Fish v. Wolfe
Fish v. Wolfe
Opinion of the Court
After the work had been let the company could not, of course, require different work to be done, or the acceptance of a mode of measurement less favorable than that originally agreed upon, unless there was something in the contract which authorized the company to make a change. The appellants contend that there was.
The essential provisions of the contract' relative to the question in issue were, in substance, that the company might relocate its road and change the grade-line if deemed expedient ; that whether the work became greater or less by any change that might be made, the contractors should be paid only for the actual work done, and at the regular prices, ex
It appears from the evidence that upon this road, as upon others, the sections were made for the convenience of letting the grading; that they were generally made each about a mile in length, but sometimes longer and sometimes shorter; that the design is to embrace in each section, as nearly as practicable, the same amount of excavation and embankment, áo that a section can be let singly to a contractor, and the grading be done without much borrowing or wasting; that upon the .relocation of this road it was found necessary, in order to embrace about the same amount of excavation and embankment in each section, to make section 79 much less than a mile and section 80 much greater. It resulted that the thirteen hundred feet in question, which would have ordinarily been embraced in section 79, was thrown into section 80. But it appears that, notwithstanding section 80 was lengthened so as to include the thirteen hundred feet, consisting mostly of excavation, that section contained an excess of embankment, and, notwithstanding section 79 was shortened so as to exclude the thirteen hundred feet, that section ■contained an excess of excavation.
The plaintiff claims to be aggrieved because the division between sections 79 and 80 was not so placed as to make the excess of excavation in oné, and excess of embankment in the other, still greater. It is not claimed by him that Eish, Neely & Co. have not been paid for all their work once as their contract provided. The mode of estimating neees
Now we see nothing in the contract which justifies this claim. The plaintiff insists that, under their contract, they, Fish, Neely & Co., were entitled to a job not less advantageous than they would have had if there had been no relocation and no disturbance of sectional divisions. To this we think it may be said, that when they agreed that a relocation might be made, and that a mode of measurement should be adopted that should, as nearly as practicable, pay them once, and only once, for their work, they precluded themselves from insisting upon a sectional division that should work an entirely different result. Besides, if we should concede that, in the-relocation, they were entitled to a division between their sections that would have made their job not less advantageous than it would otherwise have been, it does not follow that the sections should have been made coterminous with the respective sections in the original survey. No two lines of road, even near together, would have precisely the same cuts and fills. To give Fish, Neely & Co. the same excess of excavation in one section, and the same excess of embankment in-the other, would necessarily have required a change in length. Indeed, the decree of the court below was not based upon the-idea that Fish, Neely & Co. were entitled to have the sections in the relocated.road made coterminous with the respective sections in the original survey. The court found that, if they had been so made, Fish, Neely & Co. would have been allowed for nine thousand two hundred and nine cubic yards, for which they were not allowed. But that fact was not made the basis of the decree. The decree was based upon a fact
The court found that Fish, Neely & Co. should have been allowed for ten thousand three hundred and five cubic yards more than they were allowed. But what length of section would have given that allowance no witness undertakes to state, and probably no one could have stated.
The decree was based solely upon the ground that Fish? Neely & Co. were entitled to be allowed for ten thousand three hundred and five cubic yards more of excess of excavation in section 79, because there was that amount more of excess' of excavation in the corresponding section in the original survey. The fact was found from the testimony of one Lalor. He said: “Section 79 was (in the original survey) five thousand three hundred feet long. The change (in sectional division) was made to equalize, approximately, the quantities of excavation and embankment in each section. The difference would amount to ten thousand three hundred and five yards less on the profile as it is than as it was originally.”
Now, if Fish, Neely & Co. were entitled to a job under their contract not less advantageous than they would have had if there had been no relocation, and no change of sectional divisions, it does not follow that the decree can be sustained. No detriment was suffered by the change, unless there would have been an advantage in grading the original section 79, by reason of the excess of excavation which would have been in it, and we are unable to say that there would have been. As we understand it, there is not necessarily an advantage to be derived from an excess of excavation. Under some circumstances it seems clear that an advantage would arise. If an adjacent section has an .excess of embankment, and the two are let together to the same contractor, and can be graded ¡together without regard to the division between them, and the earth derived from excess of excavation in one can be fused for excess of embankment in the other, then, to that
Reversed.
Case-law data current through December 31, 2025. Source: CourtListener bulk data.