Elberta Peach Co. v. Georgia Southern & Florida Railway Co.
Cases that cite this one
1 later published case cites this decision.
- Southern Railway Co. v. Moore (Ga. 1910)
This list shows which later cases cite this one. It does not say how they treated it, and no review of that has been done. Not a substitute for Shepard’s or KeyCite — verify before relying.
Opinion of the Court
(After stating the facts.)
It appears from the petition, that, "in accordance with the request made” by defendant upon plaintiff, in the letter of July 1, 1907, written and addressed to plaintiff’s agent, Jewett, plaintiff, on the morning of the 18th of the same month, requested of defendant’s master of trains at Macon, who wrote this letter for defendant, and who was in charge of the business of placing cars, to have one refrigerator car placed at Elberta on that day and another at the same place on the following day. In reply to this request of plaintiff, the master of trains immediately notified plaintiff that a car would be furnished that day, if possible, but that there were no empty Fruit Growers Express cars in Macon that morning. Later during the same day plaintiff was notified by the master of trains that defendant would be unable to furnish a car that day, but would be in position to furnish all cars needed by noon the following day. "Whereupon petitioner immediately notified defendant that the fruit was picked, packed, and on the platform, and that petitioner must'have one ear to-day and one to-morrow to move same, as the fruit was ripe.” Do these allegations show the making of a contract between plaintiff and defendant? To consummate a contract there must, of course, be mutuality of assent to a certain definite proposition. Prior to the order given by plaintiff on July 18, defendant had notified plaintiff that the Fruit Growers Express had informed defendant that all orders for cars received after 6 p. m. would be accepted subject to delay in' furnishing them, and that therefore it was necessary for defendant to receive orders for such cars before 6 p. m., to enable the Fruit Growers Express to have sufficient time to ice them and to get them on the morning
The question as1 to the measure of damages for such delajt is not up for adjudication, as a special demurrer was sustained to the paragraph of the petition in which the damages were specifically set forth; and while error was assigned upon such ruling, no reference to it appears in the brief of counsel for plaintiff in error, and the point must therefore be considered as abandoned. In one paragraph of the petition, however, which was not specially demurred to, it was alleged that by reason of defendant’s delay in furnishing
Judgment reversed, with direction.