Co. of California v. Pac. Sur. Co.
Opinion of the Court
Plaintiff, hereinafter referred to as the Oil Company, brought this action to recover upon a surety bond in the sum of fifty thousand dollars, executed by the defendant Pacific Surety Company, hereinafter called the Surety Company, and upon an agreement executed by Carl Leonardt, hereinafter called the indemnitor, to indemnify the Surety Company. The bond was to insure the faithful performance by Weber-Duller Company, hereinafter called the contractor, of a contract dated June 28, 1910, for the construction at San Luis Obispo of two reinforced concrete oil reservoirs for appellant, each of a capacity of one million barrels. That contract, hereinafter referred to as “the contract,” among other things, guaranteed the plan for the reservoirs as well as the proper construction of the work. One reservoir having partially collapsed, and the other having shown indications of weakness when only two-thirds full, by reason of a defective plan and material, plaintiff was damaged to the extent of $286,534.86, as follows: $161,662.57 by reason of defects in said reservoirs; the loss of eighty thousand barrels of oil valued at forty-eight thousand dollars; $76,872.10 by reason of having to pay mechanics’ liens filed on such reservoirs. Judgment was rendered for defendants upon the finding that the time and amount of installment payments fixed in the written contract between the plaintiff and the contractor were not the actual terms of payment, and that the terms and times of such payments were concealed from the respondents at the time of the execution of their respective bonds, and that because of such concealment the respondents were relieved from all liability to appellant. The findings were based upon the conclusion that an agreement, hereinafter called the “side agreement,” signed by the Producers Transportation Company, hereinafter called the Transportation Company, by which the latter company agreed to make “loans” to the contractor in installments equal to ten per cent of the contract price at intervals of fifteen days during the progress
*72
of the work, plus five per cent, one hundred and four days after the first payment (which was to be made when the working crew was organized and work well started on each reservoir), aggregating seventy-five per cent of the contract price, was in fact an agreement of the Oil Company, and consequently modified the contract, which provided for different payments at different stages of the work, as required by the provisions of section 1184 of the Code of Civil Procedure, then in force. The contract being thus modified, it was held that the surety was never advised of the true contract, and because of the fraud involved in such concealment was released from its obligation upon such bond. It is not shown or claimed that Surety Company made any inquiries that called for information as to the side agreement from the contractor who secured the bond, or that the Oil Company ever came into contact with the Surety Company. The bond and contract were attached together and filed with the county recorder, as required by section 1183 of the Code of Civil Procedure.
It is next claimed that if the terms of payment in the contract of the Oil Company were the agreed terms of payment, the payments made the contractor by the Transportation Company in accordance with the side agreement were, in fact, payments by the Oil Company, and that being the case, the Oil Company, by making such premature payments, altered its contract, and thus released the Surety Company. This contention, it will be observed, is based upon the theory that the side agreement was not a part of the original contract and not binding upon the Oil Company. The Transportation Company made the initial payment of ten per cent, amounting to twenty-three thousand dollars, July 7, 1910, to the contractor, and thereupon a promissory note for that amount, payable in thirty days at six per cent, was given by the contractor to the Transportation Company, and an assignment of the payments subsequently to 'become due from the Oil Company to the contractor under the contract was also taken as security, all as provided by the side agreement. It is true that this amount, as well as all subsequent installments called for by the side agreement, were furnished to the Transportation Company by the • Oil Company, as was a total of nearly one million dollars during the five months these reservoirs were being constructed. In case of each ten per cent payment under the side agreement, the Oil Company issued a check for that amount, charging the same on its books to the Transportation Company in its account. The check was then issued by the same officers as officers of the Transportation Company, to the contractor, and his note and assignment taken as above stated. When payments became due under the contract, the amount thereof was credited back to the Transportation Company. The legal effect of the transaction was that the Union Oil Company loaned or paid to the Transportation Company the several amounts of these payments; the Transportation Company loaned the same to
*77
¡the contractor, taking his note in exchange therefor, expecting reimbursement from the Union Oil Company as the work on the contract progressed, in accordance with the assignment made to it of such installment payments. There is nothing fraudulent or immoral in such a transaction. The purpose of the Transportation Company’s side agreement was to facilitate the building of the reservoirs, for, without such payments during the course of the work, it is in evidence that the contractor could not have performed the work and would not have entered into the contract. A sufficient explanation for this circuitous method of financing the contractor is that the contract of the Transportation Company called for sutih advances and that all moneys expended by the Transportation Company were advanced to it by the Oil Company. The payments made by -the Transportation Company in accordance with its separate agreement could not be taken as payment by the Oil Company. This statement, however, leaves unanswered the question as to why the side agreement was entered into in the first instance. Appellant’s contention is that the interest of the Transportation Company in the building of the reservoirs was a sufficient reason for the acceptance by that corporation of the hazard involved in making the advancements required, and this may well be true. The testimony of Mr. Weber, who acted for the contractor, is to the effect that the attorney for the Oil Company insisted upon the payments as specified in the contract with the Oil Company, for the reason that such payments were necessary to comply with the law of California, referring, no doubt, to the Mechanics’ Lien Law. Section 1184 of the Code of Civil Procedure, relating to contracts for improvements which might result in a mechanic’s lien, provided: “No part of the contract price shall, by the terms of any such contract, be made payable, nor shall the same or any part thereof be paid in advance of the commencement of the work, but the contract price shall, 'by the terms of the contract, be made payable in installments at specified times after the commencement of the work, or on completion of specified portions of the work, or on the completion of the whole
work;
provided that at least twenty-five per cent of the whole contract price shall be made payable at least thirty-five days after the final completion of the contract.” It also provided: “No payment made prior to
*78
the time when the same is due, under the terms and conditions of the contract, shall be valid for the purpose of defeating, diminishing, or discharging any lien in favor of any person, except the contractor, but as to such liens, such payment shall be deemed as if not made, and shall be applicable to such liens, notwithstanding that the contractor to whom it was paid may thereafter abandon his contract,” etc. It also provided: “In case such contracts and alterations thereof do not conform substantially to the provisions of this section the labor done and 'materials furnished by all persons except the contractor shall be deemed to have been done and furnished at the personal instance and request of the persons who contracted with the contractor, and they shall have a lien for the value thereof.” The attorney for the Oil Company evidently took" the position that payments in accordance with the side agreement, if included in the contract, would have either invalidated the contract, or so far violated the provisions of section 1184 as to allow all materialmen and laborers liens for their work regardless of the limitation of the contract price. The attorney flatly refused to make alterations of payments in the draft of the contract to conform to the wishes of the contractor, and it was for this reason, apparently, that the side agreement was proposed. It will, therefore, be observed that if the side agreement is treated as a portion of the contract between the parties, the very result which both of the contracting parties were seeking to avoid will, by construction, be accomplished, and they will be held to have entered into a contract which neither of them intended to make. The trial court found that the side agreement “was in truth and in effect a device adopted by the plaintiff and the said contractor to avoid disclosing the actual terms of payment agreed upon between plaintiff and said contractor. ” It is not specifically found that the purpose of the parties was to deceive the Surety Company, although it is found that the terms of payment contained in the side agreement were not disclosed to the Surety Company, and that that company had no knowledge concerning the side agreement at the time it executed its bond, and that "the failure to disclose the true terms of payment “constituted and was a concealment of material facts and circumstances important for said Pacific Surety Company to know, and that the Surety Company was thereby exposed to a risk
*79
and liability greatly in excess of that to which it would have been exposed under the terms of payment set forth in the recorded contract.”
Respondents contend that, even if we assume that the side agreement was the agreement of the Transportation Com *80 pany, and that payments by .the Transportation' Company were not the payments of the Oil Company, nevertheless, the Oil Company made payments to the Transportation Company under the terms of the contract before such payments were actually due thereunder, and that these payments so made by the Oil Company to the Transportation Company of such installments so far altered the contract guaranteed by the Surety Company as to release the surety. From an examination of the record printed in the briefs, however, it does not appear that the defendants counted on these payments in their answers, nor did the court find that they were made. It- appears that the judgment was based upon the payment of the installment of the contract price as provided in the side agreement and at the times therein specified. An examination of the typewritten transcript confirms the contention of the appellant that the decision of the trial court was not based upon the theory of the premature payments by the Oil Company to the Transportation Company.
There remains to be considered the question of the responsibility of the respondent indemnitor, Carl Leonard!. In consideration of the sum of six thousand dollars he executed to the Surety Company a contract of indemnity, by which he agreed “that in consideration of the said Pacific Surety Company becoming surety upon said bond, the said parties of the first part should and would at ‘all times indemnify and keep indemnified and save harmless the said company from and against all loss, costs, damages, charges, counsel fees and expenses whatsoever, which said company shall or may for any cause, at any time sustain, incur or be put to for or by reason, or in consequence of, said company having executed said bond’; and the said parties of the first part in and by the said contract did ‘ further covenant and agree to pay to said company and its representatives, all damages for which said company or its representatives shall become responsible upon the said bond, before said company or its representatives, shall be compelled to pay the same; any sums so paid, however, to be applied to the payment of such damages. ’ ”
The judgment is reversed.
Lennon, J., and Kerrigan, 'J., pro tem., concurred. Hearing in Bank denied.
All the Justices, except Olney, J., concurred.
Reference
- Full Case Name
- UNION OIL COMPANY OF CALIFORNIA (A Corporation), Appellant, v. PACIFIC SURETY COMPANY (A Corporation), Et Al., Respondents
- Cited By
- 5 cases
- Status
- Published