Plotkin v. Leblanc, No. Cv99 0170972 S (Nov. 26, 1999)
Opinion of the Court
2. At the said closing the parties entered into an "escrow agreement" whereby the buyers placed the sum of $6,500.00 in escrow with the plaintiff to secure the payment of the completed items. CT Page 14984
3. On November 18, 1999, a hearing was conducted by the court on the said escrow.
4. After said hearing the escrow funds are ordered distributed as follows:
a. Bill of costs to Ellery Plotkin, $279.00
b. Peter LeBlane and Kerry Hanlon (hereinafter known as"LeBlanc") for unfinished painting, $450.00 for improvements in asphalt driveway $250.00 for unfinished fencing $350.00 and to complete landscaping $200.00 _______
Total $1,250.00
c. By balance of escrow funds to 828 Development Co., LLC $4,970.00
So Ordered.
HICKEY, J.
Case-law data current through December 31, 2025. Source: CourtListener bulk data.