District Court, D. Guam, 2021

United States of America for the use and benefit of Porges Electrical Group, Inc., a California Corporation v. Travelers Casualty and Surety Company of America

United States of America for the use and benefit of Porges Electrical Group, Inc., a California Corporation v. Travelers Casualty and Surety Company of America
District Court, D. Guam · Decided July 29, 2021
United States of America for the use and benefit of Porges Electrical Group, Inc., a California Corporation v. Travelers Casualty and Surety Company of America

Trial Court Opinion

I 8 UNITED STATES DISTRICT COURT 9 TERRITORY OF GUAM | UNITED STATES OF AMERICA for 1 the use: and. benchit Case No.: CV 15-00024 12 Plaintiff, ORDER RE: REMITTITUR 13 V. | TRAVELERS CASUALTY AND 1S | dnd PATRICIA | ROMERO. INC. 16 sUIEDERS as PACIFIC WEST 17 Defendants.

19 I. | BACKGROUND 20 Pacific West Builders (“PWB”) entered into two prime contracts with the 21 Government, one to construct a Working Dog facility at the Apra Harbor Naval 22 Base in Guam (“Military Working Dog Project” or “MWD Project’) and one to 23 construct the Red Horse Cantonment Operation Facility at Anderson Air Force 24 Base (“Red Horse Project’). PWB subsequently entered into a written subcontract 25 with Porges Electrical Group, Inc. (“Porges” or “PEG’’) with respect to certain 26 electrical work to be performed on the two projects. The projects experienced 27 various delays. PEG contends it was required to do extra work beyond the scope I of the contract and PWB failed to pay the balance due under the subcontracts.

2 PEG brought suit against PWB asserting claims for breach of contract, reasonable 3 value/quantum meruit, and recovery under the Miller Act. PWB contends it 4 suffered damages as a result of PEG’s failure to fulfill all of its contractual 5 obligations, and asserts backcharges against PEG as a result. The jury found in 6 favor of PEG on all of its claims, but also found for PWB on its claim for 7 backcharges.

8 Following trial, PWB filed a Motion for Judgment as a Matter of Law and 9 Motion for a New Trial. On April 13, 2021, the Court granted PWB’s Motion for 10 Judgment as a Matter of Law on PEG’s reasonable value claim and conditionally 11 ordered a new trial should the judgment be vacated or reversed on appeal, and 12 denied the motion for judgment as a matter of law as to all other claims. (Dkt. No. 13 288 (the “Order’’).) The Court granted PWB’s Motion for a New Trial on damages 14 only as to three categories: Field Office Overhead, Extra Work, and Fire Alarm 15 Redesign. (/d.)

16 The parties subsequently filed status reports (Dkt. Nos. 298, 300) and briefs 17 (Dkt. Nos. 301, 302, 303) and appeared before the Court on May 19, 2021 and 18 June 29, 2021, to address various matters including a proposed remittitur by PEG.

19 Il. DISCUSSION 20 A remittitur must reflect “the maximum amount sustainable by the proof.”

21 Oracle Corp. v. SAP AG, 765 F.3d 1081, 1094 (9th Cir. 2014) (citation omitted).

22 PEG proposes a remittitur in lieu of a new trial on damages as follows: 23 1. Eliminate the award regarding the Fire Alarm REAs entirely.

24 2. Recalculate the disputed items of extra work awarded, by 25 omitting all labor costs and adding mark-ups for only home 26 office overhead and Guam gross receipts tax (and not adding a I field overhead mark-up).* 2 po Working Dog 3 Remuittrttur Amount T&M #3 $3.915.74 $1,372.65 PpT&MaAS PATE OBAST $0.00 | 6 PT&M#1 1891 STLT4| $1,897.66 | g 9 Remuittrttur Amount 12 PpTeMeRO OOH 4G BZ □□□□□□□ | PpTRM □□□ B5OLOF | $80.00 | 3 Te&M#8 GOB BOR BT □□□□□□□ | pTeRM#9 TOA $50.00 | *The trial exhibits in the table above were identified by PEG as evidence 15 supporting the remittitur.

17 3. Apply a further reduction to the total award equal to 5-percent 18 of the agreed contract change orders (to eliminate any 19 duplication of field overhead costs between them and the field 0 overhead delay damages).

21 Contract Contract Increase 5% of Contract Unpaid Subcontract Increase Balance After 22 Adjustment 25 (Dkt. No. 301.)

26 Based on the above, the total proposed amount to be remitted by PEG for 27 both projects is $94,486.73.

28 The final accounting for each project based on PEG’s proposed remittitur is I set forth below: 19 Thus, based on PEG’s proposed remittitur, PEG contends an amended judgment should be entered in the amount of $520,216.70 against PWB (in 21 comparison to the jury’s award of $614,703.43), and $284,614.33 against 22 Travelers Casualty and Surety Company of America (in comparison to the jury’s 23 award of $379,101.04).!

24 The Court finds PEG’s proposed remittitur is “sustainable by the proof” 25 based on the trial record. Oracle Corp., 765 F.3d at 1094.

27 ' PEG filed a proposed amended judgment, (Dit. No. 301-3.) Defendants represented to the Court during the June 29, 2021 hearing that PEG’s proposed 28 amended judgment accurately reflects Plaintiff's requested remittitur.

I Tl. CONCLUSION 2 Accordingly, the Court grants PEG’s request for a proposed remittitur in the 3 amount of $94,486.73 in lieu of a new trial on damages. An amended judgment 4 shall be entered consistent herewith.

5 PEG’s request for clarification or reconsideration of the order granting in 6 part Defendant’s motion for a new trial (Dkt. No. 301) is denied as moot.

7 PWB’s request for the Court to admit excerpts of the Prime Contract into 8 evidence which it contends it would have submitted as evidence during a new trial 9 on damages (see Dkt. No. 302) is denied.

11 IT IS SO ORDERED.

13. | DATED: July 28, 2021. (i<— ie Race UNITED STATES DISTRICT JUDGE

Case-law data current through December 31, 2025. Source: CourtListener bulk data.