City of College Park v. Sekisui SPR Americas, LLC
Opinion of the Court
Sekisui SPR Americas, LLC, a subcontractor that worked on a sewer project for the City of College Park (“the City”), sued the City when the general contractor failed to pay Sekisui for work performed, alleging that the City was liable because it had failed to ensure the
Summary judgment is appropriate when the moving party demonstrates that no genuine issues of material fact remain and that the facts, construed favorably to the non-moving party, demand judgment as a matter of law. On appeal, we review the trial court’s grant of summary judgment de novo.
(Footnote omitted.) Vaillant v. City of Atlanta, 267 Ga. App. 294 (599 SE2d 261) (2004).
So viewed, the evidence shows that during the summer of 2005, the City began discussing the need for public works construction on sewer lines in the city, including the repair of the main sewer line on Embassy Drive that had apparently collapsed and needed emergency repair. Southern Products submitted a quote to install a sewer bypass near the creek adjacent to the intersection of Riverdale Road and Embassy Drive. On August 5, 2005, the City approved the quote and directed Southern Products to begin as soon as possible.
On August 8, Southern Products sent a letter requesting that the City use its existing Clayton County Water Authority Annual Contract (the “CCWA Contract”) in order to replace approximately 1,049
The City sought permission from Clayton County to use the CCWA Contract to complete the Embassy Drive Project. Clayton County authorized the City to use the CCWA Contract to establish the terms, unit pricing, and conditions of work in reaching an agreement with Southern Products, but notified the City that the CCWA Contract would not be extended to cover the Embassy Drive Project.
Thereafter, the City contracted with Southern Products to complete the Embassy Drive Project, notifying Southern Products that it was to proceed pursuant to the terms of the CCWA Contract. The CCWA Contract pertinently provided that a “Payment and Performance bond will be required only in the event that a job is assigned to the contractor that is an amount greater than $100,000.00.” Southern Products did not obtain a payment bond for the Embassy Drive Project.
Southern Products hired Sekisui as a subcontractor to provide all labor, equipment, and materials, as well as general and project administration services, for the Embassy Drive Project. See City of College Park v. Ga. Interlocal Risk Mgmt. Agency, 313 Ga. App. 239, 239-240 (721 SE2d 97) (2011) (“GIRMA”). Sekisui began working on the project in September 2005, and at the end of the month, Sekisui submitted its first invoice to Southern Products, who paid it after receiving payment from the City. Id. at 240. Based on circumstances at the site, the scope of work increased and the cost of the project exceeded the initial estimate. In October and December 2005, Sekisui submitted two additional invoices totaling over $314,000. The City paid Southern Products in full for Sekisui’s work on the Embassy Drive Project, but Southern Products did not pay Sekisui’s last two invoices. See id.
When its attempts to recover on the unpaid invoices were unsuccessful, Sekisui filed suit against Southern Products, which subsequently ceased operations and became insolvent. Sekisui also filed the instant suit against the City, and the trial court granted summary judgment to Sekisui on all counts, with the exception of attorney fees, which the trial court reserved upon conclusion of this appeal.
1. On appeal, the City contends that the trial court erred in denying its motion to dismiss Sekisui’s complaint on the ground that Sekisui failed to give proper ante litem notice under OCGA § 36-33-5. We disagree.
If a payment bond or security deposit is not taken in the manner and form required in this article, the corporation or body for which work is done under the contract shall be liable to all subcontractors... furnishing labor, skill, tools, machinery, or materials to the contractor . . . for any loss resulting to them from such failure. . . .
OCGA § 36-91-91.
With regard to ante litem notice, OCGA § 36-33-5 (a) pertinently provides:
No . . . corporation having a claim for money damages against any municipal corporation on account of injuries to person or property shall bring any action against the municipal corporation for such injuries, without first giving notice as provided in this Code section.
OCGA § 36-33-5 (a). The notice must be written and presented within six months of the event upon which the claim is predicated. OCGA § 36-33-5 (b).
The plain text of the statute makes clear that it applies only to tort claims regarding personal injury or property damage. See City of Statesboro v. Dabbs, 289 Ga. 669, 670 (1) (a) (715 SE2d 73) (2011); Sims v. City of Alpharetta, 207 Ga. App. 411, 412 (1) (428 SE2d 94) (1993). Based on this text, Georgia courts have held that a party is not required to provide ante litem notice for an action arising out of a contract. See Neely v. City of Riverdale, 298 Ga. App. 884, 885-886 (1) (681 SE2d 677) (2009); see also Dabbs, supra, 289 Ga. at 670 (1) (a) (party not required to provide ante litem notice for violations of Open Meetings Act).
In this case, Sekisui claimed that the City violated OCGA § 36-91-91 and sought payment for work performed under a subcontract under theories of unjust enrichment, quantum meruit, and implied obligation to pay. None of these claims are torts regarding personal injury or property damage. See GIRMA, supra, 313 Ga. App. at 245-246 (2) (concluding that Sekisui’s claims arose out of or were connected with its contract with Southern Products). Therefore, Sekisui was not
The City relies on Jacks v. City of Atlanta, 284 Ga. App. 200 (644 SE2d 150) (2007), in support of its argument that the ante litem notice requirement is applicable to claims arising under OCGA § 36-91-91. Jacks is disapproved to the extent it holds the ante litem notice requirement under OCGA § 36-33-5 applies to claims arising under OCGA § 36-91-91 because the plain text of OCGA § 36-33-5 is clear that it applies only to tort claims relating to personal injury and property damage. See Dabbs, 289 Ga. at 670 (1) (a).
2. The City contends that the trial court erred in denying its motion for summary judgment and granting Sekisui’s motion because the City was not required to obtain a payment bond since the Embassy Drive Project was necessitated by an emergency. We agree.
The requirement that a municipality obtain a payment bond for public works construction contracts with an estimated cost greater than $100,000 under OCGA § 36-91-90 does not apply to projects that are
. . . necessitated by an emergency; provided, however, that the nature of the emergency shall be described in the minutes of the governing authority. Any contract let by a county pursuant to this subsection shall be ratified, as soon as practicable, on the minutes of the governing authority, and the nature of the emergency shall be described therein.
OCGA § 36-91-22 (e). “Emergency” is defined as “any situation resulting in imminent danger to the public health or safety or the loss of an essential governmental service.” OCGA § 36-91-2 (7).
In this case, the evidence shows that the main sewer line on Embassy Drive had collapsed, and in August 2005 the City authorized Southern Products to install a sewer bypass and approved the Embassy Drive Project to replace approximately 1,000 linear feet of the main sewer line in the area. There is also no dispute that in September 2005, the City held a city council meeting in which it ratified the emergency replacement of the sewer main on Embassy Drive.
Sekisui argues that the City was not entitled to the statutory exception under OCGA § 36-91-22 (e) because its minutes from the city council meeting are insufficient to establish an “emergency” since the City did not describe or otherwise introduce evidence of any imminent danger to public health or safety or loss of an essential government function. Contrary to Sekisui’s arguments, however, the
3. The City contends that Sekisui’s claims for unjust enrichment, quantum meruit, and implied obligation to pay are barred as a matter of law because OCGA § 36-91-91 provided the exclusive remedy by which Sekisui could sue the City. We agree.
Under Georgia law, a materialman or subcontractor may not recover against an owner or general contractor with whom it has no contractual relationship, based on the theory of unjust enrichment or implied contract; rather, it is limited to the statutory remedies provided by Georgia’s lien statute.
(Citations and punctuation omitted.) Hussey, Gay & Bell v. Ga. Ports Authority, 204 Ga. App. 504, 506 (2) (420 SE2d 50) (1992); see also Callahan v. Hall, 302 Ga. App. 886, 888 (691 SE2d 918) (2010) (subcontractor is precluded from pursuing a quantum meruit claim in the absence of a direct contractual relationship). Consequently, in this case, as a subcontractor, Sekisui could not recover against the City under the implied contract theories of unjust enrichment, quantum meruit, or implied obligation to pay. See J. Kinson Cook, Inc. v. Weaver, 252 Ga. App. 868, 871-872 (2) (556 SE2d 831) (2001); Hussey, Gay & Bell, supra, 204 Ga. App. at 506 (2).
Regrettably, the only remedies that would have been available to Sekisui are now foreclosed. Notably, as discussed above, Sekisui could not proceed against the City under OCGA § 36-91-91 because no payment bond was required for the Embassy Drive Project. A subcontractor may pursue a lien against the public works owner on the funds payable to the general contractor when, as here, the legal remedy under OCGA § 36-91-91 is unavailable or inadequate. See McArthur Elec., Inc. v. Cobb County School Dist., 281 Ga. 773, 774-775 (642 SE2d 830) (2007). It is undisputed, however, that the
Judgment reversed.
The City attached several exhibits to its brief that caused the brief to substantially exceed the applicable page limit. See Court of Appeals Rule 24 (f). Sekisui moved to strike the excess pages, and the City responded by moving for permission to exceed the page limit. Since these exhibits appear in the record transmitted by the trial court, Sekisui would suffer no prejudice by consideration of the excess pages. See Court of Appeals Rule 24 (g) (we will not consider documents attached to an appellate brief that are not part of the certified appellate record). Consequently, we grant the City’s motion to exceed the applicable page limit and deny Sekisui’s motion to strike.
Case-law data current through December 31, 2025. Source: CourtListener bulk data.