Connecticut Court of Appeals, 1983

North American Philips Controls Corp. v. Precision Timer Co.

North American Philips Controls Corp. v. Precision Timer Co.
Connecticut Court of Appeals · Decided October 14, 1983 · Dannehy, Testo, Borden
467 A.2d 684; 1 Conn. App. 9; 1983 Conn. App. LEXIS 80 (Atlantic Reporter, Second Series)

North American Philips Controls Corp. v. Precision Timer Co.

Opinion of the Court

Per Curiam.

The plaintiff sued the defendant for payment for electric motors sold, delivered to and accepted by the defendant. The defendant admitted the sale, delivery and acceptance, and filed a special defense and counterclaim to the effect that the delivery was untimely. At trial, the parties stipulated that the defendant owed the plaintiff $26,342.19 for the motors delivered and accepted. The sole issue was whether, under the counterclaim, the delivery was untimely, on which the defendant had the burden of proof. The trial court issued a factually detailed memorandum of decision, a fair reading of which is that the defendant did not establish untimeliness. The court rendered judgment for the plaintiff on the complaint in the stipulated amount and for the plaintiff on the counterclaim, from which the defendant appealed. 1

*10 The essential factual findings on the issue of untimeliness of delivery are supported by the evidence and are not clearly erroneous. Practice Book § 3060D; Pandolphe’s Auto Parts, Inc. v. Manchester, 181 Conn. 217, 221-22, 435 A.2d 24 (1980). We have considered the arguments of the defendant on the appeal and find them to be without merit.

There is no error.

1

This appeal, originally filed in the Supreme Court, was transferred to this court. Public Acts, Spec. Sess., June, 1983, No. 83-29, § 2 (c).