Ingala v. Barlow Water Pump Co., No. 116892 (Jun. 14, 1994)
Opinion of the Court
At hearing, the parties stipulated to the existence of probable cause to sustain the validity of the defendant's lien in the amount of $1,850.00, together with such interest, if any, as may legally accrue thereon. the [The] court adopted this agreement and accordingly found probable cause.
Probable cause having been established, the plaintiffs must prove, by clear and convincing evidence, the lien's invalidity in order to obtain its discharge. Section
Towards that end, the case of Rene Dry Wall v. StrawberryHill Associates, et al,
The Rene Dry Wall case indicates that when progress payments are made to a general contractor for work performed by a subcontractor and the general contractor fails to pay the subcontractor and ultimately defaults entirely, the party making the payments is protected, provided he has acted in good faith and in a reasonable manner.
In the instant case, the plaintiffs have failed to prove their agreement with their builder/general contractor, Donald Sciarretto.
While no mechanics lien may attach to any building in an amount greater than that which the owner has agreed to pay the general contractor for its construction, Section
Even though plaintiffs have shown $77,127.00 in payments made to the builder before receiving notice of defendant's mechanics lien, plaintiffs have not produced clear and convincing evidence establishing the agreed upon price for the building being erected.
Similarly, they fail to show that the sums expended, after Sciarretto's default, to complete the house were reasonable. See Section
In accordance with the foregoing, plaintiff's Application for Discharge of Mechanics Lien is denied.
/s/ West, J. WEST