Hill v. Mathewson
Cases that cite this one
3 later published cases cite this decision.
- Walton v. Dayton Hotel Co. (Wis. 1931)
- Banking Center v. Goodrich (Connecticut Superior Court 1976)
- Banking Center v. Goodrich (Connecticut Superior Court 1976)
This list shows which later cases cite this one. It does not say how they treated it, and no review of that has been done. Not a substitute for Shepard’s or KeyCite — verify before relying.
Opinion of the Court
The plaintiff, a lumber dealer, contracted with one Sanger, a builder, who had contracted with the defendant to build for him a house and barn, to furnish lumber for the erection of the buildings. He commenced furnishing materials on the 26th day of May, 1885, and continued so to do under the same agreement until the first day of October. Not being paid m full, on the 9fch day of October he gave the defendant written notice that he commenced furnishing materials on the 26th day of May and ceased doing so on the 1st day of October; that the value of the
In an action to enforce the alleged lien the Court of Common Pleas rendered judgment for the defendant and the plaintiff appealed.
The plaintiff now abandons his claim for $341.37, and claims only to recover the .amount furnished after August 11th—$155.96.
The statute (Gen. Statutes, § 3020), is as follows:—“ No person other than the original contractor for the building, or a sub-contractor whose contract with such original contractor is in writing, and has been assented to in writing by the other part}'- to such original contract, shall be entitled' to claim any such lien, unless he shall, within sixty days from the time he shall have commenced to furnish materials or render services, give written notice to the owner of such building that he has so commenced to furnish materials or render services, and intends to claim a lien therefor on said building,” etc.
There is no uncertainty and no ambiguity about this language. The plaintiff has told us, in language not to be mistaken or misunderstood, when he commenced to furnish materials, and this court is not at liberty to say that he commenced on each and every day thereafter so long as he continued to furnish them. That would be a perversion rather than a construction of the statute, which required notice to be given within sixty days next following May 26th. It was not in fact given until October 9th, eight days after the plaintiff ceased furnishing materials. No argument can make it plainer that that was not a compliance with the statute.
In one of three ways only can the plaintiff’s claim be sus
Can we, without distorting the facts,.regard the commencement as August 11th? The record shows that the plaintiff’s claim arose from one, and only one,- contract with Sanger. There was not a separate contract for each load, or each day’s, week’s or month’s supply. Any attempt to regard the supplies furnished before August 11th as under one contract, and those furnished after that date as under another, is unwarranted. All were furnished under the same agreement, and the commencement was May 26th.
The supplies furnished by the plaintiff amount to $1,155.50. Of that amount the sum of $814.13 has been paid. If we allow the plaintiff’s claim we must apply all the payments to the materials furnished before August 11th; or, what is the same thing, we must assume that no portion of those furnished after that date have been paid for. That is to say, the law will make an application of payments, not to one of
There is no error in the judgment complained of.
In this opinion the other judges concurred.