Blake v. City of Dubuque
Blake v. City of Dubuque
Opinion of the Court
We do not think there is error in the instruction, and refusal of the court. The matter rests upon the original contract, and not upon any promise made by the officers. And the terms of the contract, do not necessarily confine his measurement to the precise grade. Those terms are somewhat general, and the work is placed under the direction of the engineer and commissioner, both which circumstances, indicate an adaptation of the contract to the character of the work, it being in rocky soil; and, therefore, not to be simply cut and- filled to a certain grade, but rocks were to be blasted and excavated, and those running in unforeseen directions, and with uncertainF declinations, thus
This is the light in which the contract appears to our minds, and it does not seem to be one, requiring the contractor either to cut the rocks at the specific grade, or to blast lower, and then fill at his own expense. It is substantially a contract to make the street of a certain grade, in the best manner, under the direction of the officers.
Judgment affirmed.
Reference
- Cited By
- 1 case
- Status
- Published