Atlas Const. Co. v. Amity Regional Sch., No. Cv97 0405442 (Mar. 25, 1999)
Opinion of the Court
On October 2, 1998, the defendant filed a motion to strike counts two through ten of the plaintiff's revised complaint. Pursuant to Practice Book §
"The purpose of a motion to strike is to contest . . . the legal sufficiency of the allegations of any complaint . . . to state a claim upon which relief can be granted. (Internal quotation marks omitted.) Peter-Michael, Inc. v. Sea ShellAssociates,
Counts Two through Ten
The defendant moves to strike counts two through ten of the plaintiff's revised complaint on the ground that they "improperly cumulate damages by incorporating from prior counts independent claims for damages [and] should be stricken or modified to exclude the cumulative clauses." (Motion to Strike, filed 10/2/98, p. 2.) In its supporting memorandum, the defendant contends that the plaintiff improperly incorporates damages "from the preceding count or counts" in counts two through ten, but that "[t]he effect of this accumulation is to multiply the potential of [its] recovery beyond what is legally sufficient." (Def.'s Mem., Supp., filed 10/2/98, p. 6.) The defendant then enumerates the specific paragraphs within each count that it seeks to have stricken.The plaintiff argues that the "[r]evised complaint does not cumulate damages. . . ." (Pl's Mem. Opp., filed 10/28/98, p. 12.) The plaintiff specifies the different damages it seeks in each of the counts and it concludes that each successive count does not cumulate the previous count's damage claim. The plaintiff also argues that a motion to strike based on said "cumulative damages" is not proper as it is not specifically delineated in Practice Book §
As a threshold matter, the court addresses the plaintiff's argument that a motion to strike based on "cumulative damages" is not proper because its not specifically delineated in Practice Book §
The court next considers the defendant's argument that the "cumulative damages" asserted in counts two through ten CT Page 3405 should be modified. The defendant may not to strike counts two through ten because these counts "should be . . . modified." "A request to revise, and not a motion to strike, is the proper procedural device for deletion of duplicative pleadings."Federal National Mortgage Assoc. v. Spooner, Superior Court, judicial district of Ansonia/Milford at Milford, Docket No. 055501, (January 7, 1998, Curran, J.).
Finally, the court considers the defendants argument that counts two through ten should be stricken because no cause of action exists for which a party may recover "cumulative damages." The plaintiff has not cumulated its damages. The plaintiff begins its revised complaint by setting out in count one, the background leading to execution of the construction contract; then, the plaintiff makes a claim in count one for the unpaid balance of the contract. In each successive count, the plaintiff incorporates the whole of the preceding count, including the preceding counts prayer for relief. While it is accepted practice for parties drafting complaints to use the "incorporation by reference" tool to avoid complete reiteration of facts set out in prior counts, these parties typically only incorporate facts, and do not, as the plaintiff does in its revised complaint, incorporate a prior count'sprayer for relief.1 However, the court's research has not revealed a rule which specifically proscribes incorporating a prior count's prayer for relief. The court also notes that it is constrained to construe "the facts in the complaint most favorably to the plaintiff." Faulkner v. United TechnologiesCorp. , supra,
The defendant's motion to strike counts two through ten on the ground that they improperly cumulate damages is denied.
Counts Two through Five and Seven
The defendant also moves to strike counts two through five and count seven on the ground that they fail to state valid claims because these counts "improperly multiply [the plaintiff's] single legal theory of breach of contract and should be stricken or merged into a single breach of contract count." (Motion to Strike, p. 1.)The plaintiff counters that the defendant is improperly using CT Page 3406 the motion to strike to obtain revisions to the revised complaint.
The essence of the defendant's argument is that counts two through five and seven are repetitive. "A request to revise, and not a motion to strike, is the proper procedural device for deletion of duplicative pleadings." Federal National MortgageAssoc. v. Spooner, supra, Superior Court, Docket No. 055501. The defendants motion to strike counts two through five and seven is denied.
Count Six
The defendant moves to strike count six on the ground that it alleges "a pass-through" claim of [the plaintiff's] subcontractor, United Steel, . . . and there is no privity of contract between United Steel and [the defendant]." (Motion to Strike, p. 7.) The defendant cites a provision of the construction contract which specifically excludes a contractual relationship between the defendant and the subcontractor.2 Count six of the plaintiff's revised complaint alleges the following: "As a result of the [defendant's] breaches of contract and warranty as aforesaid, [the contractor] is liable to the [subcontractor] for its costs, expenses and damages arising therefrom." (Revised Complaint, filed 9/15/98, ¶ 30, p. 11.)The defendant also argues that count six violates public policy as the plaintiff is attempting to shift its costs from the asserted breach of contract and warranty to the defendant. The defendant asserts that these costs are compensable by the bond which the plaintiff was required to post, pursuant to the "bid documents, which were incorporated into the [construction] [c]ontract." (Motion to Strike, p. 8.)
The plaintiff argues that count six is a legally sufficient claim because allegations that the plaintiff, a contractor, is liable to United Steel, its subcontractor, create a legally sufficient claim against the defendant.
"It is a fundamental concept of judicial administration that no person is entitled to set the machinery of the courts into operation unless for the purpose of obtaining redress for an injury he has suffered or to prevent an injury he may suffer. . . ." Wexler Construction Co. v. Housing Authority,
In Walter Kidde Constructors. Inc. v. State, supra,
Count six alleges that as a result of the defendant's breaches, the plaintiff's subcontractor, United Steel, suffered financial harm and has made a claim against the plaintiff for damages. The plaintiff further alleges that the plaintiff is liable to United Steel for its damages. The plaintiff has set forth a legally sufficient claim by a plaintiff-contractor for damages sustained by the subcontractor because in said claim, the plaintiff-contractor expressly alleges its liability to its subcontractor. A contract does not need to exist between the plaintiff and United Steel.
The court will not consider the defendants public policy argument as it refers to facts outside the pleadings, facts contained in the bid documents, and thus constitutes a speaking motion to strike. Doe v. Marselle,
The defendant's motion to strike count six is denied. CT Page 3408
Count Nine
The defendant also moves to strike count nine on the ground that it fails to state valid claim for punitive damages. The defendant notes that this ninth count incorporates the eighth count, which in its turn, incorporates every preceding count of the complaint. The defendant reasons that as "[a]ll ten counts of the [c]omplaint sound in contract [and as] there are no allegations of negligence or tortious conduct"; (Motion to Strike, p. 12); the plaintiff's allegation, in count nine, that these acts and omissions "were willful, wanton, reckless, malicious and oppressive" is conclusory, for "nowhere in its [c]omplaint does it describe the nature of [the defendant's] acts and omissions. Merely categorizing [the defendant's] alleged acts and omissions in plain, generalized assertions (willful, wanton) in order to claim punitive damages, is not adequate. . . ." (Motion to Strike, p. 14.)The plaintiff argues that count nine is legally sufficient because it alleges that the defendant's conduct was "willful, wanton, reckless, malicious and oppressive," language which Connecticut caselaw has found to support a cause of action for recovery of punitive damages. See L.F. Pace Sons. Inc. v.Travelers Indemnity Co.,
"Punitive damages are not ordinarily recoverable for breach of contract." Barry v. Posi-Seal International, Inc.,
As a threshold matter, research reveals only one reported case, L.F. Pace Sons, Inc. v. Travelers Indemnity Co., supra,
The trial court allowed punitive damages, and the appellate court affirmed, reasoning that the complaint disclosed "allegations of tortious misconduct by the defendant in its refusal to furnish the payment and performance bonds in violation of its implied contract after issuing the bid bond on the . . . project. In substance, the plaintiff alleges therein malicious and wanton misconduct." L.F. Pace Sons. Inc. v.Travelers Indemnity Co., supra,
The allegations of the instant complaint do not rise to the level of the allegations contained in L.F. Pace and Sons, Inc.v. Travelers Indemnity Co., supra. The gravamen of the injury asserted in the L.F. Pace case was that the defendant maliciously destroyed the plaintiff's business opportunity in the construction contract. This destruction malicious because of the nature of a bid/performance bond contract. The surety knew, because of standard business practice, that the plaintiff-contractor, its client, could only obtain and maintain the construction contract if the bid and performance bonds were issued. In the present case, by contrast, the plaintiff fails to set out facts showing either a specific tort or "outrageous conduct . . . done with a bad motive or with a reckless indifference to the interests of others." L.F. Pace Sons. Inc.v. Travelers Indemnity Co., supra,
The defendant's motion to strike count nine, its claim for punitive damages, is granted.
For the foregoing reasons, the motion to strike is granted as to count nine. The motion to strike is denied as to counts two through eight and ten.
John W. Moran, Judge
Case-law data current through December 31, 2025. Source: CourtListener bulk data.