Cilabot v. Winter Park Co.
Cilabot v. Winter Park Co.
Opinion of the Court
The appellant, who was.complainant below, brought: his bill in equity against the appellees. The bill prayed for specific performance by the defendant, the Winter Park Company, of a contract for the sale of a lot in the town of Winter Park, and for cancellation of a deed made to the same lot by said defendant to-George B. Dorn, its co-defendant; and also prayed in. the alternative that the defendant, the Winter Park Company, be compelled to refund to the complainant-the difference between the fair value of the premises- and the amount due to said company by the complainant. After demurrers to the bill of complaint were-overruled, the defendants answered the same. The-case was set down by the complainant for hearing upon bill and answer and was so heard, and upon such hearing the court dismissed the bill. By this course all the material averments of the answer were admitted to-be true.
The facts of the case as gathered from the bill and answer are substantially as follows: On the 12th day of September, A. D. 1885, the Winter Park Company agreed to sell to the complainant, and the complainant agreed to buy, the lot in the bill of .complaint mentioned. The purchase price of said lot was $250, of which amount $100 was paid in cash, and the remainder, with interest at eight per cent, per annum, was to-be paid one year from the date of said sale. The complainant went into possession, but the Winter Park Compay reserved the title to said lot, agreeing to execute a warranty deed to the complainant upon his compliance with the terms of sale. The record does not.
The Winter Park Company,
Winter Park, Orange County, Florida..
June 14th, 1888.
Charles S. Chabot, Esq.,
My Bear Sir: I enclose a statement of your account for Lot thirty, Block 31, of the town of Winter Park, which you bargained for from the Winter Park Co. on Sept. 12th, 1885, promising to pay the balance in one year from date, at eight per cent.-interest. Not having carried out any part of that arrangement, this is to-
Very resp’y,
Tire Wetter Park Co.,
Per J. S. Capen, Sec’t’y.
The above was signed in presence of Henry S. Chubb, J. H. Abbott.
This letter was accompanied by a statement of account which was as follows:
The complainant paid no attention whatever to this letter, not even acknowledging receipt. On the 26th of July, 1888, the defendant, the Winter Park Company, sold and conveyed said lot to its co-defendant • George B. Dorn for $300, and put him in possession of the same, the said defendant Dorn having full knowledge of the status of the contract between the complainant and his co-defendant. The defendant, the Winter Park Company, had according to their notice taken possession of said property before selling the -same to Dorn. The complainant by himself or his tenant had been in possession of the property a portion of the time intervening between the date of the sale and the retaking of possession by the defendant, the Winter Park Company, but what portion of said time, is .not shown by the record. The secretary of the Winter Park Company, acting for its benefit, had looked after the property, collected some rents and accounted for the same to the complainant as part of the purchase money, as shown by the statement of account herein-before set out. The complainant a short time before ^November 16th, 1889, tendered to the Winter Park «Company the amount due, and demanded a deed to the premises. The complainant offered to pay the amount due, upon delivery of a deed to the premises, or to pay the money into the registry of the court. The tender having been refused, and the Winter Park ^¡Company refusing to make the deed, the bill of com
From the facts stated it appears that the Winter Park Company had been extremely liberal in extensions of time to the complainant, and endeavored to afford him full opportunity to comply with his contract. In granting such favors it cancelled the original contract and made a new one, giving an extension ■of one year, or until September 12th, 1887. At complainant’s request it granted a further extension until •January, 1888. After this date the complainant ceased, until October 16th, 1888, long after the lot had been sold to Dorn, to have any communication with the Winter Park Company. Although it wrote him several times in reference to taxes upon the lot, and ■other matters connected with the same, he entirely ignored the letters, not even acknowledging receipt of them; and a reasonable conclusion from his actions in the matter was that ,he did not desire further negotiations with the company, and had abandoned his contract with them. During this interval the notice of June 16th, 1888, hereinbefore set forth, was sent to complainant. Not only did he fail to comply with the notice, but it failed to elicit any reply whatever from him, beyond the receipt required to be given by the recipient of a registered letter by the United States postal laws and regulations. Upon the expiration
It is admitted by all parties that the various extensions granted the complainant amounted to an acquiescence in his failure to perform his contract, and kept the contract in force until the time limited in the notice of June 14th, 1889. It is insisted by the appellant that time was not of the essence of the contract, and that the Winter Park Company had no right to make it such, or to put a limitation upon the time of performance by the complainant, by giving such notice. We agree that time was not of the essence of the original contract in this case; unless expressly stated so to be, it is not generally so regarded in a court of equity. Southern Life Ins. & Trust Co. vs. Cole, 4 Fla., 359. While time may not be the essence of the original contract, the principle is well established that where one party to a contract is guilty of laches and negligence to perform the same, and the time for performance has passed, the other party may, by giving notice, fix a reasonable time for the performance of the contract, and has the right to treat the contract abandoned if not complied with in such limited time. Waterman on the Specific ■ performance of Contracts, secs. 465-483; 2 White and Tudor’s Leading-Cases in Equity, p. 1137, note to Seton vs. Slade and authorities cited; Kirby vs. Harrison, 2 Ohio St., 326... Although the complainant was in default, he made no reply whatever to the notice. If he had desired still further extension of time he should have let his wishes be known. If he considered that he had further rights . in the matter, and that the Winter Park Company could not put a limitation of time upon...
There is another reason why we think the complainant was not entitled to spe'cific performance of the contract: He did not come into court with sufficient promptness. While a court of equity will not as-stated regard time as of the essence of a contract unless expressly made such by the contract itself, yet it will require that one who seeks specific performance of
It is claimed by the appellant that although he-might not have been entitled to a specific performance of the contract, yet that while he was a vendee in possession he made valuable improvements upon the land, and that the bill should have been retained, that he might recover compensation for these improvements. The alternative prayer of the bill is, that “said company be compelled to refund to complainant the difference between the fair value of said premises and the amount due said company.” The “fair value” of the premises is not shown in the record. The price for which it was sold to Dorn, and the value of improvements put upon it by the complainant, are the only data throwing any light upon the subject of value of the premises. The case of Lewis vs. Yale, 4 Fla., 418, asserts the general doctrine to be ‘ ‘that a court of equity can not award compensation in damages for injury sustained by non-performance of a contract, where the primary relief (specific performance) can not be decreed.” This case was upon the general subject of damages for the breach of contracts for the sale of lands, and the damages sought to be recovered were not on account of improvements erected upon the land.
There is no error in the decree appealed from, and it is affirmed.
Reference
- Full Case Name
- Charles S. Cilabot v. The Winter Park Company, a Corporation, and George B. Dorn
- Cited By
- 58 cases
- Status
- Published
- Syllabus
- 1. In a court of equity time is not considered as of the essence of a contract, unless expressly so provided by the terms thereof. Ü. Where one party to a contract for the sale of lands is in default and is guilty of laches and negligence to perform the same, the other party may give a notice fixing a reasonable lime for the performance of the contract, and has the right to treat the contract as abandoned if not complied with in such limited time. tí. Where a party to a contract is in default, and receives a notice of the character mentioned in the preceding head-note and makes no reply thereto, or any protest or assertion of right contrary to the notice, and makes no effort to comply with the requirements of the same, he will be held as acquiescing in the demand contained in the notice as consenting to a rescission of the contract, and as abandoning all rights he might have had to enforce the performance of the same. 4. There can be no general rule as to what is a reasonable time to be .allowed a party in default for the performance of a contract, when required to do so by a notice of the kind mentioned in preceding head-notes. Much depends upon the circumstances •of each case. In this case the act required to be performed was simply the payment of a sum of money. The time fixed for the performance of the act by the notice requiring performance was nearly forty days. Under all the circumstances of this case, held to be a reasonable time. ¡3. While a court of equity does not regard time as of the essence of a contract, unless it is so expressly stipulated, yet it will require of one who seeks specific performance of a contract that he shall not be guilty of unreasonable delay, and shall bring his suit with reasonable promptness. '•6. The specific performance of a contract for the sale of lands is not a matter of right in either party, but rests in the sound reasonable discretion of a court of equity. *7, In this case the complainant, who was in default in performing his contract, received from the Winter Park Company, the .other party to the contract, a notice fixing a reasonable time for the performance of the contract, or that it would consider the same abandoned, and resume possession of the land; he paid no attention to such notice, and made no effort to perform the contract for considerably more than a year, and waited for nearly a year and four months after the expiration of the time fixed in the notice, and after the property had been sold to another, before bringing his suit: Held, That such delay was unreasonable, and that by reason thereof a court of equity should not decree a specific performance of the contract. ■8. In cases where the complainant does not make such a showing as entitles him to specific performance of a contract for sale of lands, the prayer of the bill for specific performance may be denied, and if the bill contain appropriate prayers it may be retained for the purpose of adjusting other equities which may have arisen between the parties in relation to the same contract. 9. Where a vendee in possession under a contract of purchase makes valuable improvements upon the land, upon the faith of his contract, and the contract is such that specific performance can not be enforced, the vendor will be compelled to refund the purchase money, and to pay the actual value of the improvements. 10. A vendee in possession who sues for specific performance of a contract for sale of lands is entitled to compensation for improvements only when he is free from fault himself and fails to obtain specific performance of the contract by reason of some technical defect in the contract, or on account of its failure to comply with the statute of frauds. If the failure to obtain specific performance is owing to laches or negligence of the vendee to perform his part of the contract, he is not entitled in a court of equity to compensation for such improvements.