York v. Tyler
York v. Tyler
Opinion of the Court
delivered the opinion of the Court:
The bill in the case of York against Tyler seeks to em force a mechanics’ lien, and alleges that on the 18th of August, 1883, the plaintiff entered into a contract with the defendants, Tyler & Rutherford, described in the said contract as agents, to build and construct seven houses upon seven sub-lots in square 115, in this city, for the sum of $30,800; that the plaintiff proceeded to perform the contract on his-part, and while so performing and carrying out the same, on the 8th of October, 1883, the defendants, Tyler & Rutherford, took possession of the buildings so being erected, dispossessed the plaintiff and refused to allow him to proceed with his contract, and thereupon proceeded to complete the work themselves; that at the latter date materials had been furnished and labor performed by the plaintiff upon all of the said houses, and some payments had been made by the defendants, Tyler & Rutherford, on account of such work and materials, leaving a balance due to the plaintiff; that at the date of the contract, four of these lots, 69 to 72, inclusive, were owned by the defendant Tyler; another lot, 73, by Emma J. Brewer, and two others, 74 and 75, by George L. Knowles and Joseph A. Jones, as tenants in common; that on the 24th of November, 1883, plaintiff filed his notice of lien on the first four mentioned lots and premises in the name of Tyler & Rutherford, as owners, and subsequently on the 12th' of July, 1884, filed another such notice of lien against the said lots in the name of Richard W. Tyler as owner. There are other averments in the bill which are not material to the stating of this account. The original answer of the defendants, Tyler & Rutherford, admits the making of the contract and partial execution of the work; also the taking possession by them on the 8th of October, and their refusal to allow the plaintiff to proceed, and that they finished the said work. This answer also assigns as
The plaintiff brought similar suits to enforce similar liens in causes Nos. 9105 and 9106. Proofs were taken, and by stipulation are to be used in the three causes. A copy of the contract of August 18, 1885, is filed as an exhibit to the bill. The agreement was made between the plaintiff, as
The specifications in general terms required that all material should be of the best description; that the contractor should furnish all material and do all necessary work to complete the buildings, whether specified or not, excepting certain things which were specifically omitted; no changes were to be made without previous agreement, and that the plans and drawings should form a part of both contract and specifications.
Replication was made to the answers of defendants. Testimony was taken, and the cause referred to the auditor to state an account between the parties. The auditor made his report, in which he passed upon the several alleged defects in the performance of the contract on the part of the plaintiff, as mentioned in the amended answer, and some in a letter which was written by tne architect to the plaintiff on the 5th of October, three days before the letter was written and notice given by the defendants and served upon the plaintiff which terminated the contract and dispossessed the plaintiff, and also some defects which it is claimed by the defendants appear in the evidence produced by them.
After passing upon all these matters in his report, the auditor states an account between the parties, in which he
In the next case, that of York against Brewer, No. 9105, he -finds to be due from the defendants to the plaintiff, $399.35- In the case of York against Knowles, Jones and others, No. 9106, the auditor finds to be due from the defendants to the plaintiff the sum of $798.72.
To this report and finding of the auditor, the defendants in each of the causes excepted, as follows:
No. 9104. First, they except to the allowance.by the auditor to the plaintiff of $1,226.34, for work done and materials furnished on houses on lots 69, 70, 71 and 72, in square 115.
Second. They excepted to the allowance by the auditor to the plaintiff of $499.34 as due him on account of excess of work on said houses.
Third. They except to the allowance of the auditor to the plaintiff of $370.39 on account of materials set forth in said Schedule A.
And said defendants, Tyler & Rutherford, aver in each of their said exceptions that each of said findings and certifications of the auditor is not supported by the evidence in said cause; and further, said auditor ought to have found there was nothing due to said plaintiff.
In cause No. 9105 the exceptions are precisely the same as in the previous case, with the exception that the amount is less; and the same is true of cause No. 9106.
Our first suggestion is in regard to the character of the exceptions. We think they are altogether too general. They are simply as to the amounts found due .from the defendants to the plaintiff. There are no exceptions to the finding of the auditor as to the defects which they allege in their answer existed in the workmanship of the plaintiff and in the materials which were furnished by the plaintiff.
Only recently, in the case of Haller vs. Clark, ante, p. 128,
In other words, the exception should be definite and specific, and go to the very evil complained of by the party filing the exception. Otherwise, it should be disregarded by the court entirely.
This position is sustained by Harding vs. Handy, 11 Wheaton, 126, and in Story vs. Livingston, 13 Peters, 365.
We desire again to emphasize the importance of reform m this respect.
We have,'notwithstanding the imperfect character of these exceptions, proceeded to examine the case, following the arguments of counsel as if their exceptions reached all the matters of difference between the parties upon the hearing before the auditor.
The real question at issue between the parties is stated by the auditor on page 8 of his report to be as follows:
“The primary and pivotal question here is whether the act of the defendants' in taking possession of the premises and refusing to allow the plaintiff to proceed with the work was lawful and justifiable?”
“We maintain that the present is that case; that the plaintiff did not perform or comply with his contract, and is therefore in the condition of one who sues on a contract which he himself has not kept. Our contention is that the testimony will show this non-compliance. If it does not, then we take nothing from the above rufe of law.”
It will be seen, then, that the auditor substantially adopts the position which the defendant, in his brief concedes; and he proceeds in his report to examine the evidence relating to each one of the specifications of defective performance on the part of the plaintiff, and gives his conclusion. So that there is really in the case for our consideration no question of law. This leaves only issues of fact, whether the evidence sustains the averments by defendant of defective workmanship and materials, or whether it shows that plaintiff substantially complied with his contract, and was not in that respect in default at the time that the defendants saw proper to give the notice which terminated his performance of the contract.
The auditor has, as we think, very carefully examined the evidence applicable to the determination of the several matters of contest between the parties, and has come to a rational, sensible and just conclusion in relation to all of them. His conclusion is, that as to all of these alleged shortcomings and defective performances on the part of the plaintiff, the defendants have failed to establish them or any of them by a preponderance of evidence to his satisfaction.
When we come to the amounts which have been stated by the auditor as being due from the defendants to the plaintiff, there is hardly any room for controversy, because it is not contended seriously by the counsel for defendants that if they fail to establish their right to terminate the contract, they are not under obligation to pay the fair value of all the work performed and materials furnished by the plaintiff under the contract; and it is not alleged or claimed by counsel for the defendants that if the plaintiff is to be allowed the value of these materials and for this work — if he is not held to be in default — the values fixed by the auditor aré excessive.
We may again call the attention of the bar to the auditor’s findings in a report of this character, as has been repeatedly defined by the Supreme Court of the United States. We find that in the case of Crawford vs. Neal, 144 U. S., 585, the doctrine is repeated by Chief Justice Fuller. In delivering the opinion, he says:
* “The cause was referred to a master to- take testimony therein, ‘ and to report to this court his findings of fact and his conclusions of law thereon.’ This he did, and the court, after a review of the evidence, concurred in his findings and conclusions. Clearly, then, they are to be taken as presumptively correct, and unless some obvious error has intervened in the application of the law, or some serious or important mistake has been made in the consideration of the evidence, the decree should be permitted to stand.”
Citing: Tilghman vs. Proctor, 125 U. S., 136; Kimberly vs. Arms, 129 U. S., 512; Evans vs. State Bank, 141 U. S., 107.
In the next volume, 145 U. S., 132, in the case of Furrer vs. Ferris, the Supreme Court had the same question before them, and reaffirmed Crawford vs. Neal.
We think it entirely a work of supererogation to spend an hour or more, as would be required even in a very ab
The decree of the court below affirming the auditor's report will be affirmed.
Reference
- Full Case Name
- JAMES M. YORK v. RICHARD W. TYLER SAME v. EMMA J. BREWER SAME v. GEORGE L. KNOWLES
- Status
- Published