Darien Asphalt Paving, Inc. v. Giordano, No. Cv 90 0107529 (Oct. 30, 1998)
Opinion of the Court
The plaintiff filed a complaint containing five counts. In the first count, the plaintiff alleges that on or about December 9, 1988, it entered into a contract with the defendants to perform site work at an unimproved lot owned by the defendants and located at 90 Saugatuck Avenue, Westport. The plaintiff further alleges that it performed excavating, grading and related services at said location between December, 1988, and July, 1989. The plaintiff also alleges that it is owed approximately $27,000, which the defendants have refused to pay, as a result of which the plaintiff filed a mechanic's lien in the Westport land records on October 5, 1989. The plaintiff seeks a foreclosure of this lien, damages and related relief.
In the second count, alleging breach of contract, the plaintiff claims that the defendants were obligated originally to pay $39,500 for the plaintiff's services, but subsequently ordered additional work in the amount of approximately $12,500, for a total of $52,000. The plaintiff alleges that there is a balance due of $27,000.
In the third and fourth counts, the plaintiff alleges "quantum meruit" and "unjust enrichment" on the basis that the reasonable value of its labor and material was $52,000. In the fifth count of the complaint, the plaintiff seeks to set aside as fraudulent a conveyance of premises at 37 William Street in Norwalk from Giordano to his wife, Cecelia Lampitelli, dated March 6, 1988, but not recorded until April 3, 1989. The plaintiff bases this claim on its belief that the defendants do not have sufficient equity to satisfy a judgment against the Saugatuck Avenue property in Westport and that the conveyance of the Norwalk property was intended to hinder Giordano's creditors, including the plaintiff.
The defendants' answer admits that they had an agreement with the plaintiff and that the defendants paid the plaintiff $25,000 based on the agreement, but denies the material allegations of the complaint. The defendants also asserted four special defenses. In the first special defense the defendants claim a breach of contract in that the work by the plaintiff was performed improperly and in an unworkmanlike manner. In the second and third special defenses, the defendants contend that the plaintiff performed its services and supervised its employees and subcontractors in a negligent manner. In their fourth special defense, the defendants claim that in May of 1989, an entity CT Page 12374 known as FGB Paving and Excavating Co.(FGB) took over the work remaining to be done by the plaintiff, but that FGB failed to file a trade name certificate, thus violating both General Statutes §
The case was referred to Attorney Judith Rosenberg, an attorney trial referee, in accordance with General Statutes §
The attorney trial referee concluded, on the basis of the above findings of fact, that: (1) the defendants owe the plaintiff $19,062; (2) the defendants are obliged to pay statutory prejudgment interest pursuant to General Statutes §
Pursuant to Practice Book (1998 Rev.) § 19-12, both the plaintiff and the defendants moved to correct the referee's report.2 The plaintiff asked the referee to: (1) add a recommendation that the plaintiff's mechanic's lien be foreclosed; (2) recommend an award of attorney's fees based on the language of both the proposal submitted to the defendant dated December 2, 1988,3 and the tickets for extras signed by defendant Dudek;4 and (3) recommend attorney's fees based on General Statutes §
The defendants' motion to correct sought the addition of findings that: (1) the plaintiff had agreed that it would reimburse the defendants for the topsoil removed from the subject premises at the rate of $17 per yard, and that the plaintiff had removed 594 yards, which was worth $10,098; and (2) the cost for the plaintiff of blasting was not $6,939, but rather only $1,347.
The attorney trial referee declined to make any changes in her report or recommendations in response either to the plaintiff's or to the defendant's motion to correct.
In accordance with Practice Book (1998 Rev.) § 19-13, the defendants thereafter filed exceptions to the referee's report.5 The exceptions relate to the referee's refusal to make the corrections to her report sought by the defendants in their motion to correct regarding the removal of topsoil and the cost of blasting.
The defendants also filed objections to the report as authorized by Practice Book (1998 Rev.) § 19-14.6 The objections are similar to the motion to correct and involve the defendants' claims that: (1) they were entitled to compensation CT Page 12376 for the topsoil removed by the plaintiff from their lot; (2) the defendants were obliged to spend $2,200 to purchase topsoil that the plaintiff had removed from their lot; (3) they were overcharged for blasting performed by the plaintiff because the invoice in question includes items that were not part of blasting; and (4) the plaintiff was not entitled to interest based on General Statutes §
Thereafter, this matter appeared on the law or motion calendar for judgment on report and objections thereto.7
This court's scope of review of an attorney trial referee's report was reiterated by the Supreme Court in Elgar v. Elgar,
Pursuant to Elgar v. Elgar, supra,
The only issue that the plaintiff contests relates to "the ATR report . . . that the documents do not support a claim for attorney's fees." As noted previously, the referee left the decision regarding attorney's fees to the court because it involves the applicability of a statute, General Statutes §
Regarding the defendants' exceptions and objections, the first issue is the matter of topsoil. The referee found that the plaintiff and defendants did not agree that the plaintiff was obliged to pay for the topsoil it removed from the defendants' lot. The transcript furnishes support for this finding.8 Regarding the cost of blasting, the plaintiff submitted an invoice dated January 30, 1989 for blasting in the amount of $6,939, which justifies the referee's addition of this amount to that owed by the defendants.9
Both the issues of topsoil and blasting are factual determinations that should not be disturbed by this court. In their motions to correct and exceptions, it appears that the defendants are attempting to substitute their own version of the facts concerning these two issues. If the defendants' exceptions were sustained, the court in effect would be retrying the case and reexamining the credibility of the witnesses. This is not permitted. Argentinis v. Gould,
The transcript certainly contains testimony that is contrary to the referee's findings regarding the payment for topsoil. It is obvious, however, that the referee chose to believe testimony presented by the plaintiff. "In making this explicit factual determination, the attorney trial referee implicitly found certain witnesses to be credible and believable in their testimony. This was precisely his function as a fact finder. The resolution of conflicting factual claims falls within the province of the trial court."Nor'easter Group, Inc. v. Colossale Concrete, Inc., CT Page 12378
Additionally, "[g]reat deference is given to the trial court's findings because the trial court is responsible for weighing the evidence and determining the credibility of witnesses." Beizer v.Goepfert,
In addition, findings of fact in a contract action should be overturned "only when they are clearly erroneous." WilcoxTrucking, Inc. v. Mansour Builders, Inc.,
The defendants also dispute the recommendation of the referee that interest be awarded pursuant to General Statutes §
Based on the standard of review outlined in Elgar v. Elgar,supra,
This case should now be claimed for the foreclosure calendar in order to determine the type and date of foreclosure, value of the premises, and other details. Judgment is also entered in favor of the plaintiff with respect to the counterclaim filed by the defendants, with the matter of attorney's fees to be held in abeyance pending the hearing.
Costs are to be taxed by the office of the chief clerk in accordance with General Statutes §
So Ordered.
Dated at Stamford, Connecticut, this 30th, day of October, 1998.
William B. Lewis, Judge
Case-law data current through December 31, 2025. Source: CourtListener bulk data.