Lord v. Walker
Lord v. Walker
Opinion of the Court
OPINION OF THE COURT BY
Tbe plaintiffs brought a bill fox an injunction to enjoin and restrain the superintendent of public works from executing a certain contract with the defendant Walker for dredging the Alakea street slip and from approving any vouchers for work done or materials furnished under the contract, and to restrain the auditor of the Territory from approving any vouchers for
The bill shows that the superintendent advertised for bidders as follows:
DREDGING ALAKEA STREET SLIP.
“Proposals will be received at the office of the supt. of public works, until 12 o’clock noon of Nov. 19th, 1904, for excavating and dredging Alakea street slip, Honolulu, T.H.
“Plans and specifications are on file at the office of the asst. supt. of public works, copies of which will be furnished intending bidders on receipt of $5, which sum will be returned intending bidder after lie has deposited his bid and returned the plans and specifications.
“Proposals must be submitted on the blank forms, which will be furnished by the asst. supt. of public works and enclosed in a sealed envelope addressed to Hon. C. S. Holloway, supt. of public works, Honolulu, T. H., endorsed ‘Proposal for excavating and dredging Alakea St. slip.’
“Each proposal must contain the full name of the party or parties making the same and. all persons interested therein and must be accompanied by a certified check of 3 per cent, of the amount of the proposal, payable to C. S. Holloway, superintendent of public works, as surety that if the proposal be accepted, a contract will be entered into.
“No proposal will be entertained unless made on the blanks furnished by the asst. supt. of public works, previous to 12 o’clock noon on the day specified.
“The superintendent reserves the right to reject any or all bids.
“C. S. Holloway,
“Superintendent of Public Works.
“Dept, of Public Works, Honolulu, Sept. 6th, 1904.”
4.
“That in response to said advertisement several parties filed with said Superintendent of Public Works proposals or bids for the work referred to therein, among them being the respondent, John Walker, and said complainant, Ixird and Belser.
*439 5.
“That accompanying the proposal or bid of said complainants was a certified check of 3 per cent, of the amount of the proposal made payable to said G. S. Ilolloway, Superintendent of Public Works, as surety; that if the proposal be accepted a contract would be entered into, in accordance with the provisions of said, advertisement.
6.
“That upon the opening of said bids or proposals, it was-found that the lowest bidder was the said respondent, John Walker. And that it also then appeared that the bid of said John Walker was not accompanied by a certified check of 3 per cent, of the amount of his proposal as required by the terms-of the aforesaid advertisement.
7.
“That said bid of said respondent, John Walker, was accom-. panied by a pretended certified check, consisting of a piece of paper containing the following words and figures, to wit:
“Honolulu, 19 November, 1904.
“Pay to the Superintendent of Public Works or order the-sum of six thousand dollars.
“To Messrs. Theo. H. Davies & Co., Ltd.
‘Honolulu
“John Walker.”
And that written across the face thereof were the following words, to wit:
“Certified. Theo. H. Davies & Co., Ltd.
“W. IT. Baird, Treasurer.”
8.
“That the said paper was not and is not a certified check within the meaning and intent of the aforesaid advertisement inasmuch as Theo. H. Davies & Co., Limited, the corporation therein named as drawee is not a banker nor a banking house and is not engaged in the banking business. And that said paper does not purport to be drawn upon any fund or deposit in the possession of said corporation or belonging to the said John Walker.
“And complainants are informed and believe and so allege upon information and belief that said paper or pretended check was not in fact drawn upon or against any such fund or deposit.
9.
“That said respondent, O. S. Holloway, as Superintendent of Public Works, has awarded the contract to perform said work to*440 the said John Walker, and said Holloway and said Walker are about to execute such contract and a bond in conjunction therewith for the completion of the work.
10.
“That said John Walker is about- to commence work under -said contract; and said Superintendent of Public Works is about to incur obligations thereunder in the name of the Territory of Hawaii, and intends to pay out large sums of money as said work progresses and to approve vouchers therefor, and for materials to be furnished under said contract by said John Walker; and that said J. IT. Fisher, as auditor aforesaid will, if not enjoined, issue warrants upon the treasury of the Territory to said John Walker in payment of the obligations so proposed to be incurred by said Superintendent of Public Works as aforesaid.
11.
“That said contract is null and void and contrary to law and the awarding thereof to said John Walker as herein set forth was illegal and unfair and will result in irreparable injury to the complainants herein as well as to all other taxpayers of said Territory; and deprives said complainants of their right of fair, equal and impartial competition under the law in bidding on public contracts.”
The answer of the superintendent and auditor admitting substantially the averments in the bill denies “that the bid of said J ohn Walker was not accompanied by a certified check of 3 per cent, of the amount of his proposal as required by the terms of the aforesaid advertisement.
“They deny that the paper filed by said John Walker was not and is not a certified check within the meaning and intent of the aforesaid advertisement, and have no knowledge or information sufficient to form a belief as to the other allegations contained in paragraph 8 of said complaint, and therefore deny the same and leave the complainants to their proofs thereof.”
The answer of the defendant Walker is in substance the same as that of the superintendent and auditor.
The bid of the respondent Walker was $168,000. The next lowest bidder was $188,900. The bid of the complainants was $209,000, there being one higher bid for $215,860. The complainants appellants contend as follows:
(2.) That the requirement of a certified check must be understood in its usual acceptation as known in the law.
(3.) That the requirement having been imposed upon all bidders both by the terms of the advertisement and also by the specifications, it became a condition precedent, and no bid not accompanied by such a check could be considered.
(4.) That if the superintendent had authority to prescribe such a condition it was binding on himself as well as on the bidders and could not be waived.
(5.) That, if the superintendent had no authority to impose such a condition, the imposition of it invalidated the whole advertisement and the bids filed pursuant to it.
(6.) That even if the superintendent had authority to insert the condition in the advertisement, and also to waive it, he had no authority to waive the provision of the specifications which contained the same clause.
(7.) That, therefore, the decree should be reversed and the cause remanded with instructions to grant the injunction.
We hold that the superintendent of public works had authority to make the condition that a certified check should be deposited with the bid, that such requirement was a reasonable one and that it was not within the power of the superintendent to waive ii. Also that the requirement was obligatory upon all bidders and that a bid unaccompanied by such á check or its equivalent could not be considered. The question remains, did the. respondent Walker substantially comply with the requirement. Strictly, the instrument filed by the respondent Walker was an inland bill of exchange accepted by Theo. H. Davies & Co., Ltd. In its general characteristics other than it was not drawn on a banker it was substantially equivalent to an accepted and certified check. In general terms a check is an inland bill of exchange. Edwards on Bills, 396. Daniel on Negotiable Instruments, Sec.
The principal points of difference between a check strictly considered and an accepted bill of exchange are generally as follows: (1) A check is always drawn on a bank or banker; (2) No days of grace are allowed; (3) The drawer of a check is not discharged by the laches of the holder unless he has sustained injury (4) A check is not due until payment is demanded; (5) It is by its face the appropriation of so much money of the drawer; (6) It is not necessary that the drawer of a bill should have funds in the hands of the drawee. The character of a check, however, changes on being certified; it then more closely resembles a bill of exchange. The certification in the one case and the acceptance in the other are in effect identical
Moreover, a further reason why a strict definition of the term
As for the plaintiff’s claim that the acceptance of drafts is not authorized by the charters of commercial houses, “in general it may be said that one whose rights are not injuriously affected by reason of the fact that a corporation is acting in excess of its powers, or beyond the warrant of law, has no standing in court to complain of the same.” 5 Thomp. on Corp., Sec. 6030. A violation of the charter, if any there was in this case, “does not of itself affect any of his (the plaintiff’s) rights.” Railroad Co. v. Ellerman, 105 U. S. 174.
The injunction prayed for is disallowed and the complainants’ bill of complaint dismissed.
Reference
- Full Case Name
- E. J. LORD AND J. J. BELSER v. JOHN WALKER, C. S. HOLLOWAY, SUPERINTENDENT OF PUBLIC WORKS, AND J. H. FISHER, AUDITOR
- Cited By
- 1 case
- Status
- Published