Wisconsin Engine Co. v. Altoona Portland Cement Co.
Wisconsin Engine Co. v. Altoona Portland Cement Co.
Opinion of the Court
The opinion of the court was delivered by
The plaintiff sued to recover an alleged balance of $66,000 of the purchase price for three gas engines built for the defendant. In December, 1907, it contracted to build and furnish three engines of a specified kind in strict accordance with the ■ specifica
Each engine was to develop 550 brake horsepower and to operate alternating generators in parallel with each other, the title and right of possession to remain in the plaintiff until final payment should be made. In November, 1909, a supplementary agreement was entered into reciting that “the three engines furnished under the original contract are not performing in a manner as to fulfill the guarantee set forth in the original contract,” and providing that the engine company should, with all possible speed, replace all defectivo parts and proceed with the work in such manner that the first engine should be in perfect condition according to contract not later than January 15, 1910, the second and third not later than March 15, 1910; to maintain until the completion of all permanent changes a sufficient force of mechanics' to make any changes, alterations, and repairs without additional cost to the
“It is further agreed that after all permanent changes in the design and construction have been made upon the first engine the party of the second part shall have the privilege of operating said engine for a term of 45 days, and to notify the party of the first part at any time during these 45 days to run a 72 hour test to ascertain if said engine in its redesigned and reconstructed condition will meet all the stipulations and guarantees of the original ■ contract.
“It is further agreed that if by the result of this test or by the failure of the party'of the second part to have the first engine ready for such test within the stipulated time, or by the ordinary operating conditions, it should be .demonstrated that the terms of1 the original contract have not been fulfilled, the party of the first part shall have the right at his own option to notify the party of the second part to remove each or any of the three units and if the party of the second part fails to comply át once with such notification then the party of the first part shall have the right to remove any or all engines with its own help at the expense of the party of the second part, and the party of the second part ■agrees to remit and refund upon removal of each engine from the foundation of the party of the first part one-third (%) of the sums paid to this date in stock, cash and note, provided however that the party of the first part shall not use the first engine more than two (2) months, the second engine more than four (4) months, and the third engine more than six (6) months, after the test has been demonstrated that the guarantee of the original contract has not been fulfilled.”
The petition alleged that the engines had been furnished in accordance with the contract,- that after each and all of them were completed and in place and in operation they were operated for a period of more than forty-five days, and that during such period (namely, on or about the twentieth day of May, 1910) the plaintiff notified the defendant to run a seventy-two-hour test to ascertain if the engines would meet all stipulations and guarantees in the contract, that the defend-.
Special findings were returned to the effect that the plaintiff first offered the defendant the seventy-two-hour test provided for in the contract about May 21, 1910, and the last test about June 22, 1910, at Kansas City, Mo. That the first test was not refused “except under the supervision of Victor Beutner”; that the second test was refused “in a measure”; that the defendant started using engine No. 3 about July 1, 1910, after this suit was begun, engine No. 2 about July 1, and engine No. 1 about July 1, 1910, and quit using engine No. 3 about December 20, 1910, No. 2 about November 15, 1910, and No. 1 about January 10, 1911. That the defendant notified the. plaintiff on July 22, 1910, that all three of the engines failed to comply with the contract and ordered them removed; that it used the engines more or less to operate its plant from July 1, 1910, to January 1, 1911.
The plaintiff appeals and complains of the rejection and admission of certain testimony, of giving and refusing certain instructions, refusing to require a more direct answer to question number four, overruling the
The plaintiff contends that it was entitled to judgment on the special findings. It is argued that acceptance could be brought about either by a seventy-two-hour test or by trial under ordinary operating conditions; that if the plaintiff demanded the seventy-two-hour test that was the only means of demonstration open to the parties; if the plaintiff failed to offer the engines for test within the stipulated period the trial under ordinary conditions would necessarily follow as a means of determining the quality of the engines, and that, a failure to make the test or permit it to be made operated as an acceptance; that the findings of the jury concerning the time to which the engines were used showed acceptance by the defendant; that the defendant ran its plant with the engine to within six days of the six months period after offer of test by the plaintiff, thus showing a fixed design to get the maximum use out of the engines and still avoid an acceptance.
It must be borne in mind, however, that the general verdict was in favor of the defendant, and unless the special findings are consistent with one another and contrary to the verdict they can not form the basis for a judgment. These findings do not show that the defendant refused the first offered test except under the supervision of Beutner, who was not then with the •company, while they show that the second was refused only in a measure. The findings as to the time the engines were used by the defendant were simply to the effect that they were used “more or less to operate its plant” which is too indefinite to overturn the general verdict.
Complaint is made that the court read the. contracts to the jury and attempted to give the substance of the pleadings without plainly advising what the issues were. An examination of the instructions, however, shows that in numbers four to seven, inclusive, the
It is complained that in the eleventh and twelfth instructions the jury were told that they must determine-whether or not the engines conformed to the terms and specifications of the contracts '“without telling the jury, either at that time, or before or afterwards, what, the terms and specifications of the contracts were.” But, as already suggested, not only were the claims arising out of the contracts made plain but the contracts were read to the jury.
Instruction No. 13 was to the effect that if on or about June 22, 1910, the plaintiff was and had been operating the engines through its engineer Ostedt, they not having been accepted, and such engines, or either of them, were at that time broken or of poor-workmanship or were not in their operations fulfilling the requirements of the contract, then the plaintiff could not at that time tender and require defendant to accept them. It is asserted that this instruction confused tender for acceptance with tender for test, but certainly the plantiff was not harmed by advising the jury that the defendant could not be made to accept engines which were not of the kind contracted for.
In No. 15 the jury were told that the plaintiff requested the test but the defendant refused to make it under the supervision of Beutner and the plaintiff refused to accept some one else, but that the parties-themselves construed this as applied to all engines, for,, just a day or two prior to the bringing of the action,, the plaintiff requested that a test run be made for seventy-two hours and was told that the defendant desired a thirty- or sixty-day test.
“The question then arises, was defendant bound to> make a 72-hour test under the supervision of VictorBeutner, or was there any warrant or right on the part of the defendant to demand a 30- or 60-day test run.?.”'
In the 16th instruction the jury were advised that the parties themselves had eliminated the question of a seventy-two-hour test, and as there was no warrant for the defendant to' demand a thirty- or sixty-day test run, the remaining question was as to the test of the engines as appearing from ordinary operating conditions in connection with the plant. This is said to have brought a new issue into the case which could not have arisen if the seventy-two-hour test was not necessary. Referring to the contract, it will appear that under the one first made the quality of the design and material and the character of the workmanship were to be subject to the inspection and approval of Beutner, and the contractor was to furnish such skilled help as necessary to supervise the erection and assembling of the engines and the pipe work and to operate the installation “until its success is clearly demonstrated and until the engines are accepted and final payment for the same is approved by the owner’s engineer.” Under this contract whoever might be the •engineer at the time was manifestly the one to determine as to acceptance and approval. Under the supplemental contract it was agreed that the plaintiff was to maintain a sufficient force to make any changes, alterations and repairs, etc., “and party of the second part agrees to be guided in this respect both as to the number of mechanics required and to the repair and spare parts necessary to fulfill this agreement by the .judgment of Victor Beutner, the engineer under whose supervision the original contract is to be carried out.” 'Then follow the provisions as to a seventy-two-hour
“It is further agreed that if, by the result of this test, or by the failure of the party of the second part to have the first engine ready for such test within the stipulated time, or by the ordinary operating conditions, it should be demonstrated that the terms of the original contract have not been fulfilled, the party of the first part shall have the right at his own option to notify the party of the second part to remove each or any of the three units,” etc.
This is coupled with the proviso that the defendant should not use the first engine more than two, the second more than four or the third more than six months “after the test has been demonstrated that the guarantee of the original contract has not been fulfilled.”
We think the only result of these various provisions is that the plaintiff contracted to furnish enginés which would do the work specified; that whenever it was demonstrated that they would thus perform it was the duty of the defendant to accept and pay for them; but that after it had been demonstrated that they would not so perform then the defendant could not use the engines more than the lengths of times specified. Not only do the findings fail to show that the use of the engines exceeded the length of time referred to, but there was testimony to show that the engines at no time did the work prescribed without frequent breaks and stoppages causing loss, delay and damage to the operation of the plant. It appears that Beutner left the employ of the defendant and ceased to be its engineer, and we find nothing in the contracts which required either party to rely exclusively upon his judgment as to whether the engines fulfilled the requirements of the supplemental contract.
The jury found that the defendant began using two of the engines about July 1 and the other about the middle of July, 1910; and began repairing the latter
Complaints are made touching certain rulings as to the admission of evidence, but we find no material error therein.
The refusal to require the jury to answer question No. 4 directly and specifically was not materially prejudicial for the reason that the answer given was fairly correct, and for the further reason that the seventy-two-hour test referred to in the question had been, as the trial court instructed, practically eliminated by the parties.
The plaintiff insists that the verdict and judgment are contrary to the evidence and contrary to law; that the conditions were that the engines be completed by the various times agreed upon, that the plaintiff was to be guided with respect to changes and repairs by the judgment of Beutner, that the fulfillment of the contract was to be determined either by a seventy-two-hour test or by trial under ordinary operating conditions, and that all of these prerequisites were complied with by the plaintiff. It is contended that the delay in the completion was caused by the changes suggested by the defendant’s engineer, and that the defendant by its conduct waived completion at the time fixed by the written contracts, and in this counsel are correct. It is submitted, with a claim of support by numerous quotations from the evidence, that the uncontradicted testimony shows that the engines conformed to the specifications, and it is but fair to say that the testimony of Beutner and other witnesses goes far to support this contention. However, the story of the way in which the engine -operated, as detailed by numerous other witnesses who were at the plant and saw the frequent trouble, delay, stoppage and demoralization of
The judgment is affirmed.
Reference
- Full Case Name
- The Wisconsin Engine Company v. The Altoona Portland Cement Company
- Status
- Published
- Syllabus
- SYLLABUS BY THE COURT. 1. Special Findings — Verdict—Judgment. Special findings do not form the basis for a judgment unless inconsistent with the general verdict and consistent with one another. 2. Instructions — Reading Contract to Jury. Instructions which fairly recite the claims and contentions of the parties are not rendered erroneous by reading to the jury the contracts involved in the action. 3. Special Questions Unanswered — Not Prejudicial. A refusal to require the jury to answer a certain question more specifically is not materially prejudicial when such question has already been given a fairly correct answer and when the matter covered by such question has by the parties been eliminated from the controversy. 4. JURY' — Triers of Facts. The jury are the triers of facts, and their verdict reached after considering an abundance of conflicting evidence, and approved by the trial court, must stand.