Galer Mechanical, Inc. v. Hastings, No. Cv90-0270280 (Mar. 21, 1991)
Opinion of the Court
On May 11, 1990, the plaintiff moved to cite in Stelco Industries as an additional party defendant and filed an amended complaint alleging that Stelco's lien in the property was subsequent in right to the plaintiff's. The plaintiff filed a second amended complaint on May 18. The court, Jones, J., ordered the plaintiff to summon Stelco as a codefendant on July 10, 1990.
On October 23, 1990, the plaintiff filed a revised complaint which described the subject property and included copies of the agreement between the plaintiff and Fitzpatrick Construction (exhibit A), notice to the defendants (exhibit B), and the mechanic's lien (exhibit C).
On October 29, 1990, the Hastings filed a motion to strike the revised complaint arguing that the plaintiff failed to state a claim for relief and to join an indispensable party. CT Page 2064 The Hastings argue that the complaint is deficient for not alleging that the defendants failed to tender all sums owed. They also argue that the general contractor is an indispensable party. On November 5, 1990, the plaintiff filed an objection to the motion, arguing that the complaint does state a cause of action and that the general contractor is not a proper defendant.
A motion to strike challenges the legal sufficiency of a pleading. Mingachos v. CBS, Inc.,
A. CLAIM FOR RELIEF
The plaintiff has stated a claim on which relief can be granted. Although the plaintiff indeed neglected to state that the Hastings failed to tender all sums due and owing, it did attach a copy of the notice and mechanic's lien against the Hastings' property. See exhibits B and C. Practice Book 141 states: "Where the plaintiff desires to make a copy of any document a part of his complaint, he may, without reciting it or annexing it, refer to it as exhibit A, B, C, etc., as fully as if he had set it out at length." By annexing the lien and notice, although not required to do so, the plaintiff incorporated them as part of the complaint.
The mechanic's lien is governed by Connecticut General Statutes
Because the purpose of a mechanic's lien is to secure payment for services or materials rendered, the court may infer that the plaintiff in the present case sought the lien for amounts due and owing. See Mingachos,
B. GENERAL CONTRACTOR NOT INDISPENSABLE
Connecticut General Statutes
(f) Any such subcontractor shall be subrogated to the rights of the person through whom the subcontractor claims, except that the subcontractor shall have a mechanic's lien or right to claim a mechanic's lien in the event of any default by that person subject to the provisions of sections
49-34 ,49-35 and49-36 , provided the total of such lien or liens shall not attach to any building or its appurtenances, or to the land on which the same stands or to any lot or to any plot of land, to a greater amount in the whole than the amount by which the contract price between the owner and the person through whom the subcontractor claims exceeds the reasonable cost, either estimated or actual, as the case may be of satisfactory completion of the contract plus any damages resulting from such default for which that person might be held liable to the owner and all bona fide payments, as defined in section49-36 , made by the owner before receiving notice of such lien or liens.
"The subcontractors, even though they are second tier . . . are prima facie within the ambit of the mechanic's lien law. It is not necessary to their lien status that they have any direct contractual relationship either with the owner or the general contractor. . . ." Seaman v. Climate Control Corp.,
Mechanic's liens may be foreclosed in the same manner as ordinary mortgages. Connecticut General Statutes
The subcontractor is required to name the general contractor as a party to the action when the latter's encumbrance on the subject property is placed in issue." Upon proper pleading, in an action to foreclose a lien of a CT Page 2066 subcontractor, the amount due the original contractor is a material issue." Pierce, Butler Pierce Mfg. Corp. v. Enders,
The plaintiff in the instant case has not put in issue the amount, if any, owed to the general contractor. In the revised complaint, paragraphs three and four, the plaintiff describes only how it furnished materials pursuant to an agreement with the contractor. The plaintiff has not listed the contractor among the junior encumbrancers identified in paragraphs eight and nine.
The courts have characterized parties "as `indispensable' when they `not only have an interest in the controversy, but an interest of such a nature that a final decree cannot be made without either affecting that interest, or leaving the controversy in such condition that its final termination may be wholly inconsistent with equity and good conscience.'" (Citations omitted.) Sturman v. Sacha,
For the foregoing reasons, the motion to strike is denied.
E. EUGENE SPEAR, JUDGE.
Case-law data current through December 31, 2025. Source: CourtListener bulk data.