Semco Mfg. v. B-G Mech. Contractors, No. Cv93-052 29 90 S (Apr. 22, 1994)
Opinion of the Court
The action is brought in Five Counts. First count is against a subcontractor, B-G Mechanical Contractors, hereafter known as "B-G", alleging unjust enrichment and breach of certain representations made to Semco. The Second Count is against the Hartford Casualty Insurance Company, hereinafter "The Hartford" on a payment bond issued to "B-G" pursuant to Section
The parties jointly filed with the court a "Statement of Undisputed Facts" which the court herewith adopts and repeats as follows:
"Semco fabricated and supplied spiral ductwork for the Somers Special Management Facility project. Annulli was the general contractor for the project with a contract in the amount of $26,114,034.00. USFG issued a labor and material payment bond in the amount of $26,114,034.00 naming Annulli as principal. B-G was the mechanical subcontractor on the project having a subcontract with Annulli in the amount of CT Page 4282 $3,150,000.00. The Hartford issued a subcontract labor and material payment bond in the amount of $3,150,000.00, naming B-G as principal. Concept 2000 was a subcontractor to B-G. Semco originally entered into a purchase order with Concept 2000 in the amount of $95,000.00 to supply the spiral ductwork. Concept 2000 was a subcontractor to B-G. Semco delivered materials to the job site on September 21, September 23 and September 28, 1992. The value of those materials amounted to $29,008.00, and Semco has never received payment for those shipments. The materials were incorporated into the construction project. Concept 2000 filed for bankruptcy on September 23, 1992. After Concept 2000's bankruptcy, Semco and B-G had direct communications about the materials remaining to be delivered under Semco's original purchase order with Concept 2000. These communications resulted in a new purchase order being issued by B-G to Semco on October 23, 1992 in the amount of $65,992.00 for the remaining spiral ductwork. This ductwork was subsequently shipped to the job site and incorporated into the project. B-G has paid Semco for that ductwork in the amount of $65,992.00. At all times relevant to this action, B-G was a direct subcontractor to Annulli.
There is no dispute as to the timeliness or adequacy of notice given by Semco under the respective bonds issued by The Hartford and USFG."
Section
The action against USFG is brought under section
The defendants, USFG and The Hartford, base their opposition to the plaintiff's claims on the allegation that Semco is not a proper claimant under either of these bonds. These defendants divide subcontractors and suppliers into tiers and maintain that the protection of the bond extends only to subcontractors and suppliers in the first two tiers and does not extend to third tier participants. As to the unjust enrichment claim, the defendant, B-G, maintains that the unjust enrichment claim which is briefed by the plaintiff is not the unjust enrichment which was pleaded.
It is the opinion of this court that Semco is a proper claimant under the bond furnished by USFG under the provisions of section
Although useful in describing the relationship of the parties to each other, the defendants and to some extent the plaintiff, have placed undue emphasis on the classification of parties as sub-subcontractors or first, second, third, etc. tier subcontractors. Plaintiff is correct in relying upon the American Masons' decision as determinative under the facts of this case but in doing so it was unnecessary to rely upon the separate contract with B-G for $65,000.00 for the balance of the ductwork. The defendant because of its designation of various tiers and its theory of remoteness has placed undue emphasis upon what it terms "two distinct chains of contractual relations."
The Connecticut Supreme Court in American Masons' does not rely upon various tiers of subcontractors nor the designations of tiers of sub-subcontractors in its analysis of that case. It refers only to subcontractors. The statute upon which the analysis of American Masons' is based, i.e., the combination of section
"Every person who has furnished labor or materials in the prosecution of the work provided for in such contract in respect of which a payment bond is furnished under the provisions of section
49-41 and who has not been paid in full therefor . . . may enforce his right to payment under the bond . . . . Any person having a direct contractual relationship with a subcontractor but no contractual relationship express or implied with the contractor furnishing the payment bond shall have a right of action upon the payment bond . . . ."
It is uncontroverted that Semco furnished materials in the prosecution of the work provided for in the contract for the Somers Special Management Facility in Somers, Connecticut, that Annulli was the general contractor that USFG supplied a payment bond to Annulli under the terms of section
An examination of the USFG contract reveals that despite all of the references in argument to tiers and separate contract claims, etc., the parties to the contract recognized the true intention of section
"Any party, whether a subcontractor or otherwise, who furnishes materials or supplies or performs labor or services in the prosecution of the work under said contract, and who is not paid therefor, may bring a suit on this bond in the name of the person suing, prosecute the same to a final judgment and have execution thereon for such sum or sums as may be justly due."
As in the statute the reference is to subcontractors without reference to tiers or levels.
Despite the reference to a 1958 revision of the Connecticut General Statutes this court finds that the intention of said bond is to reflect the provisions of section
The situation with reference to the bond furnished by The Hartford Casualty is quite a bit different from that of USFG. Although it appears from footnote #2 on p. 6 of the defendants, brief that Annulli intended that the subcontractors furnish a bond similar to that required of it under section
In Count One of the complaint Semco alleges unjust enrichment by B-G Construction, Inc. In paragraph Five and Six of this Count, the plaintiff alleges that B-G requested that Semco continue to furnish materials for the project and represented to Semco that it would pay Semco for all of the material supplied through Concept 2000 and in reliance upon these representations Semco continued to supply materials to B-G for use in the project. As indicated by the defendants, the plaintiff has failed to prove these points. However, despite the fact that the plaintiff has failed to prove these points and did not rely upon them in its brief, this court is of the opinion that the remaining paragraphs in Count One together with the evidence are sufficient to substantiate the claim of unjust enrichment. The plaintiff in its brief correctly recites the basis for the theory of unjust enrichment and that to recover under this theory a party must show (1) that the defendant has benefited from the transaction or has received something in value; and (2) that the benefit was unjust, that is, was not paid for by the defendant, to the detriment of the plaintiff citing Monarch Accounting Supplies, Inc. v. Prezioso,
Judgment may enter for the plaintiff Semco Manufacturing, Inc. against B-G Mechanical Contractors, Inc. under Count One of the complaint.
Judgment may enter for The Hartford Casualty Insurance Company on Counts Two and Three.
Judgment may enter for Semco, Inc. against USFG on both Counts Four and Count Five.
Judgment, may enter for the plaintiff against B-G and USFG on Counts One, Four and Five in the amount of $29,008.00.
The plaintiff filed in timely fashion an offer of judgment in the amount of $26,000.00 which was not accepted within thirty days after such offer was made. Since the plaintiff has recovered an amount greater than the sum certain stated in the offer of judgment it is entitled to 12% annual interest on the amount recovered computed as provided in section
The complaint was received in court on March 22, 1993 and the offer of judgment was received in court on May 25, 1993. Since the offer of judgment was filed within 18 months from the date the complaint was received in court, interest must run from the date that the complaint was filed with the court, i.e., March 22, 1993, a period of 396 days through April 22, 1994. $29,008.00 at 12% for 396 days equals $3,776.60. The total judgment therefore is $32,784.60. Under Section
Plaintiff at the time of trial reserved his right to seek recovery of attorneys fees against USFG pursuant to the provisions of section
Hale, State Trial Referee. CT Page 4288
Case-law data current through December 31, 2025. Source: CourtListener bulk data.