Supreme Court of Iowa, 1941

Reconstruction Fin. Corp. v. Deihl

Reconstruction Fin. Corp. v. Deihl
Supreme Court of Iowa · Decided February 18, 1941 · GARFIELD, J.
296 N.W. 385; 229 Iowa 1276 (North Western Reporter)

Reconstruction Fin. Corp. v. Deihl

Opinion of the Court

Since the original decision in this case, all parties before the court have entered into a stipulation of settlement, copy of which is on file with the clerk of this court. The parties jointly have petitioned for a rehearing and the court finds that such rehearing should be granted.

IT IS THEREFORE ORDERED that rehearing is granted as prayed and that as a result thereof the cause is remanded to the district court for a decree in conformity to the terms of the stipulation and in accordance with the provisions of chapter 358.2 (formerly chapter 358-F1) of the Code.

MILLER, SAGER, STIGER, BLISS, and WENNERSTRUM, JJ., concur.

HALE, C.J., takes no part. *Page 1291