R. A. Brown & Co. v. Board of Supervisors
R. A. Brown & Co. v. Board of Supervisors
Opinion of the Court
It appears that certain proceedings ■ were had for the location and construction of a public ditch in Harrison and Pottawattamie counties, under the provisions of Code, section 1939 et seq., and that plaintiff’s bid for a portion of the work was accepted. But, before any actual work had been done by plaintiff in performance of its con
It is contended, however, for the plaintiff, that, by mutual understanding between him and the respective boards of supervisors, the performance of1 the work was to be postponed until the validity of the first proceeding and the constitutionality of the law should be determined. It appears from the testimony that there was doubt on both sides as to the validity of the proceedings, and that representatives of the plaintiff had conversations and correspondence' with the county auditors and members of the boards of supervisors as to whether plaintiff should proceed. But there was no objection on the part of defendants to the carrying out of the contract by plaintiff, and the sole question was whether plaintiff was likely as a matter of law to be able to get the money which he was to have for his work. The defendants interposed no obstacle to the performance of the work, and we think that plaintiff must be held to have acted at its peril in postponing the performance until after the time for performance had expired. Indeed plaintiff seems to have abandoned, for more than a year prior to the institution of the new proceeding, any idea of performing the contract, and, only after the decision in Ross v. Board of Supervisors of Wright County, 128 Iowa, 427, was handed down by this court, in which it was held that proceedings already commenced under the provisions of the Code might be continued under the provisions of Acts 30th General Assembly, page 59, chapter 67, by complying with the requirements of the new statute^ did plaintiff entertain any idea that he had a contract which might be specifically enforced. Plaintiff was not a party to any action with regard to the validity of the proceedings first instituted for the construction of a ditch, nor was he enjoined by any action from carrying out his contract. The county officers, and members of the boards of supervisors with whom plaintiff conferred and corresponded had no authority to set
The contractor shall not be entitled to any claim for hindrance or delay from any cause whatever in the progress of the work or any portion thereof, but such hindrance may entitle the contractor to an extension of time for the completion of this contract sufficient to compensate for the detention; the same to be determined by the boards of supervisors of the several counties, provided that immediate notice of said cause of detention be served on the said boards of supervisors.
No notice of any cause of detention was given by plaintiff to the boards of supervisors or either of them, and no extension of time was granted. It is to be borne in mind that plaintiff’s failure to carry out his contract was not attributable to any fault or omission of the defendants. Nothing which defendants were to do under the contract prior to its performance by plaintiff was omitted to be done. The simple fact is that plaintiff thought the proceeding to be illegal and his contract unenforcible, and for that reason failed to perform. It cannot now ask equitable relief on the theory that, if it had performed, the contract would have been enforceable as against defendants.
We reach the conclusion that plaintiff was not entitled to any relief, and the decree of the lower court is- affirmed.