Conn v. Milliken
Conn v. Milliken
Opinion of the Court
The defendant entered into a contract with Humboldt County for the excavation and construction of a certain ditch, by the terms of which the work was to be done in a good and workmanlike manner, and in compliance with the plans and specifications therefor. The ditch was to be completed within a certain time, unless an extension of time for its completion was made necessary by the act of the county, and payments for the work were to be made in accordance with the statute. Thereafter the plaintiff and the defendant entered into the following contract:
This agreement made between S. Milliken of Walnut, 111., and Geo. Conn of Royal Center, Indiana, wherein S. Milliken agrees to give the said Geo. Conn (9) nine cents per cubic yard for the excavation of branch A, also tributaries one and two in drainage district No. (6) six in Humboldt County, Iowa, wherein the said Geo. Conn agrees to do said work in a satisfactory and workmanlike manner under the supervision of the county engineer. The said Geo. Conn is to draw his pay according to S. Mil-liken’s contract with said county on S. Milliken’s order on said county, the said Geo. Conn is to ship dredge at once to job and commence work as soon as possible.
The plaintiff set out in his petition a part of the appellant’s contract, with the county, and alleged that under the terms thereof the ditch was to be completed by the 1st of August, 1907. It. was further alleged that the appellant failed to construct the ditch within the time fixed by the contract, and failed to keep the ditch open, as required by the contract. Plaintiff also alleged: That he completed his work according to the terms of his contract with the appellant before the 1st day of August, 1907. That the same was duly approved, and accepted by the engineer of the county and by the appellant, and
The appellant’s principal contention is that the plaintiff agreed to accept and did accept an order on the county for his work, and that the order issued by the appellant was an absolute payment so far as he is concerned, and that the plaintiff’s only remedy is on the order. It may be conceded for the purposes of this case that if the plaintiff had agreed to accept an order on the county as payment absolute, or if he did so accept such order without any previous agreement, he would have to look to the county alone for his money. But the contract does not so stipulate. .It provides only that the plaintiff shall draw his pay according to the' appellant’s contract with the county on Milliken’s order on said county. Fairly, construed, the provision contemplates payments to the plaintiff at the time they became due the appellant from the
The second count of the petition was for work done in cleaning out a part of the ditch. An' itemized statement of the days and hours engaged in such work was not required.
We are of the opinion that the demurrer was rightly overruled, and the judgment is therefore affirmed. ■
Case-law data current through December 31, 2025. Source: CourtListener bulk data.