Brandon Mill Manager, LLC v. United States

District Court, District of Columbia

Brandon Mill Manager, LLC v. United States

Opinion

UNITED STATES DISTRICT COURT FOR THE DISTRICT OF COLUMBIA

_________________________________________ ) BRANDON MILL MANAGER, LLC et al., ) ) Plaintiffs, ) ) v. ) Case No. 20-cv-1279 (APM) ) UNITED STATES OF AMERICA, ) ) Defendant. ) _________________________________________ ) MEMORANDUM OPINION

I. INTRODUCTION

This action concerns the Federal Deposit Insurance Corporation’s (“FDIC”) refusal to

consent to refinancing a construction loan. The loan was made to Brandon Mill, LLC, which used

the proceeds to convert a historic textile mill located in Greenville, South Carolina, into loft

apartments while retaining the mill’s historic character. Plaintiffs Brandon Mill Manager, LLC

and Brandon Mill Tenant, LLC are entities formed to develop and manage the historic renovation.

They complain that the FDIC’s refusal to agree to an initial refinancing offer caused them

economic injury after the construction loan was ultimately refinanced on less favorable terms.

Plaintiffs bring this action under the Federal Tort Claims Act (“FTCA”), asserting claims of

common law and statutory breach of fiduciary duties, breach of contract, negligence, and

intentional interference with prospective contractual relations. Defendant United States moves to

dismiss for lack of subject matter jurisdiction and for failure to state a claim.

For the reasons that follow, Defendant’s motion is granted. Although the court rejects

Defendant’s contention that Plaintiffs’ tort claims are barred because they were inadequately presented to the agency, the court nevertheless agrees that it lacks subject matter jurisdiction. The

FTCA does not waive sovereign immunity for tort claims that “arise out of” acts comprising

interference with contractual rights, and all of Plaintiff’s tort claims fall within that exemption.

Furthermore, the court lacks subject matter jurisdiction over Plaintiffs’ breach of contract claim.

Because the court dismisses the case for lack of jurisdiction, it does not reach Defendant’s

arguments that Plaintiffs have failed to state a claim.

II. BACKGROUND

A. Factual Background

In 2015, real estate developer H. Pace Burt, Jr. embarked on a project to convert Brandon

Mill—“a designated historic textile mill in Greenville, South Carolina”—into loft apartments

while preserving its historic value (“the Project”). Compl., ECF No. 1 [hereinafter Compl.], ¶¶ 7,

22. Efforts to renovate and preserve “historically significant properties” can earn significant tax

credits that are valuable to investors. Id. ¶ 8. Burt formed multiple limited-liability companies to

own, operate, and generate such tax credits for the Project. Id. ¶ 9. Understanding the relationship

between these entities is critical.

Brandon Mill, LLC (“Mill Owner”) owns the property underlying the project. Mill Owner

had two members, Plaintiff Brandon Mill Tenant, LLC (“Mill Tenant”) and Brandon Mill Investor,

LLC (“Mill Investor”). See Pls.’ Resp. & Opp’n to Def.’s Mot. to Dismiss, ECF No. 13, Pls.’

Mem. of P. & A. in Supp. of Pls.’ Resp. & Opp’n to Def.’s Mot. to Dismiss, ECF No. 13-1

[hereinafter Pls.’ Opp’n.], at 3. Mill Tenant, in turn, at first consisted of two members: Plaintiff

Brandon Mill Manager, LLC (“Mill Manager”) and First NBC Historic Tax Partners, LLC (“Tax

Partners”), a wholly owned subsidiary of First NBC Bank. Compl. ¶ 27. Mill Manager was formed

to “represent[] the interests of multiple investor members” and was responsible for executing the

2 Project’s business plan. Id. ¶ 12. In 2017, Louisiana regulators closed First NBC Bank, resulting

in the FDIC becoming the receiver for the bank and the successor to the rights and obligations of

First NBC Bank, including those of Tax Partners. Id. ¶¶ 33–34.

Two agreements are relevant for purposes of this litigation: the Operating Agreement and

the Master Lease. Their provisions concerning the refinancing of debt are central to the case.

Under the terms of the Operating Agreement, Mill Manager is responsible for “the day-to-day

operations of Mill Tenant.” Id. ¶ 30. But the Operating Agreement provides that Mill Manager

can cause Mill Tenant to incur debt only with the consent of Tax Partners. Id.; Def.’s Mot. to

Dismiss, ECF No. 11 [hereinafter Def.’s Mot.], Ex. 2, ECF No. 11-4 [hereinafter Operating

Agreement], § 2.4(A)(iii). Such consent cannot be “unreasonably withheld.” See Operating

Agreement § 2.4(A)(iii) (requiring “Consent of the Investor Member”); id. § 1 (“Consent of the

Investor Member”) (defining “Consent of the Investor Member”). The second agreement, the

Master Lease, is a separate agreement between Mill Owner and Mill Tenant. See Def.’s Mot., Ex.

3, ECF No. 11-5 [hereinafter Master Lease]. Under it, Mill Owner could refinance the Project’s

construction loan only with the approval of Tax Partners. See id. § 20.5. Tax Partners could grant

or withhold consent to refinance the construction loan “in [its] sole and absolute discretion.” Id.

In or around 2015, Branch Bank and Trust Company (“BB&T”) extended a construction

loan of $18 million to Mill Owner to fund the Project. Compl. ¶ 16.1 Once the property was

rehabilitated and achieved a certain occupancy threshold, it became eligible for permanent

1 The Complaint alleges that “Brandon Mill borrowed $18 million from BB&T.” Compl. ¶ 16. The court reads Plaintiffs’ reference to “Brandon Mill” in this paragraph to mean Brandon Mill, LLC or Mill Owner. That Mill Owner was the debtor on the BB&T is made clear in other Complaint allegations. See id. ¶¶ 81, 89 (alleging that the FDIC breached duties of care and loyalty by threatening to interfere and actually interfering “with the refinancing of Brandon Mill, LLC”); id. ¶ 95 (alleging the “FDIC intentionally interfered with Plaintiffs’ ability to refinance the Brandon Mill, LLC construction loan”). 3 refinancing. Id. ¶ 17. In the spring of 2017, Mill Manager received term sheets “from Arbor

Commercial Funding . . . reflecting the terms on which Arbor would provide Mill Manager with

permanent financing to refinance the BB&T Construction Loan.” Id. ¶ 38. “The Arbor term sheets

were very favorable for the LLCs . . . .” Id. ¶ 39. By that point, the FDIC had taken over as

successor to Tax Partners, and so in “the summer of 2017, the LLCs, through Mr. Burt, made

repeated requests that the FDIC, in its capacity as Receiver for First NBC Bank, give Tax Partners’

consent to proceed with refinancing the BB&T Construction Loan on the terms set forth in the

Arbor term sheet.” Id. ¶ 40. Although the FDIC acknowledged receiving the requests for consent

and understood their urgency, it never affirmatively responded, leading the refinancing opportunity

with Arbor to slip away. Id. ¶¶ 41, 46.

Meanwhile, in its capacity as receiver, the FDIC was attempting to liquidate the assets of

First NBC Bank, and it proposed that Mill Manager “make an offer to purchase Tax Partners’

membership in Mill Tenant.” Id. ¶ 35. Mill Manager made an offer to the FDIC, to which the

FDIC did not respond. Id. ¶¶ 35–36. By September 2017, Burt became suspicious that the FDIC

had withheld its consent to Arbor’s refinancing proposal to extract a higher price for the buyout of

Tax Partners’ membership in Mill Tenant. Id. ¶ 47. In other words, Burt believed that the FDIC

would consent to refinancing only if Mill Manager increased its offer to buy out Tax Partners’

interest in Mill Tenant. Id.

In October 2017, Burt secured an alternative commitment to refinance from another lender,

but on less favorable terms than what Arbor had offered. Id. ¶ 49. Burt then requested the FDIC’s

consent to the new refinancing, and the FDIC responded by promising to consider the offer but

“tied” its consent to a buyout of Tax Partners’ interest in Mill Tenant. Id. ¶ 51. Only after Burt

threatened legal action did the FDIC consent to the refinancing. Id. ¶¶ 52–53.

4 B. Exhaustion of Remedies

Notwithstanding the FDIC’s eventual consent, Plaintiffs pursued legal action against the

FDIC, starting with exhausting their administrative remedies. On May 13, 2019, Plaintiffs Mill

Manager and Mill Tenant filed identical claim forms, known as Standard Form 95s (“SF 95s”),

with the FDIC. See Def.’s Mot., Ex. 4, ECF No. 11-6; Def.’s Mot., Ex. 5, ECF No. 11-7

[hereinafter, collectively, SF 95s]. The FDIC treated the SF 95s as asserting claims under the

FTCA and the Financial Institutions Reform, Recovery and Enforcement Act of 1989

(“FIRREA”). See Reply in Support of Def.’s Mot. to Dismiss, ECF No. 16 [hereinafter Def.’s

Reply], Ex. 8, ECF No. 16-1 [hereinafter Grieser Decl.], ¶ 3. According to narratives

accompanying the SF 95s, Mill Owner and Burt had suffered economic damages in the amounts

of $320,629.77 and $1,250,701.31, respectively, due to the FDIC’s refusal to approve the Arbor

refinancing. See SF 95s ¶¶ 50–51. Neither the SF 95s nor the accompanying narratives identified

a damages amount for either Plaintiff.

On October 10, 2019, a claims agent for the FDIC, Donald Grieser, mailed to each Plaintiff

an identical pair of letters, both of which referenced only Plaintiffs’ claim under FIRREA.

See Grieser Decl., Exs. C–F (each letter citing FIRREA provisions under

12 U.S.C. § 1821

(d)(5)).

The first letter requested that Plaintiffs submit “additional information regarding [their] Proof of

Claims” by October 24, 2019, and the second letter sought a 30-day extension of the 180-day

statutory deadline to respond to a FIRREA claim. See

id.

On October 10, 2019, Grieser also sent

via email to Plaintiffs’ counsel the letters he had sent by regular mail. Grieser Decl. ¶¶ 6–7; Grieser

Decl., Ex. G.

Plaintiffs never received the mailed letters. The U.S. Postal Service returned them marked

“Return to Sender Not Deliverable as Addressed Unable to Forward.” Grieser Decl. ¶ 8 (internal

5 quotation marks omitted). It is unclear when precisely Plaintiffs’ counsel received the letters via

email. Not until a month later, on November 10, 2019, did counsel responded to Grieser’s email,

stating that his law firm had been experiencing “debilitating” technical issues “for many weeks.”

Grieser Decl., Ex. J. Still, counsel returned executed forms consenting to the extension request.

See

id.

In the interim, however, FDIC had decided to deny Plaintiffs’ claims, at least under

FIRREA, without receiving additional information from Plaintiffs. On November 6, 2019, Grieser

sent by certified mail a “Notice of Disallowance of Claim” that stated, “This claim has not been

proven to the satisfaction of the Receiver.” Grieser Decl., Exs. H–I (citing

12 U.S.C. § 1821

(d)(5)(D)(i)). It is uncertain whether by November 10, 2019, Plaintiffs’ counsel had

received these denials when he forwarded by email consents to the extension requests. Grieser

eventually responded to counsel’s November 10th email eight days later, attached the Notices of

Disallowance, and stated that they were “FINAL.” Grieser Decl., Ex. K.

As for the FTCA claims, the FDIC separately denied those on November 15, 2019. Colleen

Boles, Assistant General Counsel of the FDIC, sent letters to Plaintiffs stating that the FDIC had

considered Plaintiffs’ claims under the FTCA “for $0 in damages related to the Brandon Mill

Project” and that the agency was denying those claims. Def.’s Mot., Ex. 6, ECF No. 11-8; Def.’s

Mot., Ex. 7, ECF No. 11-9 [hereinafter, collectively, FTCA Disallowance].

C. Parallel Litigation Brought by Mill Owner and Burt

This is not the first action arising from the FDIC’s refusal to consent to the Arbor

refinancing terms. In 2018, Mill Owner and Burt sued the FDIC, asserting tort, contract, and state

law statutory claims arising under South Carolina law, similar to those advanced here.

See Brandon Mill, LLC v. FDIC,

831 F. App’x 526

(D.C. Cir. 2020). The trial court dismissed the

6 action on July 31, 2019, and the D.C. Circuit affirmed on December 18, 2020. See Brandon Mill

LLC v. FDIC (Brandon Mill I), Civ. A. No. 18-2308 (RMC),

2019 WL 3458688

(D.D.C. July 31,

2019), aff’d,

831 F. App’x 526

. The D.C. Circuit held that Mill Owner and Burt’s “various claims

fail, at bottom, because [Mill Owner and Burt] have no direct relationship with Tax Partners and

therefore lack the requisite legal relationship to plead their claims.” Brandon Mill, LLC, 831

F. App’x at 527.

D. Procedural History

On May 14, 20201, while Mill Owner and Burt’s dismissed action was pending on appeal,

Mill Manager and Mill Tenant filed this case against the United States under the FTCA.

See Compl. Plaintiffs assert various theories that purportedly give rise to liability under the FTCA:

(1) breach of fiduciary duty (Count I), (2) breach of contract (Count II), (3) negligence (Count III),

(4) breach of duty of loyalty under the South Carolina Limited Liability Company Act (“South

Carolina LLC Act”) (Count IV), (5) breach of duty of care under the South Carolina LLC Act

(Count V), and (6) intentional interference with prospective contractual relations (Count VI). Id.

The United States now moves to dismiss the action in its entirety for lack of subject matter

jurisdiction and for failure to state a claim. See Def.’s Mot.

As noted, because the court dismisses the action for lack of jurisdiction, it does not reach

Defendants’ arguments for failure to state a claim. See Simpkins v. D.C. Gov’t,

108 F.3d 366, 371

(D.C. Cir. 1997) (“[T]he rule is strict that once a court determines that it lacks subject matter

jurisdiction, it can proceed no further.”).

7 III. DISCUSSION

A. Legal Standard

Under Federal Rule of Civil Procedure 12(b)(1), a defendant may move to dismiss a

complaint for lack of subject matter jurisdiction. Fed. R. Civ. P. 12(b)(1). The plaintiff bears the

burden of establishing that such jurisdiction exists. See Khadr v. United States,

529 F.3d 1112, 1115

(D.C. Cir. 2008). A court must accept all well-pleaded factual allegations in the complaint

as true. See Jerome Stevens Pharms., Inc. v. FDA,

402 F.3d 1249, 1253

(D.C. Cir. 2005). A court

is not limited to the allegations made in the complaint, however, and may consider such materials

outside the pleadings as it deems appropriate. See

id.

B. Jurisdictional Challenges

Defendant challenges the court’s subject matter jurisdiction on three grounds. First, it

asserts that Plaintiffs failed to satisfy the jurisdictional presentment requirement because they

failed to make a sum-certain administrative claim for damages. See Def.’s Mot., Mem. of P. & A.

in Supp. of Def.’s Mot. to Dismiss, ECF No.11-2 [hereinafter Def.’s Br.], at 11–12. Second,

Defendant contends that all of Plaintiffs’ claims (except their contract claim) are barred under

section 2680(h) of the FTCA as claims arising out of “interference with contract rights,”

28 U.S.C. § 2680

(h). Def.’s Br. at 12–13. And third, Defendant maintains that Plaintiffs’ breach of contract

claim must be dismissed as the FTCA does not waive sovereign immunity for contract claims.

Id. at 13

. The court disagrees with the first of these jurisdictional contentions but agrees with the

second and third.

1. Failure to Present

The FTCA contains “an administrative-filing requirement, satisfaction of which is a

jurisdictional prerequisite to the maintenance of a tort suit against the United States.” GAF Corp.

8 v. United States,

818 F.2d 901, 904

(D.C. Cir. 1987). An FTCA claim is deemed presented “when

a Federal agency receives from a claimant . . . an executed Standard Form 95 or other written

notification of an incident, accompanied by a claim for money damages in a sum certain for injury

to or loss of property, personal injury, or death.”

28 C.F.R. § 14.2

(a); see also

28 U.S.C. § 2675

(a).

Thus, a “jurisdictionally adequate presentment is one which provides to the appropriate agency

(1) a written statement sufficiently describing the injury to enable the agency to begin its own

investigation, and (2) a sum-certain damages claim.” GAF Corp.,

818 F.2d at 905

. A claimant is

“entitled to file suit at the point at which the claim presented is finally denied, or six months after

it is presented if the agency fails to make final disposition of the claim within that period.” Id.;

see also

28 U.S.C. § 2675

(a) (“The failure of an agency to make final disposition of a claim within

six months after it is filed shall, at the option of the claimant any time thereafter, be deemed a final

denial of the claim for purposes of this section.”).

Defendant contends that Plaintiffs failed to satisfy the presentment requirement, rendering

their claims jurisdictionally barred, because their “administrative claims provided no sum-certain

amount for damages, as required by Section 2675(a).” Def.’s Br. at 11. Defendant points out that

Plaintiffs’ SF 95s, on their face, specify no dollar amount in damages. Instead, the forms state that

the “claim asserted herein does not involve damage to personal property or real estate,” but instead

“involves economic damages,” and supply an address where claimants’ books and records can be

inspected. SF 95s at 2. In addition, the identical narratives accompanying the SF 95s only identify

sum-certain damages amounts for Mill Owner and Burt, neither of whom are plaintiffs in this

action. See

id.

9 The court agrees that Plaintiffs failed to administratively present sum-certain damages

claims, but that deficiency does not defeat jurisdiction in this case. In GAF Corp., the D.C. Circuit

observed that

[w]here a claimant makes a reasonable effort to notify federal agencies of a claim in accordance with the administrative filing procedures of Section 2675(a), and the Government takes no action to apprise the claimant of objections to the presentment within the six-month time period it has to make final disposition of the claim, it seems . . . that such delay qualifies the force of the Government’s objections when it subsequently moves for dismissal on the ground that the presentment was inadequate for its investigative purposes.

GAF Corp., 818 F.2d at 915–16. The court elaborated in a footnote that the government’s failure

to raise an objection within the six-month statutory period was a question not of waiver but of

jurisdiction “as a matter of statutory entitlement.”

Id.

at 916 n.86. Based on the FTCA’s

“commitment” to preserving “the claimant’s right to sue under the Act” even as it simultaneously

encourages settlement, the court found that “there appear to be strong grounds for treating an

agency’s failure to make timely objection to the adequacy of a presentment as a an instance of

agency inaction, giving rise to jurisdiction within the meaning of § 2675(a).” Id.

The circumstance discussed in GAF Corp. is precisely what occurred here, and so its

reasoning squarely applies. Plaintiffs filed their administrative FTCA claims on May 13, 2019,

but the FDIC did not deny those claims until November 15, 2019—186 days later. See FTCA

Disallowance. At no point during the statutory six-month period did the agency “object to the

adequacy of [the] presentment,” GAF Corp.,

818 F.2d at 916

n.86, thereby denying Plaintiffs the

opportunity to “cure [their] presentment in an expeditious fashion,”

id. at 916

. The agency’s

failure to act within the statutory six-month period, when combined with its failure to object to the

10 adequacy of notice provided during that time, qualifies as “an instance of agency inaction”

sufficient to give rise to jurisdiction under GAF Corp. See

id.

at 916 n.86.

Defendant retorts that the scenario contemplated in GAF Corp. is distinct from what

occurred here because the FDIC did object to the adequacy of Plaintiffs’ presentments. Defendant

cites the deficiency notices sent to Plaintiffs’ counsel by Claims Agent Grieser on October 10,

2019, for this proposition. See Def.’s Reply at 5 (citing Grieser Decl., Exs. C–D). But those

deficiency notices concerned the agency’s objection to the adequacy of Plaintiffs’ administrative

claims under FIRREA, not the FTCA. That much is clear from the face of the October 10th

notices—which cite only statutory provisions under FIRREA—and from Grieser’s sworn

declaration, in which he states, “On behalf of the FDIC, I processed these Claims for purposes of

FIRREA.” Grieser Decl. ¶ 3. Defendant has submitted no similar deficiency notice concerning

Plaintiffs’ administrative FTCA claims. Nor has it offered an affidavit from Coleen Boles, the

FDIC’s Assistant General Counsel, who belatedly denied Plaintiffs’ FTCA administrative claims.

Accordingly, because the FDIC neither objected to nor acted with respect to Plaintiffs’

presentment within the six-month statutory period, Plaintiffs’ failure to specify a sum-certain

damages claim does not foreclose the court’s jurisdiction.

2. The Interference-with-Contracts-Rights Exception

The court now turns to Defendant’s argument that all of Plaintiff’s tort claims are excluded

from the FTCA’s immunity waiver under section 2680(h). “Although Congress has waived the

government’s immunity with respect to damages or injuries caused by the ‘negligent or wrongful

act or omission of a government employee acting within the scope of employment,’ it has not

waived immunity for every type of tort.” Kugel v. United States,

947 F.2d 1504, 1506

(D.C. Cir.

1991) (citation omitted) (quoting

28 U.S.C. § 1346

(b)). Among the torts excepted from the

11 immunity waiver are “claim[s] arising out of . . . interference with contract rights.”

28 U.S.C. § 2680

(h).

There can be little doubt that at least one of Plaintiffs’ claims is foreclosed by the

interference-with-contracts-rights exception—Count VI, intentional interference with prospective

contractual relations. See Compl. ¶¶ 93–98. In Art Metal-U.S.A., Inc. v. United States, the

D.C. Circuit held that the plaintiff’s “claims for interference with prospective advantage are barred

as claims arising out of interference with contract rights.”

753 F.2d 1151, 1155

(D.C. Cir. 1985).

The court explained that “[t]he duty that the [government] officials allegedly breached is the duty

not to interfere with [the plaintiff’s] economic relationship with third parties.”

Id. at 1154

. “That

duty,” the court went on to say, “is the same as the duty underlying a claim for interference with

contract rights; the claims are distinguished only because the plaintiff’s rights or expectancies

under the latter are secured by an existing contract.”

Id. at 1154

. It then concluded:

To hold that interference with prospective advantage does not arise out of interference with contract rights under section 2680(h) would subject the government to liability if its employees interfered with the plaintiff’s mere expectation of entering a contract, but not if they interfered with a contract already in existence. Such a result would be illogical and contrary to the “words and reason of the exception.”

Id. at 1155

(citation omitted) (quoting Kosak v. United States,

465 U.S. 848

, 853 n.9 (1984)).

With Art Metal squarely foreclosing Count VI, 2 the question becomes whether Plaintiffs’

other claims qualify as “claim[s] arising out of . . . interference with contract rights.”

28 U.S.C. § 2680

(h). The Supreme Court has directed that a court’s task in “construing the exceptions set

forth in section 2680(h) is to identify those circumstances which are within the words and reason

of the exception—no less and no more.” Art Metal,

753 F.2d at 1154

(cleaned up) (quoting Kosak,

2 Plaintiffs offer no argument to the contrary. See Pls.’ Opp’n at 15–17. Indeed, their Opposition does not even cite Art Metal. 12

465 U.S. at 853

n.9). “To determine whether a non-enumerated claim ‘arises out of’ an enumerated

claim, the court must examine the actual conduct upon which the claims are based.” Klugel v.

Small,

519 F. Supp. 2d 66, 75

(D.D.C. 2007) (citing Kugel,

947 F.2d at 1507

(noting the court

must “scrutinize the alleged cause of [plaintiff’s] injury”)); Truman v. United States,

26 F.3d 592, 595

(5th Cir. 1994) (“[T]he focus of th[e] inquiry is on the conduct on which [plaintiff] bases her

claim.”). Thus, “the label which a plaintiff applies to a pleading does not determine the nature of

the cause of action which he states.” Johnson v. United States,

547 F.2d 688, 691

(D.C. Cir. 1976)

(citation omitted).

Having closely scrutinized the Complaint, the court concludes that all of Plaintiffs’

remaining tort claims arise out of alleged interference with contract rights. As the court in Art

Metal observed, the duty underlying the tort of interference with contract is “the duty not to

interfere with [the plaintiff’s] economic relationship with third parties.”

753 F.2d at 1154

. Here,

all three claims for breach, regardless of their individual labels, are predicated on the same duty

not to interfere with Plaintiffs’ economic relationship with a third party—the prospective

refinancing with Arbor. The Complaint generally alleges that the FDIC “breached its . . . duties .

. . to the LLCs by virtue of” (1) “[f]ailing to timely review the Arbor terms sheet”; (2) “[f]ailing to

consider and consent to the Arbor terms sheet”; (3) “[a]ttempting to extort an exorbitant price for

Tax Partners’ interest in [Mill Tenant] by refusing to consent to the Arbor terms sheet”;

(4) “[m]aking threats and [the above] actions” in relation to the Arbor refinancing; and

(5) “[f]ailing to exercise reasonable care in the oversight and supervision of its employees and

contractors.” Compl. ¶ 57. The individual breach counts echo this duty to avoid interfering with

a prospective business relationship with Arbor. In Count I (breach of fiduciary duty), Plaintiffs

allege that “[b]y failing to timely respond to the request to sign off on new financing, FDIC

13 breached its fiduciary duty to [Plaintiffs].” Id. ¶ 62. Likewise, in Count IV (breach of duty of

loyalty under the South Carolina LLC Act), Plaintiffs maintain that the FDIC “breached [its] duty

of loyalty by threatening and actually interfering with the refinancing of [Mill Owner] as described

above.” Id. ¶ 81. And, in Count V (breach of duty of care under the South Carolina LLC Act),

Plaintiffs aver that the FDIC “breached [its] duty of care by threatening and actually interfering

with the refinancing of [Mill Owner] as described above in a manner that was grossly negligent,

reckless, and intentional.” Id. ¶ 89. Plaintiffs’ Opposition confirms that interference with

contractual rights lies at the heart of the case: they state that “[t]his lawsuit has been brought

because FDIC . . . unreasonably withheld consent [to the Arbor refinancing agreement] for the sole

purpose of pressuring Mr. Burt and [Mill Owner] into paying more” to buy out Tax Partners’

interest. Pls.’ Opp’n at 20–21. Thus, Plaintiffs’ breach of duty causes of action seek “to recover

for the breach of duties identical to those underlying a barred claim”; the court thus lacks

jurisdiction to hear them. Art Metal,

753 F.2d at 1154

.

For their part, Plaintiffs do not contest this analysis. See Pls.’ Opp’n at 15–17. They do

not, for example, assert that their breach claims involve a duty other than “the duty not to interfere

with [the plaintiff’s] economic relationship with third parties.” Art Metal,

753 F.2d at 1154

;

cf. Jerome Stevens Pharms.,

402 F.3d at 1256

(holding that, because the plaintiff’s claims for

misappropriation of trade secrets and breach of a confidential relationship involved a duty—not to

disclose trade secrets and confidential information—different from the duty not to interfere with

the economic relationship of a third party, the FTCA did not bar such claims). Rather, they argue

that “as long as some aspect of the conduct upon which a plaintiff bases a tort claims does not

constitute a tort as listed in § 2680(h), the suit may continue.” Pls.’ Opp’n at 15. To that end,

Plaintiffs argue that “[n]egligence claims are cognizable under the FTCA,” and that “Plaintiffs

14 make tort claims stemming out of negligence.” Id. at 16. Plaintiffs describe the negligent conduct

as follows: “FDIC as Receiver . . . ignore[d] and delay[ed] requests to grant consent in an attempt

to force [Plaintiffs’] hand at paying a larger sum for Tax Partners’ interests in the Project in

exchange for the consent needed to refinance the Project’s initial construction loan.” Id. at 17. As

is plain from this description, Plaintiffs’ negligence theory—that the FDIC improperly withheld

consent to the Arbor refinancing for its own benefit, which in turn economically harmed

Plaintiffs—is simply a repackaging of their claim for interference with prospective contractual

relations. “[A] litigant cannot circumvent the [FTCA] by the simple expedient of drafting in terms

of negligence a complaint that in reality is a claim as to which the United States remains

immunized.” Johnson, 547 F.2d at 691–92. But that is precisely what Plaintiffs have attempted

to do here. The court therefore lacks subject matter jurisdiction over their negligence claim as

well. See Ecco Plains LLC v. United States,

728 F.3d 1190, 1195

(10th Cir. 2013) (rejecting

jurisdiction over negligence and conversion claims that arose out acts interfering with contractual

rights).

3. Breach of Contract Claim

That then leaves Plaintiffs’ breach of contract claim (Count II). That claim, too, fails for

lack of subject matter jurisdiction.

The Tucker Act,

28 U.S.C. § 1491

(a)(1), gives the U.S. Court of Federal Claims exclusive

jurisdiction over suits against the United States for money damages in excess of $10,000.

See Bowen v. Massachusetts,

487 U.S. 879

, 910 n.48 (1988); Franklin-Mason v. Mabus,

742 F.3d 1051, 1055

(D.C. Cir. 2014) (“We have construed the Tucker Act . . . to provide for exclusive

jurisdiction in the Court of Federal Claims for contract disputes seeking more than $10,000 in

damages [unless an independent grant of jurisdiction exists].”). That appears to be the essence of

15 Plaintiffs’ contract claim. Plaintiffs allege that the FDIC, as successor to First NBC Bank,

breached “duties and obligations” owed under “the LLC’s operating agreement.” Compl. ¶ 67.

Plaintiffs’ breach of contract claim therefore belongs in the Court of Claims.

If what Plaintiffs seek to do is jurisdictionally tie their breach of contract claim to their tort

causes of action, they cannot now do so. Because the court lacks jurisdiction over the FTCA

claims, it lacks jurisdiction over the contract claim, too. See Perry Cap. LLC v. Mnuchin,

864 F.3d 591, 623

(D.C. Cir. 2017) (“If a separate waiver of sovereign immunity and grant of jurisdiction

exist, district courts may hear cases over which, under the Tucker Act alone, the Court of Federal

Claims would have exclusive jurisdiction.”). None of the cases that Plaintiffs cite, see Pls.’ Opp’n

at 17–18, compel a different result.

IV. CONCLUSION

For the foregoing reasons, Defendant’s Motion to Dismiss, ECF No. 11, is granted. A final,

appealable order accompanies this Memorandum Opinion.

Dated: August 23, 2021 Amit P. Mehta United States District Court Judge

16

Reference

Status
Published