College Plaza, Inc. v. Harlaco, Inc.
Cases that cite this one
18 later published cases cite this decision.
- Frager v. Pennsylvania General Insurance (Conn. 1967)
- Scinto v. Sosin (Conn. App. Ct. 1998)
- Connecticut Dep. of P. W. v. Saturn Cons., No. Cv 96 0556963 (Apr. 10, 1996) (Connecticut Superior Court 1996)
- Cfc Greenwich Realty Devel. v. Gabelli, No. Cv 91-0115071 S (May 3, 1991) (Connecticut Superior Court 1991)
- Bio-Polymers, Inc. v. D'Arrigo (Conn. App. Ct. 1990)
- Security Insurance v. DeLaurentis (Conn. 1987)
- Paranko v. State (Conn. 1986)
- John A. Errichetti Associates v. Boutin (Conn. 1981)
- Ramos Iron Works, Inc. v. Franklin Construction Co. (Conn. 1978)
- Board of Education v. Frey (Conn. 1978)
- City of Hartford v. Local 308 (Conn. 1976)
- Gary Excavating, Inc. v. Town of North Haven (Conn. 1972)
- A. Sangivanni & Sons v. F. M. Floryan & Co. (Conn. 1969)
- Kantrowitz v. Perlman (Conn. 1968)
- Carter, Morse Co. v. Perrotti, No. Cv97-0407162 (Feb. 2, 1998) (Connecticut Superior Court 1998)
- Automated Salvage Tr. v. Auto. Co. Rec., No. Cv-95-0465819-S (Jun. 1, 1995) (Connecticut Superior Court 1995)
- Dwan v. Gardella, No. Cv91 28 55 58 (Oct. 23, 1991) (Connecticut Superior Court 1991)
- Fair Street Foundry Assoc. v. Nash, No. Cv-91-0310706s (Nov. 1, 1991) (Connecticut Superior Court 1991)
This list shows which later cases cite this one. It does not say how they treated it, and no review of that has been done. Not a substitute for Shepard’s or KeyCite — verify before relying.
Opinion of the Court
The defendant, which constructed a shopping center for the plaintiff, has appealed from a judgment directing it to proceed with the arbitration of a dispute which arose when water damage occurred, allegedly from faulty construction. The defendant contends that the plaintiff is not entitled to arbitration since the contract required that the plaintiff first obtain a ruling by the architect and also that the claim be presented within a year from the completion of the work. The court ruled that these were questions to be determined by the arbitrators and not by it.
Whether the arbitrability of a dispute is a question for the court or for the arbitrators depends upon the language of the contract. The agreement in the present case provided that “[a]ny disagree
There is no error.