Manson v. New York, New Haven & Hartford Railroad
Manson v. New York, New Haven & Hartford Railroad
Opinion of the Court
This is a libel in personam, for demurrage. On January 21st, 1885, the West Virginia Central & Pittsburgh Railway Company shipped at Baltimore on board the schooner Henry Sutton, of which Gilbert Manson was master and managing owner, and the other libellants were co-owners, 980 tons of coal of 2240 pounds each, to be delivered to the New York, New Haven & Hartford Railroad Company at the “ Consolidated Road Docks,” New Haven, for a specified freight. The railroad company is very commonly called “The Consolidated Road.” The bill of lading contained the following provision in regard to demurrage:
“And twenty-four hours after the arrival at the above named port, and notice thereof to the consignee named, there shall be allowed for receiving said cargo, at the rate of one day, Sundays and legal holidays excepted for every hundred tons thereof, after which the cargo, consignee or assignee shall pay demurrage at the rate of eight cents per ton a day, Sundays and legal holidays not excepted, upon the full amount of cargo, as per this bill of lading, for each and every day’s detention, and pro rata for parts and portions of a day, be\’ond the days above specified, until the cargo is fully discharged; which freight and demurrage shall constitute a lien upon said cargo.”
The Henry Sutton reached Morris Cove, within the entrance to New Haven harbor, on Friday, January 30th, 1885, at 12 o’clock, midnight. On January 31st, 1885, at 2 o’clock P. M., the captain reported to William A. Waterbury, who was then the freight agent of the consignee.
The consignee has three docks: Belle Dock, the Middle Dock, and the Pocket Dock, close to each other, at which coal is delivered. Belle Dock is the largest. These docks are
The coal on board the Henry Sutton was bought for the use of the locomotive engines of the consignee. The largest part of this class of coal is received at the Shop Dock, a small wharf southwest of the passenger depot, and connected with the main channel, three fourths of a mile distant, by an artificial channel which has been dug out within the last five or six years, and which is about ten feet deep at low tide and eighty feet wide. At this wharf are facilities for rapidly discharging a cargo by day and by night.. One vessel only at a time can .lie at the wharf and be discharged. Two vessels can lie at the same time in the basin. Another portion of the coal for the engines of the consignee is delivered at a dock above the drawbridge. A portion of the same class of coal is delivered at Belle Dock.
At this time, on January 31st, the consignee had three cargoes of this class of coal in the port, one, a small cargo, on board the George Aery, which reported on January 30th, and was then discharging at Belle Dock; another on board the Crescent, which reported on January 31st, at 11 o’clock A. M.; and the third on board the Sutton. The Win. O. Snowwas then lying light at the Shop Dock, having discharged her cargo.
At the conversation on January 31st, said Waterbury told Capt. Manson that he must go to the Shop Dock and discharge. The captain replied that he did not think the channel was deep enough for his vessel. Waterbury thought it was. The captain replied that he would try and take his vessel there on the first tide, which would be that night. Waterbury replied that he could not take her in then, as the Crescent was to go in first and they did not want two there at once, as they had had some trouble with two vessels in the basin at the same time.
This conversation was of such importance that I think it desirable to state the reasons for the finding that it took place. Manson testifies positively that he reported to Waterbury on the 31st, was assigned to the Shop Dock, and was pro
The Wm. O. Snow came out and the Orescent went to the Shop Dock on February 1st. On the same day, about 12 o’clock noon, the Sutton was towed to the entrance of the Shop Dock channel. The tides were good and she could have gone up to the Shop Dock basin. On January 31st, the ice was about an inch thick in the channel.. On February 1st, it was broken by rains. On February 2d and thereafter it increased in thickness, and so continued until after February 15th, and a vessel could not get to the Shop Dock unless a tug boat should make a special trip and break the ice in advance.
During the first week of February Manson attempted to contract with the manager of one of the two principal tug boat companies to tow him to the Shop Dock, but was refused, because the manager did not think it safe either for the tug or tow to make the attempt. The Crescent tried to make a contract on February 6th with a tug boat captain, to tow her out, but was unsuccessful. She remained at the wharf frozen in until March 6th.
From January 31st to February 15th the Sutton could easily have gone to Belle Dock, as the main channel was kept open by the daily line of passenger steamboats. The owners of tug boats refused to take her to Belle Dock because Mr. Waterbury had requested them not to do so.
The Crescent was discharged at 2.20 A. M. on Thursday, February 5th. On February 4th Waterbury notified Manson that the Crescent would be discharged on the 5th and that he should want the Sutton on that day. On February 5th Manson saw Waterbury and told him if the Crescent got out he would go in. Waterbury replied that when the Sutton got in he would have the Crescent out. The captain declined to go in until a passage was clear and Waterbury declined to break the ice.
I make no finding in regard to a conversation which Mr. Waterbury and others say occurred on February 2d, which was to the effect that Manson asked for a birth at the Shop Dock and Waterbury told him to go up the channel and Manson declined to go till the Crescent was out of the way, because, in view of the conversation of January 81st, forbiding Manson to go up the channel, and of the fact that on February 2d Waterbury knew that the ice prohibited the vessel from goi.ng up until it was broken, and of the further fact that the condition of the ice was about the same on February 2d as on February 5th, when the Sutton could not get to the wharf by the use of reasonable means, the conversation was not in my opinion of importance.
The Sutton lay at the mouth of the Shop Dock channel until February 15th. Then an arrangement was made between the captain and consignee by which the cargo was delivered at Belle Dock to Williams, Wells & Co., who paid the freight and sold the coal, the captain retaining all his rights to claim demurrage and no claim of either party being waived, relinquished or admitted.
The vessel commenced discharging on February 16th, at one o’clock P. M., and was discharged on February 28d, about 9.15 A. M. If demurrage is to be allowed, it commenced on February 18th at 9.15 A. m. and is due for a period of ten days and amounts to $784.
Under the terms of the bill of lading the Sutton was obliged to discharge at that one of the docks of the consignee
While this is true it is also true that under a bill of lading which requires delivery to be made at a named dock, arrival of the vessel at the dock is ordinarily a prerequisite to demurrage, and delays of the vessel within the port for a considerable time from accidents of navigation without the fault of the consignee, do not require him to receive the freight at another place than that named in the bill of lading. Aylward v. Smith, 2 Lowell, 192; Parker v. Winlow, 7 Ellis & B., 942; Bastifell v. Lloyd, 1 Hurlst. & C., 388; Hodgdon v. N. York, N. Haven & Hartford R. R. Co., 46 Conn., 277.
At the time of the arrival of the Sutton the Shop Dock was designated and was accessible by the aid of a tug and could have been reached without difficulty. But the consignee requested that the vessel should not proceed to the dock, but should wait at the mouth of the channel, three-fourths of a mile distant. If she had voluntarily waited at this point and had been frozen in, the case would present different features; but having waited there at the request of the consignee, and being unable on the 5th, when she was notified that she would be wanted, to obtain a tug to break the ice, and being prevented by the express direction and authority of the consignee from unloading at its accessible dock, the liability of the consignee for demurrage seems to me to be complete.
The accident of navigation which prevented the Sutton from reaching the Shop Dock was encountered by the direc
There should be a decree in favor of the libellants for $784, and interest from February 23d, 1885, and costs.
The case was appealed by the respondent to the Circuit Court, and was there argued by the same counsel. The principal part of the opinion in that court, affirming the decree of the District Court, is here given.
Wallace, J. (After stating the facts). The foregoing are the essential facts upon which the case turns. Demur-rage was allowed by the District Court for a period of ten days, commencing on February 13th, in the sum of $784. The appellant contends that the Sutton was under obligation to proceed to the Shop Dock, that being the place of delivery designated by the consignee, and that no liability for demurrage arises because she had not completed her voyage prior to February 16th, and was not prepared to make delivery of the cargo at the proper place.
The decision of the learned district judge recognized the rule that when a bill of lading designates a particular dock at the port of delivery where the cargo shall be discharged, the carrier can make no claim for demurrage for any detention arising from the state of the elements prior to the arri
The decree below is not one of which the appellant can reasonably complain. If the libellants had appealed, they woidd have been entitled to recover one day’s demurrage more than was allowed by the District Court.
The law undoubtedly is that the obligation of the carrier is not alone to carry the cargo, but is in addition to deliver it at the place of discharge in the port of destination mentioned in the bill of lading; and the consignee incurs no liability for demurrage until such delivery is made or tendered. M’Intosh v. Sinclair, 11 Irish R. (C. L.), 456; Aylward v. Smith, 2 Lowell, 192; Parker v. Winlow, 7 Ellis & B., 942; Hodgson v. N. York, N. Haven & Hartford R. R. Co., 46 Conn., 277. It is equally well settled that where the bill of lading allows a given number of days to the consignee for unloading, a contract is implied on his part that, from the time when the ship is at the usual place of discharge, he will take the risk of any ordinary vicissitude which may occur to prevent the release of the ship at the expiration of the running days. Tiis v. Byers, 34 L. T. (N. S.), 526; Randall v. Lynch, 2 Camp., 352; Cross v. Beard, 26 N. York, 86. The place of discharge designated in this bill of lading was any one of the several docks of the consignee known as the Consolidated Road Docks; and there was no proof of any usage or custom by which any particular one of these docks was to be treated as the place of discharge.
Under this bill of lading the consignee had the right, and
The court below adopted a view more liberal to the consignee. It is plain that until February 3d the master of the Sutton was ready to deliver his cargo, and could have made delivery at any one of the docks of the consignee; but the court found, and the proofs sustain the finding, that the master of the Sutton was induced to delay proceeding to the Shop Dock for the convenience of the consignee, and waited at a place as near that dock as he could get in pursuance of the instructions of the consignee until the ice prevented him from reaching it. He then offered to discharge at another of the docks named in the bill of lading, which was then accessible; but permission to do so was refused by the consignee. Under such circumstances it is not open to fair doubt that the consignee took the risk of any detention of the ship by vis major while it was waiting to get access to the Shop Dock. Tapscott v. Balfour, L. R.., 8 C. P., 46; Jones v. Adamson, 35 L. T (N. S.), 287. The consignee
The decree of the District Court is affirmed, with interest and costs.
Reference
- Full Case Name
- Gilbert Manson and others v. The New York, New Haven & Hartford Railroad Company
- Cited By
- 1 case
- Status
- Published