Timberland Dev. Corp. v. East Haven P. Z., No. Cv 90297525s (May 9, 1997)
Opinion of the Court
The following facts are taken from the decision in TimberlandDevelopment Corp. v. Planning Zoning Commission,
Timberland appealed, and the trial court, Cretella, J., sustained its appeal in a memorandum dated July 28, 1989, in which it ruled that the commission had improperly considered the application under an incorrect section of the East Haven zoning regulations. The trial court did not order a remand, but rather concluded: "Accordingly, the relief sought by [Timberland] to have the application approved in addition to sustaining the appeal cannot be granted since the commission was entitled to consider under § 27 many of the identical conditions that are set forth in § 32. In future consideration of this matter, the board must be limited to considering only those provisions of § 27 of the zoning regulations." Timberland Development Corp.v. Planning Zoning Commission, Superior Court, judicial district of New Haven, Docket No. 276005 (June 26, 1989, Cretella, J.). CT Page 4934
On September 11, 1989, Timberland filed a "motion in aid of judgment," requesting the court to enter an order "directing the commission to decide [the plaintiff's] application on its merits in accordance with the memorandum of decision in the case and in accordance with the provisions of [§] 27 of the zoning regulations." The trial court denied Timberland's request. Also on September 11, 1989, Timberland requested the commission to set the matter down for a rehearing and reconsideration, and requested notification of the date that it would be on the agenda of the commission. The commission ignored Timberland's request for a rehearing of the previously filed application.
On March 30, 1990, Timberland filed a complaint in the trial court. It alleges three counts against the commission and the individual defendants, Alfred Cronk, Frank Cappeloni, William Lockery, Anthony Bagnoli, Jr. and Ronald Mazzucco, all of whom were members of the commission at the time of its decision in this matter. The first count sounds in tortious interference with contractual relations; the second sounds in negligence; and the third is brought pursuant to
Timberland appealed the decision, and the Appellate Court reversed and remanded for further proceedings on the third-count finding that "[Timberland] was not required under the regulations of the town of East Haven to resubmit its application . . . The trial court incorrectly determined that [Timberland] did `not CT Page 4935 properly request a hearing nor submit an application.'"Timberland Development Corp. v. Planning Zoning Commission,supra,
On February 3, 1997, Timberland filed a motion for summary judgment, as to the third count, accompanied by a memorandum of law and seven exhibits. On February 27, 1997, the commission filed a motion for summary judgment as to the third count accompanied by a memorandum of law.1
Timberland moves for summary judgment solely on the issue of liability on the ground that there is no issue of material fact and that it is entitled to judgment as a matter of law. Timberland further moves the court to order an immediate hearing to ascertain the amount of damages. Timberland argues that its third count claims a deprivation of rights in violation of the
The holding of the Appellate Court is carefully limited. It does not reach as far as Timberland contends. The Appellate Court neither expressly stated nor implied that Timberland had a constitutionally protected property interest in the rehearing. It merely found that Timberland had properly requested a rehearing. Moreover, the trial court's decision did not address the merits of the procedural due process claim. The trial court observed "[t]here can be no procedural due process claim where the plaintiff has failed to initiate its application in accordance with the law . . . [Timberland] did not comply with the procedures of § 27 of the East Haven zoning regulations respecting informal meetings and submissions of documents, and thus did not properly request a hearing or submit an application." Timberland Development Corp. v. Planning ZoningCommission, supra, Superior Court, Docket No. 297525, 14 CONN. L. CT Page 4937 RPTR. 590 at 592. Based on this determination, the trial court granted summary judgment. The Appellate Court concluded that § 27 does not require a party to resubmit a formal application when requesting a rehearing after an appeal is sustained, because after the appeal is sustained the application is still pending before the commission. The court concluded that Timberland properly requested a rehearing and that summary judgment was improperly rendered based on the ground that Timberland did not follow the proper procedure. The Appellate Court then remanded for further proceedings as to count three. The Appellate Court did not apply or discuss the constitutional test applicable in determining whether a plaintiff has been deprived of its constitutional due process rights. The absence of constitutional language strongly suggests that the court's holding applies only in the context of a request for a rehearing after an appeal from the commission is sustained. In addition, the court declared only that Timberland should have been given a rehearing on its pending application. It did not state that Timberland was entitled to an award of damages pursuant to
"The [plaintiffs] claim is one of procedural due CT Page 4938 process . . . [A]n entitlement to procedural due process requires an underlying substantive entitlement or protected property interest." (Emphasis in original.) New England Savings Bank v.Lopez,
"The `clear entitlement' test mandates the possession of a constitutionally protected property interest as a threshold requirement for a successful substantive or procedural federal due process claim . . . If a claimant does not establish a constitutionally protected interest, the due process analysis ceases because no process is constitutionally due for the deprivation of an interest that is not of constitutional magnitude. If, however, a due process claimant does establish a constitutionally protected interest, [the claimant] may then seek to establish other required elements of the due process claim, such as reliance on inappropriate procedures or arbitrary or oppressive conduct. See generally Zinermon v. Burch,
"The `clear entitlement' test asks whether there is a certainty or a very strong likelihood that the application in question would have been granted, but for the wrongful conduct of the local officials . . . A very strong likelihood means not simply a high probability of approval, but rather a virtual assurance of approval because any discretion is narrowly circumscribed . . . Application of the [`clear entitlement'] test must focus primarily on the degree of discretion enjoyed by the issuing authority, not on the estimated probability that the authority will act favorably in a particular case." KelleyProperty Development, Inc. v. Lebanon,
In the present case, Timberland argues that it had a "clear entitlement" to a rehearing for a special permit because the board had no discretion but to schedule a rehearing.
Timberland's purported procedural due process claim is nothing more than its previously rejected substantive due process claim, in a different guise. In making its present procedural due process claim, Timberland claims that its constitutionally protected property interest is its right to a rehearing, and that its damages arise from the commission's refusal to grant a rehearing on its application.4 Timberland argues that because the commission had no discretion to deny the rehearing, it has a constitutional property right in the rehearing. Timberland therefore concludes that the commission is bound by the constitution to provide the rehearing. The plaintiff tries to convert a simple procedural right into a constitutional property right. It cannot succeed. "A party seeking to demonstrate a property interest entitled to protection under the due process clause cannot simply rely upon the procedural guarantees of state law or local ordinance." Double I Limited Partnership v. Plan Zoning Commission,
Since Timberland has failed to establish that it has a constitutionally protected property interest, no process is due. "If a claimant does not establish a constitutionally protected interest, the due process analysis ceases because no process is constitutionally due for the deprivation of an interest that is not of constitutional magnitude." Hunt v. Prior,
For the reasons given above, the court denies Timberland's CT Page 4940 motion for summary judgment as to count three. The plaintiff is not entitled to judgment as a matter of law.
FREEDMAN, J.