Bailie v. Woodward Lumber Co.
Bailie v. Woodward Lumber Co.
Opinion of the Court
The Woodward Lumber Company brought its action to enforce its materialman’s lien against Mrs. M. C. Bailie, the owner, of the premises improved, and W. S. Gregg, the contractor. The case was heard by the court without the intervention of a jury. The defendant pleaded estoppel, and that she had discharged the lien by payment, part of which was paid to the materialman and part to the contractor with the consent of the materialman. Upon the hearing of the cause the defendant, Mrs. Bailie, offered to prove that she had called up the Woodward Lumber Company and talked with its superintendent over the telephone, and stated that Mr. Gregg was asking payment of $300, and that she would not pay Mr. Gregg unless she had authority from the Woodward Lumber Company to pay the same (the Woodward Lumber Company having furnished the material for the construction of the house then in process of being built upon her premises by the contractor); and that the superintendent of the Woodward Lumber Company, in reply, authorized her to pay the contractor
The Civil Code (1910), § 3352, par. 2, declares: “When work, done or material furnished for the improvement of real estate is done or may be furnished upon the employment of a contractor, or some other person than the owner, then, and in that case, the; lien given by this section shall attach to the real estate improved &s against such true owner, for the amount of the work done, or material furnished, unless such true owner shows that such lien has been waived in writing, or produces a sworn statement of the contractor, or other person, at whose instance the work was done or material was furnished, that the agreed price or reasonable value thereof has been paid: provided that in no event shall the aggregate amount of the liens set up hereby exceed the contract price of the improvements made.” It is contended that the testimony which was rejected by the court would only tend to establish a verbal waiver of the materialman’s lien; whereas the lien could only be waived in writing. The force of this evidence is, not to show a waiver of the lien, but to establish an estoppel against the material-man from asserting the lien against the property for the amount paid the contractor with the consent and upon the authority of the materialman. The owner of the premises recognized that the materialman was entitled to a lien for material furnished to the contractor, which entered into the improvement. She was clearly mindful that her property would not be discharged from the lien of the materialman if she paid the contractor without his consent and direction. Accordingly, she applied to him for direction as to whether she should pay the contractor the sum of money which he was demanding. If the.materialman authorized the payment of the specific sum to the contractor, and the sum was paid to the contractor under his direction, the materialman will be estopped from
Judgment reversed.
Case-law data current through December 31, 2025. Source: CourtListener bulk data.