Hale & McClure v. Johnson & Wiggins
Cases that cite this one
1 later published case cites this decision.
- Orr v. Fuller (Mass. 1899)
This list shows which later cases cite this one. It does not say how they treated it, and no review of that has been done. Not a substitute for Shepard’s or KeyCite — verify before relying.
Opinion of the Court
The opinion of the court was delivered by
No. 1. “ Under the written contract Johnson & Wiggins were to receive $3.75 per perch for performing the whole of the stone work. As they only finished a part of the work, the value of the part they did perform, can be ascertained by the cost of completing the remainder of the building.”
General charge: “ If the jury believe that when Johnson and Wiggins abandoned the work, they did so in consequence of Hale and McClure’s not furnishing material as required by Johnson and Wiggins, then plaintiffs, would be entitled to recover $3.75 per perch actually erected, and for such damages as may have been proven that Johnson and Wiggins suffered in consequence of the failure of Hale and McClure to comply with their part of the contract.”
We are of the opinion that thé court was right in refusing the first of these instructions. It is no doubt true, that the rule which it is quite plain was intended to be expressed therein, or at least one similar in principle, might be found to apply in some measure to a case substantially like the one stated in the pleadings in this record; but if so applicable, it would be necessary that it should be couched in such terms as would not be calculated to mislead the jury, when they should come to pass
As to the last instruction above set out, we think it was wrong, and for the reason that it is not in conformity with the rule laid down in the statute by which to estimate the amount which a party in a case of this kind is entitled to recover. This was an action brought under the provisions of the Mechanics’ Lien Act, ch. 137, Comp. L. 1862. Section 11 of said act provides as follows:
“ Sec. ll.-"When the owner of thé land shall have failed to perform his part of the contract, and by reason thereof the other party shall, without his own default, have been prevented from performing his part, he shall be entitled to a reasonable compensation for as much thereof as he has performed in proportion to the price stipulated for the whole; and the court shall adjust his claim accordingly.”
The difference between the rule here established and that expressed in the instruction given is apparent at a glance, and needs not to be enlarged upon. For the