Donohue v. Greenwich, No. Cv97-0260802-S (Sep. 25, 2002)
Opinion of the Court
The Town through memorandum filed August 20, 2002, has objected to the plaintiffs motion to amend. On September 17, 2002, the plaintiff filed with the court a reply memorandum to the objection. Thereafter, on September 20, 2002, the Town filed a surreply. The case is currently scheduled for jury selection on November 4, 2002. In addition, a motion for summary judgment is now pending.
Pursuant to Practice Book §
The Supreme Court in Connecticut National Bank v. Voog,
"While our courts have been liberal in permitting amendments; . . . this liberality has limitations. Amendments should be made seasonably. Factors to be considered in passing on a motion to amend are the length of delay, fairness to the opposing parties and CT Page 12125 the negligence, if any, of the party offering the amendment. . . . The motion to amend is addressed to the trial court's discretion which may be exercised to restrain the amendment of pleadings so far as necessary to prevent unreasonable delay of the trial. . . . It is within the discretion of the trial court to grant or deny an amendment, and a decision to deny an amendment during a trial will not be disturbed unless there is a clear abuse of that discretion." (Citations omitted, internal quotation marks omitted.)
The court having evaluated the parties positions in light of the factors to be considered, grants the plaintiff leave to amend the complaint. The Town may move the court for costs which may be occasioned by the amendments.
BY THE COURT
___________________ Peter Emmett Wiese, Judge