Connecticut Superior Court, 1997

Lemarchand v. C. Berry Contractors, Inc., No. Cv97 0160773 S (Jan. 12, 1997)

Lemarchand v. C. Berry Contractors, Inc., No. Cv97 0160773 S (Jan. 12, 1997)
Connecticut Superior Court · Decided January 12, 1997 · MINTZ, J.
1997 Conn. Super. Ct. 12378
Lemarchand v. C. Berry Contractors, Inc., No. Cv97 0160773 S (Jan. 12, 1997)

Opinion of the Court

[EDITOR'S NOTE: This case is unpublished as indicated by the issuing court.]MEMORANDUM OF DECISION RE: MOTION TO STRIKE #102 "Superior Court cases have held that a simple breach of CT Page 12379 contract, even if intentional, does not amount to a violation of [CUTPA. Rather,] a [claimant] must show substantial aggravating circumstances attending the breach to recover under the act. . . . However, the same facts that establish a breach of contract claim may be sufficient to establish a CUTPA violation." (citations omitted; internal quotation marks omitted.) Concom,Inc. v. Redmon Sport, Inc., Superior Court, judicial district of Stamford-Norwalk at Stamford, Docket No. 147896 (Sept. 26, 1996, Mintz, J.).

In the present case, the plaintiffs allege only a simple breach of contract. The plaintiffs fail to allege "substantial aggravating" facts which establish a cause of action for a violation of the Connecticut Unfair Trade Practices Act (CUTPA), General Statutes § 42-110a, et seq.

Count three of the plaintiffs' complaint is legally insufficient. The motion to strike, therefore, is granted.

MINTZ, J.