Hartzell v. Pranger
Hartzell v. Pranger
Opinion of the Court
This was a suit by appellee Pranger, against appellants, to recover a balance alleged to be due him for installing a heating plant in appellants’ residence, and to foreclose a mechanic’s lien against the real estate upon which the residence is located.
Briefly,- the complaint alleges that in 1912 appellee entered into a contract with appellants by which they agreed to pay him $638 to install a' hot-water plant for heating their dwelling house, and to furnish all materials therefor; that he performed said contract, and completed the work on May 23, 1913; that said materials, work and labor were of the reasonable value of $638; that appellants paid $400 on said contract leaving $238 unpaid, which, on demand, they refused to pay; that on July 19, 1913, within sixty days after completing the work, he filed notice of a mechanic’s lien, which was duly recorded, and is made a part of the complaint by exhibit, praying judgment for said balance, $100 attorneys’ fees and for foreclosure of said lien.
To this complaint appellants filed an answer in two paragraphs, the first being a general denial, and* the second a plea of payment to which appellee replied in general denial. Appellants also filed a counterclaim setting up in substance that appellee was employed by the P. & H. Sup
Appellee filed a reply in general denial to the counterclaim. The cause was submitted to the court for trial, resulting in a finding and judgment in appellee’s favor for $167, and for■ foreclosure of appellee’s lien and sale of the real estate described in the complaint.
The only error relied on for a reversal is the overruling of appellants’ motion for a new trial, in support of which it is urged that the decision and finding of the court is contrary to law, and is not supported by sufficient evidence.
Appellants in their brief make no contention that the
The contract between appellee and appellants for the installation of the heating plant was • a verbal one, and there is a direct conflict in the evidence by the parties as to what the contract was with reference to the time when the work should be paid for. Appellee contends that he was to be paid for the work when the same was completed, and that his contract to install a heating plant that would heat appellants’ residence to seventy-two degrees in zero weather was not a condition precedent to his receiving payment for the work.
Appellants contend that one-half of the contract price was to be paid when the heating system was installed, and the other half when the plant was tested out and heated the house to seventy-two degrees in zero weather. Appellants admit that $300 of the contract price was paid before the heating system was installed and that an additional $100 was paid about the time the system was installed. The sum paid by appellants was almost two-thirds of the contract price, and their conduct in that respect is wholly inconsistent with their contention here.
It is not contended by either party to this appeal that any time was fixed by the contract in which the work was to be performed. It is admitted by appellee that the heating plant was installed in the fall of 1912.- The evidence shows that during the following winter appellants were making complaint that the plant did not work satisfactorily, and appellee on different occasions secured the services of experts to examine the plant, and along in March was advised by one of such experts that a change should be made in the boiler by removing a section. This advice was communicated to appellant Hartzell and appellee was thereupon directed to “go ahead and take that section of the boiler out of there.” It is not disputed that
In the case of Stephenson v. Ballard (1882), 82 Ind. 87, the court said: “In the case at bar, the claim is for work and also for materials in repairing a dwelling-house, and the suit is by the original contractors, who did the work and furnished the materials under one entire contract, and the notice was filed within sixty days after the last work done, but not within sixty days after the materials were furnished; they were furnished two months before the last work was done. In such a case, upon such an entire contract, the statute is satisfied if the notice is filed, as it was in this case, within sixty days after the last work done.”
In the case of Jeffersonville Water Supply Co. v. Riter (1894), 138 Ind. 170, 37 N. E. 652, a standpipe was so far completed as to be ready for testing and inspection in September, but it was not actually tested by filling with water until November, when leaks were found which were closed and the work finally received. The court held that the work was only then finished, the additional labor being in fact necessary and performed by the mechanic. See, also, Whitcomb v. Roll (1907), 40 Ind. App. 119, 81 N. E. 106.
We are of the opinion that the court below was clearly fight in concluding that appellee filed his notice of lien in time, and was entitled to foreclosure of the lien. As stated before, the other questions involved in appellants’ motion for a new trial were decided in appellee’s favor upon conflicting evidence, and in such ease this court is powerless to disturb such finding. Judgment affirmed.
Note. — -Reported in 112 N. E. 530. Mechanic’s lien: (a) whether work done or material furnished in perfecting original work are
Case-law data current through December 31, 2025. Source: CourtListener bulk data.