Rowland Ironworks v. 1200 Post R. E Assoc., No. Cv 97 0156531 (Dec. 4, 1998)
Opinion of the Court
The plaintiff filed a complaint alleging that the defendant 1200 Post Road owns a commercial building located at 1200 Post Road East in Westport, and that it had a written contract dated October 9, 1995, and amended December 27, 1995, with National Video, which occupied a portion of the subject premises, and is described in the lien as "contractors or agents" for 1200 Post Road, to render services and furnish materials for a construction project at the subject premises. The plaintiff further alleges that it rendered services and furnished materials to the defendants between November, 1995 and April, 1996; that the contract price was approximately $29,000; that the defendant National Video had paid the plaintiff approximately $12,000, leaving a balance due of $16,776; and that the plaintiff had filed a mechanic's lien in that amount.
In their answer, 1200 Post Road and National Video, hereafter referred to as the defendants, denied the material allegations of the complaint and asserted a counterclaim with two counts. In the first count, the defendants allege that National Video was in possession of a certain portion of the building at 1200 Post Road East, Westport. which was the location where the plaintiff was to perform its construction services. The defendants contend that the plaintiff breached its contract by failing to perform in a workmanlike manner in accordance with the terms of the contract. The defendants also allege that the plaintiff failed to finish the project in a timely manner. In the second count of the counterclaim, the defendants allege that the plaintiff performed its work in a negligent manner and that the defendants incurred CT Page 14268 "substantial costs above the contract price."
The case was referred to Attorney Sherwood Spelke, an attorney trial referee, in accordance with General Statutes §
The attorney trial referee concluded, on the basis of the above findings of fact, that: (1) the plaintiff was entitled to a foreclosure of its mechanic's lien; (2) the debt as of the date of his report. June 21, 1998, was the contract price, less a deposit of $6,187.25, and less the cost of correction, for a total of $20,771 owed to the plaintiff; and (3) the plaintiff had substantially performed the contract when the defendants breached the contract by terminating the plaintiff's services without justification, and hence the referee recommended that judgment enter for the plaintiff with respect to the counterclaim.
Pursuant to Practice Book (1998 Rev.) § 19-12, the defendants moved to correct the referee's report1 in the following respects: (1) the plaintiff's delay in commencing and finishing the project could not be based on a delay in receiving the shop drawings because the plaintiff was in control of preparing such drawings; (2) the plaintiff breach the contract by not beginning the project until mid-March. 1996, and by not finishing it by the time the defendants terminated the plaintiff's involvement with the project; (3) the referee CT Page 14269 recommended a recovery in an amount greater than that claimed in the mechanic's lien; and (4) the defendants should prevail on their counterclaim as their expert witnesses' testimony was unchallenged.
The attorney trial referee declined to make any changes in his report or recommendations in response to the defendants' motion to correct except to reiterate that the contract did not contain a specific date for completion and, hence, the plaintiff had a reasonable time to do so.
The defendants did not, thereafter, file exceptions to the report as authorized by Practice Book (1998 Rev.) § 19-13.2 However, they did file objections to the report as authorized by Practice Book (1998 Rev.) § 19-14.3 The objections reiterate the claims asserted in the motion to correct and assert that: (1) the plaintiff is not excused from a tardy beginning and a failure to complete the project in a timely manner because of an alleged delay in receiving approval of the shop drawings, as the plaintiff was in control of such drawings; and (2) the defendants presented two experts who testified about the cost of completing the project, but who did not contradict each other as the referee indicated, because they were testifying as to different methods of such completion.
This court's scope of review of an attorney trial referee's report was reiterated by the Supreme Court in Elgar v. Elgar,
Pursuant to Elgar v. Elgar, supra,
Whether the plaintiff performed its contract in a timely and workmanlike manner is a factual determinations that should not be disturbed by this court. In their motion to correct, it appears that the defendants are attempting to substitute their own version of the facts concerning this issue for those of the referee. If the defendants' position were to be accepted, the court, in effect, would be retrying the case and reexamining the credibility of the witnesses. This is not permitted. Argentinisv. Gould,
It is obvious that the referee chose to believe testimony presented by the plaintiff in regard to the quality and timeliness of the work. "In making this explicit factual determination, the attorney trial referee implicitly found certain witnesses to be credible and believable in their testimony. This was precisely his function as a fact finder. The resolution of conflicting factual claims falls within the province of the trial court." (Internal quotation marks omitted.)Griffin v. Planning Zoning Commission,
Additionally, "[g]reat deference is given to the trial court's findings because the trial court is responsible for weighing the evidence and determining the credibility of witnesses." Beizer v. Goepfert,
As to the objections filed by the defendants, it is axiomatic that "[s]ection 440 . . . cannot be used to attack findings of fact." Iroquois Gas Transmission System v. Mileski,
Based on the standard of review outlined in Elgar v. Elgar, supra.
Judgment therefore enters in favor of the plaintiff that its mechanic's lien be foreclosed. The debt as of the date of the referee's report is determined to be $16,776, on the theory that CT Page 14272 the plaintiff cannot recover in a mechanic s lien foreclosure action an amount greater than that set forth in the lien itself. This case should now be claimed for the foreclosure short calendar in order to determine the type and the date of foreclosure, the value of the premises and all other details. Judgment is also entered in favor of the plaintiff with respect to the counterclaim filed by the defendants.
Costs are to be taxed by the office of the chief clerk in accordance with General Statutes §
So Ordered.
Dated at Stamford, Connecticut, this 4th day of December, 1998.
William B. Lewis, Judge
Case-law data current through December 31, 2025. Source: CourtListener bulk data.