Ragsdale v. Rodriquez, No. Cv89 0101462 S (Dec. 18, 1990)
Opinion of the Court
The plaintiff then filed a motion for summary judgment claiming that the defendant had failed to comply with General Statutes
The defendant counters by arguing that all three subsections were added to the statute in 1988 by virtue of Public Act 88-269, Sec. 9 and were not in existence in September of 1986 when the contract was entered into.
A court may render summary judgment only if the pleadings, affidavits and other proof indicate that there is no genuine issue of material fact and that the moving party is entitled to judgment as a CT Page 4901 matter of law. Practice Book 384. The movant has the burden of showing that there are no such genuine issues of material fact. Connecticut National Bank v. Great Neck Development Co.,
In 1986 at the time the contract in this case was signed, the provision in the statute requiring that a contract contain the entire agreement of the parties was in existence. General Statutes
Public Act 88-269, Sec, 9, effective October 1, 1988, added subsections 6 and 8 regarding cancellation and registration respectively, and renumbered but did not change the "entire agreement" provision to a new subsection 3. Thus, the motion for summary judgment as to subsections 6 and 8 is denied because these provisions were clearly not in existence at the time the contract was signed.
The remaining question is whether or not there is a genuine issue of material fact as to the contract containing the entire agreement of the parties. The contract provides:
The Contractor shall complete all the work required by the contract and detailed construction drawings, and all miscellaneous work as called for in the drawings and specification, except: masonary work, electrical, including heat on second floor, sheetrock and taping, installation of tile, installation of greenhouse, jacuzzi and fixtures, floor refinishing, exterior and interior painting and no allowance for wet bar.
The defendant points to the presence of the words drawings and specifications as indicating that the contract adequately defined the scope of the work to be performed.
This past June the Supreme Court issued four decisions concerning home improvement contracts, which are cited by the plaintiff as authority for the granting of his motion, but two are clearly inapposite. In both A. Secondino Son, Inc. v. LoRicco,
The closest case is Barrett Brothers v. Miller,
I believe that this contract is less "skeletonic" than the one rejected in Barrett Builders and thus presents a genuine issue of material fact regarding whether or not it adequately defines the scope of the work to be performed, and thus summary judgment is precluded.
SO ORDERED.
Dated at Stamford, Connecticut this eighteenth day of December, 1990.
LEWIS, J.
Case-law data current through December 31, 2025. Source: CourtListener bulk data.