Foundation Co. v. State
Opinion of the Court
The plaintiff constructed, upon a unit price contract, a bridged-type dam in the Mohawk river at Scotia for barge canal purposes, with a lock at one end. The defendant has paid in full for the work actually performed, according to the terms of the contract, but upon the settlement the plaintiff claimed certain additional or other compensation, which, by an understanding between the parties, resulted in the filing of this claim. By the judgment under review the plaintiff has recovered judgment for $73,689.21, of which $11,417 represents additional cost of the work below elevation 148 and the balance is an allowance of $62,272.21 for pumping from the coffer dams at the lock over and above the contract price of fifteen cents per 1,000,000 foot gallon. The first item was allowed upon the theory that both parties to the contract contemplated that the excavation and work were not to go below elevation 148 and the payment of the additional pumping was allowed upon the theory that the contract contemplated that the lock should be constructed in one coffer dam, while changes made by the State required the use of several coffer dams, thus increasing the cost.
The contract required the plaintiff to put its work upon bed rock in the river bottom for which it was to receive twenty-one dollars per cubic yard down to elevation 148 and for all work below elevation 148 the rate was to be twenty-five dollars per cubic yard. It is manifest that neither party to the contract could know with absolute certainty where bed rock would be
“ The attention of persons intending to make proposals is specifically called to paragraph ten [evidently eleven] of the form of contract, which debars a contractor from pleading misunderstanding or deception, because of estimates of quantities, character, location or other information exhibited by the State.”
Paragraph 11 is as follows: “ The contractor agrees that he has satisfied himself by his own investigation and research regarding all the conditions affecting the work to be done and labor and material needed, and that his conclusion to execute this contract is based on such investigation and research, and not on the estimate of the quantities or other information prepared by the State Engineer, and that he shall make no claim against the State because any of the estimates, tests, or representations of any kind affecting the work made by any officer or agent of the State, may prove to be in any respect erroneous.”
These provisions and the contract itself must be read in connection with section 9 of article 7 of the Constitution, which provides as follows: “All contracts for work or materials on any canal shall be made with the persons who shall offer to do or provide the same at the lowest price, with adequate security for their performance. No extra compensation shall be made to any contractor; but if, from any unforeseen cause, the terms of any contract shall prove to be unjust and oppressive, the Canal Board may, upon the application of the contractor, cancel such contract,” and the following provision of section 6 of the Barge Canal Law (Laws of 1903, chap, 147, as amd. by Laws of 1911, chap. 736): “ No change of plan or specification which will increase the expense of any such work or create any claim against the State for damage arising therefrom shall be made unless a written statement, setting forth the object of the change, its character, amount and the expense thereof, is
Section 7 of that act provides, in substance, that if it becomes apparent in the conduct of the work that any item will exceed in quantity the engineer’s estimate by .more than fifteen per cent, the engineer shall certify that fact to the Canal Board, which shall determine whether the excess work shall be completed by the contractor under the terms and at the prices, specified in the contract or whether it shall be done by the Superintendent of Public Works or by special contract. In this case the requirement was made by the Canal Board and the State Engineer that the work should be done by plaintiff according to the terms of the contract.
The plaintiff had ample time in which to make the proper tests and investigations of the site and the condition under which the work was to be performed. Evidently the examination made by it was simply perfunctory. It did not choose to incur the expense of making a proper examination or was not properly advised upon the subject by its engineer. It is not in a position to claim that the State lias done it any actionable wrong. It preferred not to incur the expense of a scientific examination of the river bottom but agreed to take its chances as to the correctness of the estimate furnished and it must abide by that decision. Under the law governing contracts of this kind and the express terms of the contract, the defendant is not liable. (Matter of Semper v. Duffey, 227 N. Y. 151; Simpson v. United States, 172 U. S. 372; Leary v. City of Watcrdiet, 222 N. Y. 337.)
In Sundstrom v. State of New York (213 N. Y. 68) the plaintiff’s contract work was interfered with by water leaking through the canal because of its lack of repairs and its defective condition; in other words, by the negligence of the State, and it was held that the plaintiff was not required to guard against the State’s negligence and that he could recover the extra cost of its work.
The contract there was quite similar to the one we are
In Faber v. City of New York (222 N. Y. 255) the plaintiff recovered upon the ground that there was an express warranty.
In Christie v. United States (237 U. S. 234) recovery was permitted upon the ground that the representatives of the government falsely stated that the material to be excavated, so far as known, was shown by the borings and drillings which might be seen in the office. The borings exhibited were not a correct showing of the conditions found. Buried logs and stumps were found by the drilling which were not disclosed by the borings exhibited.
The contract and the specifications are silent as to the number of coffer dams to be built; that was a matter left to the judgment and discretion of the contractor and to the satisfaction of the State Engineer. The lock was to be constructed next to the old Erie canal which was at an elevation of about twenty-five feet above it and the contract provided that the work must be done so as not to interfere with the navigation of the canal, giving the Superintendent of Public Works the right to require such precautions as may be necessary to insure its safety.
At the request of the claimant and upon the theory that ■wooden sheet piling would be more economical and in fact better, an alteration of the contract was duly made permitting that change and for additional concrete, the unit price to remain the same. This alteration contemplated an additional cost to the State of $76,768.15. The plaintiff submitted drawings of the proposed coffer dam which, in substance, made five separate coffer dams for the accomplishment of the work as proposed in the contract. • Evidently the contract contemplated that the whole work should be surrounded by sheet piling, but as to the number of coffer dams which were to be used within the inclosure the contracts and the papers connected with it are silent.
The judgment should be reversed and the claim dismissed, with costs.
All concur.
Judgment reversed and claim dismissed, with costs.
Case-law data current through December 31, 2025. Source: CourtListener bulk data.