Kessler v. Grocers' Chemical Works
Kessler v. Grocers' Chemical Works
Opinion of the Court
This was a suit by appellants, who were partners doing business under the firm name of Kessler, Riebenthaler & Company, against appellee, a corporation, to foreclose a mechanic’s lien. Appellee filed answer to the complaint in general denial, 'also a counterclaim, to which appellants’ demurrer was overruled, and the cause was put at issue by appellants’ reply in general denial. At the close of appellants’ evidence in chief, appellee moved the court for judgment in its favor on the ground that appellants had failed to show that the notice of lien had been filed in time, which motion the court sustained. The overruling of appellants motion for a new trial is the only error assigned which need here be considered.
It clearly appears from appellants’ evidence in chief that on January 26, 191-2, appellee and one Hoffman entered into a written agreement for the construction of a three-story brick factory building in the city of Evansville, Indiana, on the real estate described in the complaint and owned by appellee; that said contractor Hoffman employed appellants to do the brickwork and furnish materials for $5,700. The specifications for the construction of the building contained, among others, the following provisions:
“Brick layer is to work in harmony with * * * other contractors, to assist in the setting of all materials of all kinds which come in contact with his work. After the walls have thoroughly set he is to fill in around the building and repair all paving that has been disturbed. All joints between brick and stone and all brick laid back of stone shall be made tight to insure uniform settling. Point up under the sills after the work is set to make same air tight. * * * All holes which may be left in the brick work, for use of build*379 ing scaffolding or any other cause, shall be neatly filled up and finished by the mason when the building is nearing completion. All .cracks of any kind which may show around frames, or in any other part of the brick work shall be carefully closed up with cement. * * * All brick to be laid at such times and in the best manner for the interests of all contractors, and with the general progress of the building always considered. All brick work as shown necessary to complete the building is to be done without additional expense to the owner.”
It is also shown by the testimony of appellants that the brickwork was completed some time in June, 1912, but that in August, after the' other contractors had performed their part of the work, appellants went back to finish up; that they requested appellee to indicate what was lacking, and its architect, in the presence of appellee’s secretary, gave them a note of what he wanted done to finish up the work, and it was done; that some loose bricks that had been knocked loose by the carpenters were replaced; some pointing up of the brickwork was done; wooden strips were put in above the windows; that appellants did some work around the doors and put in bumpers for the sliding doors, all of which required the work of one man for a day and a half; that it was the custom that damage and defects by other contractors should be fixed up by the bricklayers; that no extra charge was made for any of this work for the reason that it was required by their contract; that this work was done about August 20 or 22, 1912; that appellants filed their mechanic’s lien, which was introduced in evidence, on October 10, 1912; that there was due and owing them for work done under their contract a balance of $851.05, which was past due and unpaid.
Under the authorities cited above and our mechanic’s lien law, which this court has said should be liberally construed to the end that a mechanic or materialman shall have the protection which the statute was intended to give, where it is clear that one falls within the protection of the statute (Toner v. Whybrew (1911), 50 Ind. App. 387, 98 N. E. 450) and the evidence introduced by appellants before they rested their case, we are of opinion that the trial court should have found for appellants. It follows that the finding and judgment of the trial court is not supported by sufficient evidence and is contrary to law, and that the court erred in refusing a new trial.
The cause is reversed, with instructions to sustain appellants’ motion for a new trial.
Note. — Reported in 113 N. E. 317. Mechanic's lien, last work done as fixing time for filing, 12 L. R. A. (N. S.) 864; 27 Cye 147.
Case-law data current through December 31, 2025. Source: CourtListener bulk data.