Fogg v. Carroll's Home Improvement, No. Cv88 02 47 56s (Apr. 13, 1991)
Opinion of the Court
In reviewing the report of an attorney trial referee the court cannot find additional facts beyond those found in the report unless they are admitted or undisputed. Dills v. Enfield,
The defendant's counterclaim is based upon the second contract between the parties and is unrelated to the plaintiff's claim that the defendant negligently performed the first contract. While the claims of the parties were joined in the same action, they are separate claims. The referee found that the second contract was fully performed by the defendant and, as a result, properly concluded that the defendant was entitled to full payment under the second contract, in the amount of $2,635.33. That contract provided for interest and attorney's fees if the plaintiff defaulted in payment of the amount due under the contract. Since the plaintiff agreed in writing to pay interest and attorney's fees in event of default, the referee properly awarded attorney's fees and interest. The amount of the interest and attorney's fees is not disputed by the plaintiff in the motion to correct the report, and the interest was apparently calculated from 1987 based upon a rate of interest agreed to CT Page 3022 between the parties. Since the plaintiff has not questioned the interest calculation it will not be reviewed.
The plaintiff claims that it was improper for the referee to award attorney's fees and interest on the counterclaim but not on the plaintiff's complaint. The plaintiff further claims that there should be a setoff of the amounts due before the calculation of interest and attorney's fees, and that if this is done the defendant is not entitled to interest and attorney's fees because the $3,750 damages of the plaintiff exceed the unpaid amount on the contract of $2,635.33. The error of this argument is that it tries to subtract apples from oranges. There were two separate claims here, and recovery by the defendant on the second contract is separate and distinct from any amounts the plaintiff may be owed for improper performance of a separate contract between the parties for installation of the siding. The plaintiff could not properly withhold payment for performance of another, completed contract to avoid paying interest he had agreed to pay by asserting a claim that another contract had been negligently performed and setting of liquidated and unliquidated claims.
The motion to correct the report is denied. The motion to accept the report is granted. Judgment may enter in accordance with the referee's report.
ROBERT A. FULLER, JUDGE