Finca Santa Elena, Inc. v. United States Army Corps of Engineers

District Court, District of Columbia

Finca Santa Elena, Inc. v. United States Army Corps of Engineers

Opinion

UNITED STATES DISTRICT COURT FOR THE DISTRICT OF COLUMBIA

FINCA SANTA ELENA, INC., et al.,

Plaintiffs,

v. Case No. 1:11-cv-00296 (CRC)

U.S. ARMY CORPS OF ENGINEERS, et al.,

Defendants.

MEMORANDUM OPINION AND ORDER

Plaintiffs in this case own property and conduct environmental research and conservation

activities along the Rio de la Plata in northern Puerto Rico. For decades, the Army Corps of

Engineers has been studying, planning, and partially constructing a flood control project to protect

residential areas within the river’s floodplain. Fearing that the project will diminish their use and

enjoyment of the area, as well as their property values, plaintiffs filed suit to enjoin further

construction. They also seek a declaration that the Corps and its Chief of Engineers violated the

Clean Water Act (“CWA”), the National Environmental Policy Act (“NEPA”), the National

Historic Preservation Act (“NHPA”), and the Administrative Procedure Act (“APA”), as well as an

order invalidating the approvals and statutory findings associated with the project. The Court

previously granted the Government’s partial motion to dismiss all claims challenging any part of

the project other than its most downstream portion (“Phase 1A”)—the only phase of the project that

has ever received Congressional appropriations. Both sides now move for summary judgment.

Because the Corps has completed virtually all construction on Phase 1A and has represented that it

will conduct further administrative and environmental reviews before any work on future phases of

the project takes place, the Court will deny both motions and dismiss this case as prudentially moot. I. Background

A. Factual Background 1

The Corps has been studying, designing, and planning the Rio de la Plata flood control project

since 1942. Defs.’ Mot. to Dismiss at 13. Yet, the only construction funding the project has ever

received is a one-time congressional appropriation for its most downstream portion, Phase 1A, as

part of the American Recovery and Reinvestment Act (“ARRA”) of 2009. First Am. Compl. ¶ 148.

According to the uncontested declaration of Gregory Schulz, Chief of the Construction Division for

the Corps’ office that oversees Puerto Rico, Phase 1A was approximately 85 percent complete as of

August 2014, with “all major Project features for flood control purposes” on schedule for

completion by October 2014 and all remaining work by January 2015. Defs.’ Supplemental Mem.

in Supp. of Defs.’ Cross-Mot. for Summ. J., Decl. of Gregory Schulz ¶¶ 6–7. Plaintiff Finca Santa

Elena, Inc. is a Puerto Rico corporation that owns property located within the project’s footprint,

including an 18th century sugar mill that is listed on the National Register of Historic Places. First

Am. Compl. ¶¶ 10–13. Plaintiff Román Más Foundation is a non-profit organization dedicated to

preserving and protecting Puerto Rico’s natural and cultural resources, including its rivers and

wetlands. Id. at 18–19. Plaintiff Angel Román Más resides in Puerto Rico and claims to visit the

Rio de la Plata approximately once or twice a month for recreation and study. Id. at 28–30.

Plaintiffs (“Finca and Román Más”) have not disputed sworn statements by the Corps that it will

conduct additional administrative and environmental reviews before beginning any additional

phases of the project, just as the Corps has done “on many occasions over the years before Phase

1A even began construction.” Mem. Op. July 9, 2012 at 10. And counsel for the Corps represented

to the Court at the most recent hearing that “nothing further will happen without” additional

1 See Mem. Op. July 9, 2012 at 2–4 for a more detailed review of the lengthy factual history of this project. 2 assessments of environmental law and historic preservation compliance. Hr’g Tr. 23: 6–20, Oct.

15, 2014. These assessments will include, according to counsel, “another [Environmental

Assessment] and [Finding of No Significant Impact] at a minimum” as “[t]hat’s the way the Corps

has handled it before and repeatedly.” Id.

B. Procedural Posture

Finca and Román Más filed their initial complaint in February 2011. They amended the

complaint in June 2011. A year later, Judge Wilkins, who previously oversaw the case, granted the

Government’s partial motion to dismiss all claims challenging any portion of the project beyond

Phase 1A. The parties’ cross-motions for summary judgment became ripe in May 2013. After the

case was reassigned to this Court in April 2014, the Court requested a report on the “status of the

‘Phase 1A’/‘ARRA’ flood control project and the impact, if any, of the project’s current status on

the Plaintiffs’ requested relief.” After receiving the status report and holding a status conference on

August 6, 2014, the Court ordered supplemental briefing on whether the progress of Phase 1A

rendered the case moot. The Court held a hearing on that question on October 15, 2014.

II. Standard of Review

The party raising the issue bears the burden of establishing mootness, “and it is a heavy

burden.” Fund For Animals v. Williams,

311 F. Supp. 2d 1, 6

(D.D.C. 2004) aff’d sub nom. Fund

For Animals, Inc. v. Hogan,

428 F.3d 1059

(D.C. Cir. 2005). Article III limits federal courts to

resolving actual cases or controversies; it “prevents their passing on moot questions—ones where

intervening events make it impossible to grant the prevailing party effective relief.” Burlington N.

R. Co. v. Surface Transp. Bd.,

75 F.3d 685, 688

(D.C. Cir. 1996) (citing Church of Scientology v.

United States,

506 U.S. 9, 11

(1992)). For a federal court to adjudicate a case, “‘an actual

controversy must be extant at all stages of review, not merely at the time the complaint is filed.’”

Arizonans for Official English v. Arizona,

520 U.S. 43, 67

(1997) (citations omitted). The doctrine

3 of prudential mootness refers to the discretion enjoyed by federal courts in exercising their Article

III powers. Penthouse Int’l, Ltd. v. Meese,

939 F.2d 1011, 1019

(D.C. Cir. 1991). The doctrine

“permits the court in its discretion to ‘stay its hand, and to withhold relief it has the power to grant’

by dismissing the claim for lack of subject matter jurisdiction.” MBIA Ins. Corp. v. F.D.I.C.,

708 F.3d 234, 245

(D.C. Cir. 2013) (quoting Chamber of Commerce v. Dep’t of Energy,

627 F.2d 289, 291

(D.C. Cir. 1980)). A court may declare a case prudentially moot when “[t]he precise conduct

that prompted th[e] suit . . . has come to an end” and the plaintiff will have “ample opportunity . . .

to renew their complaint.” Chamber of Commerce,

627 F.2d at 292

.

III. Analysis

There is no dispute that the central question in this lawsuit is whether the Corps satisfied its

NEPA and CWA obligations in deciding to proceed with Phase 1A of the project after receiving

funding under ARRA. See Finca and Román Más’s Mot. for Summ. J. at 9 (describing the “ARRA

project” as “the subject of this litigation”). Because Phase 1A of the project is now essentially

complete, however, the Court cannot provide effective relief regarding the subject of this litigation.

The Court therefore concludes that the case is prudentially moot.

A. Injunctive Relief

Finca and Román Más argue that “[e]ven if . . . Plaintiffs choose not to seek[] an injunction

requiring the Corps to undo or modify the ARRA project, the mere fact that this injunctive relief

remains available defeats a claim of mootness.” Pls.’ Response to Defs.’ Supplemental Mem. at 6–

7. Yet, Finca and Román Más do not actually seek such an injunction. As their counsel

acknowledged at the hearing: “We’re not seeking [deconstruction of the project.]” Hr’g Tr. 12:

11–12, Oct. 15, 2014. Instead, they argue that the mere existence of hypothetical relief should

defeat the Government’s mootness argument. As the Fifth Circuit has found, however,

“theoretically” available relief sufficient to defeat mootness does not include “imagined possibilities

4 beyond those requested in the complaint, but rather” involves “giv[ing] the plaintiff the benefit of

the doubt as to whether certain requested relief would in fact ease or correct the alleged wrong.”

Bayou Liberty Ass’n, Inc. v. U.S. Army Corps of Eng’rs,

217 F.3d 393, 397

(5th Cir. 2000)

(emphasis added). The Court finds that hypothetical relief the plaintiffs did not actually request in

their complaint cannot overcome the mootness arguments presented here.

Even if Finca and Román Más had requested that the Court order the Government to

dismantle or reverse the project, the Government correctly identifies a long line of cases in the

courts of appeal holding environmental challenges to completed construction projects to be moot.

See Weiss v. Sec’y of Dep’t of Interior,

459 F. App’x 497

, 500–501 (6th Cir. 2012) (holding NEPA

and NHPA claims moot because construction had been completed); Sierra Club v. U.S. Army Corps

of Eng’rs,

277 F. App’x 170, 172

(3rd Cir. 2008) (dismissing NEPA complaint as prudentially moot

because wetlands had already been substantially filled); One Thousand Friends of Iowa v. Mineta,

364 F.3d 890, 893

(8th Cir. 2004) (“A NEPA claim does not present a controversy when the

proposed action has been completed and no effective relief is available. . . . [Both injunctive and

declaratory relief are] similarly mooted by the completion of the construction project.”); Bayou

Liberty,

217 F.3d at 396

(“When a party seeks an injunction to halt a construction project the case

may become moot when a substantial portion of that project is completed”); Knaust v. City of

Kingston,

157 F.3d 86, 88

(2d Cir. 1998) (rejecting appeal of denial of injunction in NEPA case

because completion of construction rendered case moot). While the D.C. Circuit does not appear to

have addressed the precise question of the mootness of a NEPA claim involving a completed

construction project, it has found a NEPA claim to be moot when the matter in dispute—a plan for

wildlife management—had already been implemented. Fund for Animals, Inc. v. U.S. Bureau of

Land Mgmt.,

460 F.3d 13

, 18–19 (D.C. Cir. 2006). The Court is aware of no case, and plaintiffs

5 cite none, where a court in a NEPA case ordered a defendant to dismantle a completed construction

project.

In arguing that their suit still presents a live controversy, Finca and Román Más rely

primarily on West v. Secretary of Department of Transportation,

206 F.3d 920

, 922 (9th Cir. 2000),

where a split panel of the Ninth Circuit concluded that a NEPA challenge to a highway interchange

project was not moot despite the completion of the first of the project’s two phases. West is

factually distinguishable from the circumstances presented here. In that case, the Federal Highway

Administration prepared no Environmental Assessment whatsoever, as it had decided to apply a

categorical exclusion to the project. Id. at 926–27. Here, by contrast, the Corps has conducted

several Environmental Assessments over the years the project has been in development in an effort

to comply with NEPA. Moreover, the Ninth Circuit in West did not actually order the completed

portion of the highway interchange project to be deconstructed, instead noting that mitigation

measures could provide partial relief. Id. at 929 (“While we recognize that it may be too late to

correct problems that the requisite environmental review might have identified, we are not

convinced that all the problems identified by such a review would be immune from all mitigation

measures.”). In fact, the court acknowledged that the precise type of environmental review required

for the second stage of the project could not be determined until the timing, funding, and scope of

the second stage “takes shape more clearly.” Id. Thus, despite the West majority’s assertions to the

contrary, the dissent correctly notes that the majority’s acknowledgment of the need to leave the

final disposition of the case open pending further activity strongly suggests that review of the merits

was premature. Id. at 930 n.14. In short, in light of the factual distinctions, the split panel, the

uncertain final disposition, and the substantial contradictory authority provided by the Corps

supporting a finding of prudential mootness in this case, the Court finds West unpersuasive.

6 B. Declaratory Relief

Finca and Román Más also contend that, even if their claim for injunctive relief is moot,

their request for declaratory relief is not because “a declaration . . . would preclude the Corps from

undertaking any additional work pursuant to the [existing] authorizations, guaranteeing additional

environmental evaluations before the Corps could commence any future construction.” Pls.’

Response to Defs.’ Supplemental Mem. at 3. But the Government indicates that additional

evaluations will occur before any additional work on the upstream components of the project will

take place. As noted above, Finca and Román Más “do not contest Defendants’ sworn statements

that the Corps will likely conduct additional administrative and environmental review” before

beginning any additional phases of the project, just as the Corps did “on many occasions over the

years before Phase 1A even began construction.” Mem. Op. July 9, 2012 at 10. Government

counsel reiterated at the hearing that “before anything significant happens . . . there would be

another [Environmental Assessment] and [Finding of No Significant Impact] at a minimum”

because “[t]hat’s the way the Corps has handled it before and repeatedly.” Hr’g Tr. 23: 6–20, Oct.

15, 2014. A new Environmental Assessment is precisely the type of relief Finca and Román Más

have sought. Regardless, the Court concluded previously that “when it is uncontested that the

agency will engage in further administrative review before construction on the upstream project

components, judicial intervention would inappropriately interfere with the Corps’ process.” Mem.

Op. July 9, 2012 at 10–11. As the Supreme Court held in a similar environmental case, a plaintiff’s

claim seeking review of administrative action is unripe when “the possibility that further

consideration will actually occur before [implementation of a plan] is not theoretical, but real.”

Ohio Forestry Ass’n, Inc. v. Sierra Club,

523 U.S. 726, 735

(1998). Thus, the Corps’ commitment

to future assessments, and its history of conducting such assessments before engaging in significant

7 new activity, makes further judicial review of this matter inappropriate at this time. Should the

Corps renege on that promise, Plaintiffs would be free to renew their complaint.

Finally, Finca and Román Más assert that declaratory relief is necessary because it would

lift a “cloud” of uncertainty over their land which “effectively precludes investment of capital by

landowners or developers . . . due to the potential loss of that investment if the land is taken” for

any future upstream project components. Pls.’ Response to Defs.’ Supplemental Mem. at 8–9. The

plaintiffs assert variations of this argument throughout their filings in this case, but the D.C. Circuit

has explicitly held that “the possibility that the petitioner may have to make capital budgeting

decisions under a cloud of uncertainty” is not sufficient to make a claim ripe for review. Natural

Res. Def. Council, Inc. v. EPA,

859 F.2d 156

, 166 (D.C. Cir. 1988). Although Finca and Román

Más complain that the uncertainty has inhibited the likes of Wal-Mart and Walgreens from

purchasing their property, this circuit’s precedent clearly considers such hardships insufficient to

establish ripeness. Absent a ripe controversy, the case is prudentially moot.

IV. Conclusion

For the foregoing reasons, it is hereby

ORDERED that Plaintiffs’ Motion for Summary Judgment [ECF No. 39] and Defendants’

Cross-Motion for Summary Judgment [ECF No. 40] are DENIED. It is further

ORDERED that Plaintiffs’ Amended Complaint [ECF No. 13] is DISMISSED without

prejudice.

This is a final, appealable order.

SO ORDERED.

CHRISTOPHER R. COOPER United States District Judge

Date: January 6, 2014

8

Reference

Status
Published