Robles v. Lyon Billard Co., No. Cv97-0259867s (Nov. 25, 1997)
Opinion of the Court
The court heard the application on November 20, 1997. Defendant's Exhibits A, B and C establish the fact that the materials in question were delivered to the situs of plaintiff's property within 90 days from the filing of the certificate of mechanic's lien and notice.
The evidence permits a finding that the plaintiff owner and a contractor executed a contractual agreement dated February 19, 1997, requiring contractor to construct and provide materials from an addition to plaintiff's dwelling. The contract price to be paid by owner amounted to $30,885.00. Payment was to be made in specified installments with the balance due contractor upon completion. Owner made payments to contractor on February 19, 1997, March 11, 1997, March 27, 1997, April 18, 1997 and April 27, 1997. These payments totalled $31,000. (Plaintiff's Exhibits 2, 3, 4, 5 and 6).
Although the contract was approximately 90 percent completed on April 27, 1997, certain materials detailed in Defendant's Exhibit B ($3,885.65) and Exhibit C ($424.53) had not been delivered or incorporated into the house by that date. Exhibit A ($833.80) appears to have been delivered on April 23, 1997, a few days prior to April 27, 1997.
The contract contemplated a payment of approximately $7,385 upon completion of construction. Unfortunately, owner advanced this final payment well in advance of the completion of construction thus disqualifying it as a good faith payment pursuant to §
Applicant contends that §
The materials were purchased to comply with the owner's specifications, delivered to the owner's premises and incorporated into the owner's building. Seaman v. Climate ControlCorporation,
Inasmuch as the court finds that defendant has established probable cause to sustain the validity of the lien, the application is denied.
Dorsey, J. Judge Trial Referee