Republic Insurance v. Pat Dinardo Auto Sales, Inc.
Cases that cite this one
8 later published cases cite this decision.
- Hyman v. Ford Motor Co. (District Court, D. South Carolina 2001)
- FIRST INDEM. INS. CO. v. Kemenash (N.J. Super. Ct. App. Div. 2000)
- Rivera v. Semac Electric Co., Inc., No. 392642 (Apr. 28, 1999) (Connecticut Superior Court 1999)
- Dowling v. Finley Associates, Inc. (Conn. 1999)
- Tolchin v. Shell Oil Company, No. 388334 (Dec. 16, 1998) (Connecticut Superior Court 1998)
- Fjk Associates v. Karkoski No. Spnh 9707-51408 (Oct. 10, 1997) (Connecticut Superior Court 1997)
- Fjk Associates v. Karkoski, No. Spnh 9707-51408 (Nov. 3, 1997) (Connecticut Superior Court 1997)
- Kearns v. Maresca, No. 301120 (Jul. 3, 1996) (Connecticut Superior Court 1996)
This list shows which later cases cite this one. It does not say how they treated it, and no review of that has been done. Not a substitute for Shepard’s or KeyCite — verify before relying.
Opinion of the Court
The plaintiff, as surety, and the defendants, as principals, executed a surety bond for the completion of subdivision improvements for the town of Monroe by the defendants. The plaintiff executed this bond in consideration for the defendants’ signing an indemnity agreement that provided in part that the defendants would indemnify the plaintiff “from and against any and all liability, loss, costs, damages, attorney’s fees and expenses of whatever kind or nature which [the plaintiff] may sustain or incur by reason or in consequence of executing any such bond or bonds as surety. ...”
The defendants subsequently breached the terms of their contract with Monroe. As a result of that breach, Monroe filed an action against the plaintiff as surety and the defendants as principals on the bond. In accordance with the findings of an attorney trial referee, the trial court rendered judgment against both the plaintiff and the defendants.
In satisfaction and discharge of its obligation under that judgment, the plaintiff paid Monroe $91,000 and then brought this action against the defendants to recover monetary damages pursuant to the indemnity agreement. In rendering judgment in the present case, the trial court awarded the plaintiffs moneys paid under the surety bond, interest, costs and attorney’s fees.
The defendants claim that the trial court improperly (1) concluded that collateral estoppel did not bar the plaintiffs claim, (2) interpreted Public Acts 1993, No. 93-370, and (3) applied Public Acts 1993, No. 93-370, retroactively to its claim.
The judgment is affirmed.