Windham Properties, Inc. v. Joy, No. Cv 90 0106207 (Apr. 17, 1996)
Opinion of the Court
The defendants filed an answer denying the material allegations of the complaint, and four special defenses. The first special defense contends that although the contract of sale to Windham called for a closing date of May 15, 1987, the plaintiff refused to purchase the premises until two months thereafter, thus abrogating any obligation on the part of the defendants to construct said pond. The second special defense claims that the parties verbally agreed that if the plaintiff sold the subject parcel, the defendants' obligation to construct said pond would terminate. In the third special defense, the defendants allege that the plaintiff changed the construction plans for the pond to increase its size and cost, thereby releasing the defendants from any obligation to construct said pool. In the fourth special defense, the defendants contend that the cost supposedly incurred by the plaintiff greatly exceeded the reasonable and proper cost of constructing the pond in accordance with the plans that the plaintiff and the defendants had originally agreed upon.
This case was referred to Attorney Samuel V. Schoonmaker, III, an attorney trial referee, in accordance with General Statutes §
The attorney trial referee concluded on the basis of the CT Page 3609 above findings of fact that: (1) the obligation of KAJ to build the pond survived the closing and delivery of deed to Windham on July 14, 1987, because it was agreed to in the contract of sale, and referenced in the purchase money mortgage to KAJ; (2) the plaintiff released KAJ from its obligation to build the pond upon the plaintiff's conveyance to Rumar. The referee's conclusion was succinctly summarized in this sentence: "Windham's conduct manifested its assent to the substitution of Peck as the obligor to build the pond." In reaching this conclusion, the referee pointed to the following: (a) Windham failed to reference KAJ's obligation regarding the pond in its deed to Rumar, despite the provision in its contract with Rumar that nothing would survive the delivery of the deed, unless specifically so stated; (b) Windham paid off its purchase money mortgage in full at the Rumar closing even though the pond had not been built and that its agreement with KAJ provided that if the pond was not built after a certain time, the plaintiff could do so itself, which was done, and subtract the cost thereof from its obligation to KAJ, which was not done; and (c) in the escrow agreement with Rumar, the plaintiff specifically referred to Arnold Peck being obliged to construct the pond. The referee recommended that judgment enter in favor of the defendants.
The plaintiff moved to correct the report pursuant to Practice Book § 438. It sought corrections to reflect that: (1) the referee's report purports to be a judicial decision and is hence unconstitutional;5 (2) none of the exhibits in evidence purport to release KAJ from the obligation to build a pond, which obligation the referee found was created by the April 13, 1987 agreement with the plaintiff, and which survived the delivery of the deed by KAJ to the plaintiff; and (3) any purported release by the plaintiff of KAJ's written obligation to build a pond would have to be in writing because of General Statutes §
In response to the motion to correct filed by the plaintiff, the attorney trial referee declined to make any changes in his report or recommendation that judgment enter for the defendants. The plaintiff then filed exceptions to the referee's report pursuant to Practice Book § 439, but the file does not indicate that the plaintiff included a transcript with its exceptions, as required by Practice Book § 439. This means that the referee's findings of fact must stand uncorrected and may not be disturbed. Without a transcript, these findings cannot CT Page 3610 be evaluated to determine whether they find support in the transcript. Hence, the referee's report must be viewed as if no exceptions had been filed. A failure to file valid exceptions constitutes in effect a waiver of the right to "attack the subordinate factual findings contained in the report." SeeBernard v. Gershman,
The plaintiff also filed objections to the acceptance of the referee's report in accordance with Practice Book § 440. The plaintiff's exceptions and objections repeat the arguments in its motion to correct that the plaintiff did not release the defendants' obligation to construct the retention pond.
As to this court's scope of review of an attorney trial referee's report regarding the facts of a given case, the Supreme Court has stated that: (1) the trial court may not "retry the case"; and (2) a court may not find additional facts or reject facts found by the referee unless, in the words of Practice Book § 439, "a material fact has been found without evidence or the [referee] has failed to find an admitted or undisputed fact, or has found a fact in such doubtful language that its real meaning does not appear." Dills v. Enfield,
Therefore, the first issue in a review of an attorney trial referee's report is generally whether there is support in the record for the referee's factual findings. In this particular case, as noted previously, the referee's findings of facts must be and are accepted in total. However, the facts in this case do not seem to be in dispute, but rather the issue is what inferences or conclusions are to be drawn from the various deeds, mortgages, contracts, etc., that were introduced as exhibits.
In addition to determining whether "there was . . . evidence to support the attorney trial referee's factual findings," the second task of the reviewing court is to decide whether "the CT Page 3611 conclusions reached were in accordance with the applicable law."Thermoglaze. Inc. v. Morningside Gardens, Co.,
The contract between the plaintiff and the defendants provided that the latter were obligated to build a retention pond on a certain piece of property for the benefit of the plaintiff. The referee concluded, however, that the plaintiff released the defendants from that obligation based on the three reasons referred to previously. The plaintiff points out that none of these documents actually release KAJ. Specifically, the referee gave as his first reason that when Windham deeded its property to Rumar, it did not refer to KAJ's obligation to construct a pond. The referee is referring to a deed from the plaintiff to a third party, Rumar. Although the deed does not mention KAJ, it also does not purport to release the defendants from their obligations.
The second reason is that Windham paid KAJ the full balance of the purchase money mortgage, even thought KAJ had not built the pond, the inference being that Windham released the defendants from its obligations, or otherwise it would have subtracted its cost in building the pool from the balance due KAJ for the purchase money mortgage as was its right under the original agreement with KAJ. Again, there is nothing in writing that specifically releases KAJ. The third reason offered by the referee is the reference by the defendants in their deed to Arnold Peck's obligation to build the pond. Actually, the reference is to Peck and to "any other person," as pointed out by the referee. It is clear that the defendants cannot be relieved CT Page 3612 of their obligation to Windham by virtue of Peck agreeing with KAJ to construct the pond. This simply means that an additional obligor, Peck, was added to the defendants as bearing responsibility for such construction, but there is nothing to indicate that Peck was substituted for KAJ with the written approval of the plaintiff.
In summary, accepting the facts found by the referee, his conclusion that the plaintiff released KAJ from its obligation to construct the pond in question is not based on any explicit written document, but rather on inferences from certain conduct. The attempt to rely on inference based on certain actions by the plaintiff in its relationship with a third party such as Rumar runs contrary to the requirement of the statute of frauds that agreements concerning land must be in writing.6 In this case, KAJ's obligation to build a pond was an element of the agreement by Windham to purchase the subject parcel from KAJ.
The court finds that the referee's conclusions of law do not follow from his factual findings and that his recommendation for judgment for the defendants therefore cannot be accepted. See Practice Book § 443.
Accordingly, judgment is entered in favor of the plaintiff to recover from the defendants, Joy and Cromie d/b/a KAJ, the sum of $28,000, the cost to the plaintiff of constructing the pond. No evidence was offered by the defendants that this amount incurred by the plaintiff was not a reasonable charge for the construction of the pond.7 Costs are to be taxed by the clerk.
So Ordered.
Dated at Stamford, Connecticut, this 17th day of April, 1996.
William B. Lewis, Judge
Case-law data current through December 31, 2025. Source: CourtListener bulk data.